IvLAY 12, 1980
REDEVELOPMENT AGENCY
NO. 5 -
5~19-80
Inter-Corn
DAN BLANKENSHIP, EXECUTIVE DIRECTOR,
TUSTIN COMMUNITY REDEVELOPMENT AGENCY
BOB LEDENDECKER, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
AWARD OF BID-FIRST STREET MEDIAN ISLAND MODIFICATION
This project consists of the modification of the median island at 245 East
First to provide a protected left turn pocket in accordance with City Council
approval on April 7, 1980, and Redevelopment Agency approval on April 21, 1980.
Bids were opened for this project on May 9, 1980, at ll:O0 a.m. and were re-
ceived as follows:
CONTRACTOR BID
Hardy and Harper, Inc., Tustin, CA.
Sully Miller Contr. Co., Orange, Ca.
Frontier Conc. Const., Wrightwood, Ca.
Nobest, Inc., Westminster, Ca.
$ 8,141.55
10,657.00
11,990.00
12,228.00
The low bid is 17% over the engineer's estimate of $6,953.50. Due to the nature
and scope of this project, staff feels the low bid is reasonable and no reduction
of prices could be gained by re-bidding. Attached for the City Council's in-
formation is a tabulation of all bids received.
RECOMMENDATION
It is recommended that the Tustin Community Redevelopment Agency, at their
meeting of May 19, 1980, award the contract for the first Street Median Island
Modification to Hardy and Harper, Inc., of Tustin, California.
Bob Ledendecker
Director of Public Works/ City Engineer
BL/hlr