Listed below are the actions required to be taken by the Council and Agency
in order to proceed with the South/Central Project Area. Corresponding
dates are also indicated. Unless the Council feels additional information
is necessary, staff recommends that this schedule be utilized in proceeding
with the Council's and Agency's consideration of the formation of the
South/Central Project Area.
A staff report concerning vacancies on the Project Area Committee appointed
by the Council in 1982 will be submitted to the Council prior to its
February 7, 1983 meeting.
DATE ACTION
1/17/83 *
City Council determines to proceed with its
consideration of the project.
2/7/83 *
Council updates and fills vacancies on Project Area
Committee.
2/14/83 *
Committee reviews draft project plan.
2/28/83 *
Committee reviews final project plan and makes
recommendations to RDA.
3/7/83 *
RDA approves plan and submits to Planning Commission
for review.
3/14/83 *
Planning Commission reports to Council and RDA on
conformity of plan with General Plan.
3/17/83 *
3/24/83
3/31/83
4/7/83
Notice of joint Council/RDA hearing on Redevelopment
Project published for 4 successive weeks in the
Tustin News and notice mailed to all property owners
within project area.
3/21/83 *
RDA submits plan and report to City Council.
4/18/83 *
Public hearing on Project Plan and introduction of
ordinance.
512/83 *
6/2/83
Adoption of Ordinance.
Effective Date of Redevelopment Project.
BH: dmt r~