HomeMy WebLinkAboutRDA 5 PKG REQUIRE'S 06-01-81DATE:
June 1, 1981
~U_E!hU~)PMENT AGENCY
NO. 5
6-1
Inter Corn
TO:
FROM:
SUBJECT:
Chairman and Members of Redevelopment Agency
Community Development Department
Parking Requirements, Redevelopment District (190 E1Camino Real)
BACKGROUND
The Redevelopment Agency on May 18, 1981 considered a request to
waive the requirement for 9 on-site parking spaces pursuant to
Ordinance No. 510.
Action was continued until i June, 1981, for more information
pertaining to the status of public parking accommodations. The
previous parking study report is attached for agency review.
The proposal submitted for prelimina~ review would authorize the
development of a commercial and professional building on two
parcels totaling 7,000 sq. ft. (140' x 50') on the northwesterly
corner of E1Camino Real and Second Street. The proposal provides
13 on-site ground level parking spaces. Full development of the
site would require an additional + 9 spaces.
DISCUSSION
Under the provisions of Ordinance No. 510 Section g3(c) parking
spaces may be waived by contributing funds toward the acquisition
and development of public parking. It has been the general policy
of staff to utilize this provision only in the case of expanding
existing businesses, and not for new construction. The basic
reasoning for this policy is that the fee structure in Section
g3(c) is not sufficient to pay for acquiring and constructing
public parking. In addition, existing structures are usually
limited in expanding on-site parking, whereas new construction can
incorporate on-site parking as part of the design.
The applicant has a preliminary proposal which calls for retail
uses on the first floor, with offices on the second floor. The
preliminary plans have sufficient parking to support the
improvements. The breakdown is:
1st Floor 1050 sq. ft. retail
2nd Floor 2280 sq. ft. office
5.25 parking spaces
7.60 parking spaces
Parking Requirements, Redevelopment
District (190 E1Camino Real)
June 1, 1981
Page Two
Total 3,330 sq. ft.
12.85 spaces.
The nine parking spaces purchased from the redevelopment agency
would serve additional office space on the second floor. The
preliminary plan shows that the second floor has not been developed
to its full potential, and further expansion than indicated is
possible.
Enclosed is a copy of the parking study and subsequent memo. The
study indicates that the parking situation is this area of the
downtown is deficient, with several existing uses supplying no
on-site parking. These businesses either utilize the parking
facilities on the corner of "C" Street and Second Street, or
on-street parking. Without public parking, waiving additional
spaces will only further aggravate the present situation.
In the immediate area, though, is an excellent site to locate
public parking. The Tustin School District property represents a
site that can be utilized for public parking for existing
developments as well as new development. Staff has contacted Larry
Sutherland at the School District, and his immediate response was
very positive for a lease with option to purchase at a future
date. Staff will begin the process to secure the property for
public parking, and hopefully within a short period of time: staff
can present to the Council a concrete proposal.
Based upon previous actions of the Agency, parking requirements
would not be waived until the following actions take place:
1. The fee for waiving parking has been changed to reflect the
real cost of acquiring and constructing parking. An option to
lease parking or a pro-rated purchase of parking spaces could
also be considered.
2. The public parking located on the Tustin School District
property is either constucted or to the point that construction
is assured.
The applicant should continue to process the plans that were
submitted to staff, which is a new structure of 3,300 square feet
with thirteen spaces required. If in the future, the above two
items are completed, the applicant could purchase additional spaces
for the construction of more office space.
Parking Requirements, Redevelopment
District (190 E1Camino Real)
June 1, 1981
Pa9e Three
ALTERNATIVES
The following alternative actions are available to the
Redevelopment Agency, based upon the prevailing philosophy of the
Agency as related to parking accommodations:
Authorize constr~ction and full utilization of the 7,000 sq.
ft. parcel by providing 13 on-site parking spaces and
contributing to public parking pursuant to Ordinance No. 510.
2. Deny a waiver of any on-site parking requirements for new
construction.
Authorize the design of the project for full utilization but
deny occupancy of 2,700 sq. ft. of the building until such time
as Ordinance No. 510 has been revised to amend the cost
schedule for off-site parking and the Agency has entered into
an agreement to provide public parking facilities in the area.
Approve the concept of a 3,330 sq. ft. structure with 13
on-site parking with the applicant having the opportunity to
amend the plans at a later date to expand the building area
when public parking is available.
RECOMMENDED ACTION
Alternatives 3 or 4 at the option of the applicant, are recommended
for Agency approval.
EMK/dat