HomeMy WebLinkAboutWALNUT AVE. WIDENING 04-21-80DATE:
APRIL 21, 1980
Inter-Corn
TO:
FROH:
SUBJECT:
DAN BLANKENSHIP, CITY ADMINISTRATOR
DALE WICK, ASSISTANT CITY ENGINEER
AWARD OF BID FOR WALNUT AVENUE WIDENING FROM RED HILL AVENUE TO 600'~
EASTERLY
This project provides for the widening of Walnut Avenue on the northerly side
(adjacent to the Nisson Parcel) from Red Hill Avenue to 600'± easterly. The
construction will consist of adding an additional westbound travel lane in ac-
cordance with City Council approval at their meeting of March 3, 1980.
Bids were opened for this project on April 21, 1980 at lO:O0 A.M. and were re-
ceived as follows:
CONTRACTOR BID
Hardy & Harper, Inc., Tustin, CA
Porter Construction Co., Santa Ana, CA
Calex Paving Co., Long Beach, CA
Sully-Miller Contracting Co., Orange, CA
Jerry Cross Paving Co. Inc., Costa Mesa, CA
R.J. Noble Co., Orange, CA
$19,644.18
21,673.00
23,269.00
24,672,00
25,081.50
28,455.36
The low bid is 6.4% below the Engineer's estimate of $20,997.50. There is pre-
sently $44,000.00 budgeted for this work. Attached for the City Council's in-
formation is a tabulation of all bids received.
RECOMMENDATION:
It is recommended that the Tustin City Council, at their meeting of April 21,
1980. award the contract for Walnut Avenue Widening from Red Hill Avenue to
600'+- Easterly to Hardy & Harper, Inc., of Tustin, California.
DALE A. WICK
ASSISTANT CITY ENGINEER
DAW:rvm
Attachn~nt
cc: City Clerk
Finance Director
Hugh West