Loading...
HomeMy WebLinkAboutNB 2 STORM DR PPE 04-18-83APRIL 12, 1983 NEW BUSINESS NO. 2 4-18-83 nter- Corn WILLIAM HUSTON, CITYMANAGER DALE WICK, ASSISTANT CITY ENGINEER AUTHORIZATION TO ISSUE PURCHASE ORDER FOR FURNISHING OF 96"REINFORCED CONCRETE STORM DRAIN PIPE FOR MOULTON PARKWAY FAU PROJECT M-M032(O04) RECOMMENDATION: It is recommended that the City Council, at their meeting of April 18, 1983, authorize staff, subject to project approval by Caltrans/F.H.W.A., to issue a purchase order to Hydro Conduit Corporation of Corona, CA in the amount of $13,790.26 for the purchase of 114 lineal feet of 96" reinforced concrete pipe. BACKGROUND: This project encompasses the manufacturing and delivering to the site of a short segment of the storm drain pipe required for the Moulton Parkway FAU project under the Peters Canyon channel bridge crossing. Due to the short time frame involved for the bridge construction, it is imperative that the contractor for the Moulton Parkway project have the pipe on hand, so that.he can immediately lag the pipe which will enable him to begin construction of the bridge. Since the pipe takes about 6 weeks to manufacture, by having the City order the pipe ahead of time, a six week delay is eliminated. Sealed bids for this work were opened at 10:00 AM on April 12, 1983 and were received as follows: PIPE MANUFACTURER Hydro Conduit Corporation Ampac, Inc. United Concrete Pipe BUSINESS LOCATION Corona, CA Upland, CA Baldwin Park, CA BID $13,790.26 18,145.08 20,199.24 The iow bid is 17.4% below the Engineer's estimate of $16,700.00. The tentative schedule for this work calls for the purchase order to be issued on April 19, 1983 with the pipe to be delivered to the site no later than May 30, 1983. The P.O. will not be issued until the entire project is approved by Caltrans. DALE A. WICK ASSISTANT CITY ENGINEER db CC: Caltrans City Clerk Finance Director