HomeMy WebLinkAboutPH 2 USE PERMIT 81-22 08-03-81UgUSt 3, 1SSI Inter
FROM:
SUBJECT:
Honorable Mayor and City Counctl Members
Community Development Department~g~/
Appeal of Planntng Agency Approval of Use Permit 81-22
RECOHMENDED ACT[ON
Staff recommends that the City Council uphold the July 6, 1981
findings and decision of the Planning Agency approving Use permit
81-2Zby the adoption of Resolution No. 81-91.
BACKGROUND
On'July 6, Ig8I the City Council adopted Ordinance No. 853 thereby
instituting a zone' change-from Retail Commercial' (C-l) to Planned
C~munity Commercial (PC) for the property located at 615 East
First street. Also on July 6, the Planning Agency approved Use
Permit 81-22 which authorlze~the development of a 72 foot tall,
60,000 square foot office structureon the same property.
DISCUSSION
In a letter dated:July 8, i98~, Dr. James A. Padova, on behalf of
Excelsior Associates, filed an application appealing the Planning
Agency decision regarding Use Permit 81-22, "Unresolved issues
that would have impacton the area property owners" was cited as
the basis for appeal. To date no further comments or elaboration
have been brought forth by the appellant.
CONCLUSION.
Staff concludes that:
AlT appropriate measures were taken for and during the JulY
1981 Planning Agency public hearing.
A Negative Declaration for the project has been approved and
filed in accordance with the requirements of the, California
Environmental Quality Act.
Planning Agency. Resolution No. I988 addresses, and provides
mitigating measures for items that may be of concern to the
City of Tustin.
dSO/dar
July 8, 1981
Honorable Chairman and Planning Agency
City of TuStin
Gentlemen:
On behalf of Excelsior Associates, owners of the Vista Grande
Medical/Dental Professional Complex at 18102 Irvine Blvd., in
the City of Tustin, I would like to appeal the decision of
the planning agency for use permit No. 8222 reference the loca-
tion of 615 East First Street, concerning authorization to
construct a five story office building by applicant John W.
Jamison and Associates.
We believe there are unresolved issues that would have impact on
the area property owners.
Re~pectfully/~
JAMES A.. PADOVA, M. D.
Managing Partner
Excelsior Associates
JA~/sb
1
2
3
4
5
6
?
8
9
lO
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION 81-91
A RESOLUTION OF THE CITY COUNCIL OF THE
Oily OF TUSTIN, UPHOLDING THE FINDINGS AND
DECISION OF THE PLANNING AGENCY APPROVING
USE PERMIT 81-22.
The City Council of.the City of Tusttn does hereby resolve as follows:
I. The City Council finds and determines as follows:
Ae
That a proper application, (Use Permit No. 81-22), was filed on
behalf of Far West Savings and Loan Association to request
authorization to develop a 72 foot tall, 60,000 square foot
office structure located at 615 E. First Street.
B. That a public hearing was duly called, noticed and held on said
appl i cati on.
C. That the Planning Agency by the adoption of Resolution No. 1988,
did approve said use permit.
De
That James A. Padova, M.D. on behalf of Excelsior Associates did
file an appeal of the Planning Agency's decision to the City
Council.
E. l~at a public hearing was duly called, noticed, and held on said
appeal.
That the City Council determines that the concerns presented by
appellant are adequately mitigated in the resolution of approval
as adopted by the Planning Agency, and by all pertinent building
and fire codes.
II The City Council hereby upholds the findings and decision of the
Planning Agency as contained in Resolution No. 1988.
PASSED AND ADOPTED at at a regular meeting of the Tusttn City Council,
held on the 3rd day of August, 1981.
ATTEST:
James B. Sharp
Chairman
Mary E. Wynn
City Clerk
,t262 Campus Drive, Suite B-1
BASMACIYAN-DARNELL, INC.
E~GI~E.K~G A~D P~O
Newport Beach, California 92660
(714) 549-9940
June 23, 1981
Mr. John W. Jamieson RBD
445 E1 Camino Real
Saddleback Plaza
Western Building Design
Tustin, CA 92680
Subject: Traffic Report for Far West Savings Office Project on
First Street in the City of Tustin
Dear Mr. Jamieson:
In accordance with your authorization we have prepared this letter
report for the subject project. The report provides a summary of
traffic generation to/from the project area, trip distribution
and review of on-site circulation.
PROJECT DESCRIPTION
Far West savings proposes the construction of a five story office
building to the rear of their existing property located at First
Street. The existing development provides 8500 square feet of gross
floor area and 60,000 square feet of gross floor area is proposed
in the new building. Parking for the project is proposed with at
grade parking and parking within a subterranean parking level. The
location of the project site is depicted on Figure 1.
PROJECT-RELATED TRAFFIC
Trip Generation and Distribution
Trip generation characteristics of the project are summarized in
Table 1. Table 1 provides a s~u~Lary of trip generation rates
anticipated for the office development and a summary of the daily
AM and PM peak hourly traffic volumes to be generated.
