The original Community Development Block Grant Program Contract executed in 1975
delineated the curb and gutter improvements in the town center area to be on E1
Camino Real in lieu of "B" Street between Second and Third Streets. There are no
missing curbs and gutters on E1Camino~Real as indicated, but the intent of the
project was to be at various locations throughout the El Camino Real Town Center
area.
The County Housing and Community Development Office has indicated that the con-
tract must be revised to reflect the "B" Street curb and gutter improvements in
lieu of the E1Camino Real area. A revised contract is being prepared by the
County and will be distributed to the City Council at their meeting of February 4,
1980. This matter was only discovered by the County last Friday, January 22nd.
Time is of the essence in executing this project because a construction contract
has already been awarded and the contractor will be ready to commence work as soon
as a "Notice to Proceed" is issued to his firm.
This document is a routine contract which has been previously approved and execu-
ted by the City, and it is only revising the location of the project.
RECOMMENDATION:
It is recommended that the Tustin City Council at their meeting of February 4,
1980, authorize the Mayor to execute the revised Community Development Block
Grant Program Contract for the "B" Street Curb and Gutter Improvements.