HomeMy WebLinkAboutNB 4 VARIOUS PROJ'S 04-21-80DATE: APRIL ll, 1980
NEW BUSINESS
No. 4
4-21-80
Inter-Corn
TO:
FROM:
DAN BLANKENSHIP, CITY ADMINISTRATOR
DALE WICK, ASSISTANT CITY ENGINEER
SUBJECT: AWARD OF BID FOR:
PROJECT I - MAIN STREET SIDEWALK CONSTRUCTION
PROJECT II- PROSPECT AVENUE SIDEWALK CONSTRUCTION
Project I provides for construction of a pedestrian walkway along the north side of
Main Street from Williams Street through the freeway underpass and terminating at
the entrance to St. Jeanne de Lestonnac School. To accomplish this requires con-
struction of 300'± of retaining wall and 520'± of 5' high chain link fence within
the freeway underpass. The fence is necessary to protect children and pedestrians
due to the fact only a 3.0' wide sidewalk is possible within the underpass.
Project II provides for construction of sidewalk along the west side of Prospect
Avenue from 100'± north of First Street to Lockwood Park Place.
Bids were opened for this project on April ll, 1980 at ll:O0 A.M., and were received
as follows:
CONTRACTOR TOTAL BID
B.J. Construction Co of Monterey Park, CA
Fleming Engineering Inc. of Cerritos, CA
Damon Construction Co. of South Gate, CA
Granstrom Construction Inc. of Gardena, CA
$27,317.60
$28,308.15
$32,482.90
$33,213.00
The low bid is 24% over the Engineer's estimate of $21,989.90. There is presently
$26,000.00 budgeted for Project I and $2,000.00 for Project II for a total of
$28,000.00. Attached for the City Council's information is a tabulation of all
bids received.
RECOMMENDATION:
It is recommended that the Tustin City Council, at their meeting of April 21, 1980,
award the contract for Project I-Main Street Sidewalk Construction and Project II-
Prospect Avenue Sidewalk Construction to B.J. Construction Company of Monterey Park,
Cal i fornia.
DALE A. WICK
Assistant City Engineer
DAW:rvm
Attachments
CC:
City C1 erk
Finance Director