JUN P, 4 1981
Mr. John W. Jamieson RBD
june 23, 1981
Page Two
TABLE 1
S~Lm%ary of Trip Generation Characteristics
Trip Generation Rates
Office Use
Daily
AM Peak Hour
In
Out
PM Peak Hour
In
Out
Trip Generation S~LuL~ary
Daily
AM Peak Hour
In
Out
PM Peak Hour
In
Out
12.3 vehicles per 1000 Sq. ft.
1.86 vehicles per 1000 sq. ft.
0.35 vehicles per 1000 sq. ft.
0.60 vehicles per 1000 sq. ft.
1.7 vehicles per 1000 sq. ft.
738 vehicles
112 vehicles
21 vehicles
36 vehicles
102 vehicles
Trip distribution of trip making for the project was estimated and
is depicted on Figure 2. Based on the trip distribution character-
istics shown on Figure 2, the daily, and peak hourly traffic
volumes s~,,arized on Table 1 were then allocated to the surround-
ing street system. The results of this analysis are shown on
Figure 3,
Project-Related Impacts
Existing traffic volumes on First Street and Fashion Lane were
obtained from the City of Tustin and are depicted on Figure 1.
The project related traffic shown on Figure 3 was then added to
the existing traffic volumes shown on Figure 1. The results of
this analysis are depicted on Figure 4.
Based on a review of the anticipated project-related traffic and
the superimposing of project-related traffic on existing traffic
volumes, no capacity and/or congestion problems are anticipated.
4th St
17th B St
N
~OT~TO_SCAL~
(11,150) (8000)
938/1253 e 603/861-
(24,450)
Irvine (1979_2276)
(7150)
481--7~
(10,750) e
917/1208
(2150)
(4100)
318/428
Main
-w~(25,650)
1621/2251
(20,850)
1868/2092
(19,450)
1281/1881
BA.SaaACIYAJ~I DAA~'Ir I.. INC.
XX, XXX Daily Volume
YYY/ZZZ AM Peak/PM Peak Hour Volume
XXX* Noon Peak
(XXXX) .'1980 Volumes
FIGURE 1
LOCATION MAP
!EXISTING 1981 AND TWO-WAY TRAFFIC VOLUMES
4th St
5%
10%,
5%
/t\
10%
17th
5%
Irvine
25%'
St
5%
5%
t ,5'~'
1st'
0
25%~30% St
5% 5%
Main ~,
st
Blvd
40%
P~OJECT
25%
10%
5%
LEGEND
XX% Percentage
FIGURE 2
TRIP DISTRIBUTION
BY
PERCENTAGE
Main o, St
~/zz
Daily Volume
· AM Peak/PM Peak Volume
FIGURE 3
PROJECT-RELATED TRAFfiC '
4th St
St
St
16,200
4400 N/A/1369
N.A./491
St
~/zzz
FIGURE 4
Daily Volume
AM Peak/PM Pesk Volume
EXISTING PLUS
PROJECT-RELATED TRAFFIC VOLUMES
Mr. John W. Jamieson RBD
June 23, 1981
Page Three
ACCESS AND ON-SITE CIRCULATION
Access
Access to/from the project site has been reviewed and determined
to be adequate for the existing and proposed office building.
On-Site Circulation
On-site circulation within the project site has been reviewed and
has been determined to be adequate except for access to the under-
ground parking. Access to/from the underground parking enters the
main aisleway for the project at an angle. Although this angle
is not critical, a minor adjustment is recommended. To minimize
this angle we would suggest that the curb returns for the angle
portion of the access be increased in size. This minor adjustment
will allow for painting a double yellow centerline and curving
the centerline to provide a better angle entering and leaving the
underground parking. In addition the increase in curb radius will
improve the turning radius for vehicles leaving and entering the
parking structure.
Traffic Control
On-site circulation has been reviewed in terms of the need for on-
site traffic control. After reviewing the on-site circulation
patterns we would recommend that stop signs be installed at each
exit from the parking structure. The installation of the stop
signs will provide for positive control at these access locations.
In addition it is recommended that stop signs be installed at
the driveway exiting onto First Street and Fashion Lane.
SUMMARY
The proposed development of 60,000 square feet of office
is expected to generate 738 daily vehicle trip ends, 133
AM. peak hour trip ends (112 inbound and 21 outbound),
138 PM Peak hour trip ends (36 inbound and 102 outbound).
When project-related traffic is added to existing traffic
no capacity and/or congestion problems would be created
on First Street or Fashion Lane.
The access locations proposed for the project are adequate
to accommodate the anticipated traffic generated to/from
the project.
On-site circulation has been reviewed and determined to'
be adequate except for recommended minor adjustments to the
underground parking entrances.
Mr. John W. Jamieson RBD
June 23, 1981
Page Four
At the entrances to the underground parking, minor
adjustments should be made to the curb return radius
at the acute angle side of the structure access. It
is recommended that the curb return radii be increased
in size and a double yellow centerline be painted with
a curvature creating a less acute angle.
* Stop signs are recommended to be placed at the exit
from the underground, parking and at the driveways
entering First Street and Fashion Lane.
Please call me if you have any questions and or need additional
information.
Sincerely,
BASMACIYAN-~RNELLa,~ INC.
Bill E. Darnell, P.E.
ddf