0ATE: MARCH 15, 1983
NEW BUSINESS
NO. 2
3-21-83
TO:
FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
DALE WICK, ASSISTANT CITY ENGINEER
AWARD OF BID FOR F.Y. '82-'83 WATER MAIN REPLACEMENT PROJECTS
RECOMMENDATION:
That the Tustin City Council, at their meeting of March 21, 1983, award the
contract for subject project to Schuler Engineering Corporation of Anaheim, CA in
the amount of $99,199.45.
BACKGROUND:
Subject project encompasses replacement of old, leaking steel water mains at the
following locations:
(1) Olympia & Palomar way S. of Fairhaven Ave.
(2) Nisson Rd. East of Red Hill
(3) Vayano Way West of Red Hill
Bids for subject project were opened on Mrch 15, 1983 at i0:00 AM and were
received as follows:
CONTRACTOR
Schuler Engineering Corp.
S.J. Burkhardt Contracting
J & B Contractors Inc.
Forster Construction
G.R. McKervey Inc.
Loant Construction
MiraMontes Const. Co.
Cariaga & Schmidt
Jan G. Earnest Const. Co.
John T. Malloy Inc.
Brkich Bros. Corp.
R & L Sewer
Jade Construction Co.
Coronada Pipeline
G.R. Frost Inc.
Gabi Construction Co. Inc.
BUSINESS LOCATION
Anaheim, CA
Mira Loma, CA
Crestline, CA
Orange, CA
Irvine, CA
Buena Park, CA
La Puente, CA
Glendale, CA
Anaheim, CA
Los Angeles, CA
E1 Monte, CA
Paramount, CA
Fullerton, CA
Anaheim, CA
Wilmington, CA
La Habra, CA
BID
$ 99,199.45
100,387.90
112,151.49
117,773.14
121.232.40
127,037.50
127,396.85
132,780,84
136,032.30
138.878.50
139.510.20
144.046.23
144.700.55
152210.75
177.105.00
181597.00
The low bid is 32.6~ below the Engineer's estimate of $147,300. There is
presently $138,900.00 budgeted for this work. Remaining budgeted funds will be
utilized by Water Service crews to make the individual house connections to the
new mains.
AWARD OF BID FOR F.Y.
MARCH 15, 1983
PAGE TWO
'82-'83 WATER MAIN REPLACEMENT PROJECTS
Attached for the City Council's information is a tabulation of all bids received.
DALE A. WICK
ASSISTANT CITY ENGINEER
db
Attachment
cc: City Clerk Finance Director
Water Services Manager