AGENDA REPORT Reviewed:
City Manager
Finance Director
MEETING DATE: MAY 16, 2017
TO: JEFFREY C. PARKER, CITY MANAGER
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE
ADVERTISEMENT FOR BIDS FOR THE MOFFETT DRIVE (CIP NO. 70230)
AND LEGACY ROAD (CIP NO. 70231) EXTENSION ROADWAY
CONSTRUCTION PROJECT
SUMMARY
The plans and specifications for the Moffett Drive (CIP No. 70230) and Legacy Road (CIP No.
70231) Extension Roadway Construction Project have been prepared and the project is ready to
be bid.
RECOMMENDATION
It is recommended that the City Council:
Adopt Resolution No. 17-08 approving the plans and specifications for the Moffett Drive
(CIP No. 70230) and Legacy Road (CIP No. 70231) Extension Roadway Construction
Project; and
2. Authorize the City Clerk to advertise to receive bids.
FISCAL IMPACT
Sufficient funds have been budgeted and appropriated in this Fiscal Year 2016-2017 Capital
Improvement Program for the Moffett Drive (CIP No. 70230) and Legacy Road (CIP No. 70231)
Extension Roadway Construction Project. The engineer's estimate for the project is $9,500,000.
Approximately $1,200,000 is estimated to be reimbursable from the Irvine Ranch Water District
for installation of their capital facilities. The project is funded through a combination of Legacy
Community Facility District Funds and Land Sale Proceeds.
Also pursuant to the First Amendment to the Site Conveyance Agreement executed on October
18, 2016 between the City and Tustin Unified School District (TUSD) for the transfer and
grading of a 40 -acre site upon which TUSD proposes to construct the 6-12 Legacy Magnet
School, the City will be reimbursed, without interest, for the road construction and improvements
provided funds are available for reimbursement. Reimbursement, if any, shall occur after the
construction of the 6-12 Legacy Magnet School and after the expansion of the Heritage School.
Reimbursement for Moffett Drive from the TUSD drive easement to Tustin Ranch Road shall be
in the amount of 8.8% of the cost of construction representing the agreed upon price for the
acquisition of a private drive easement and the pro rata share of the cost of construction based
upon traffic impacts generated by the school project. Reimbursement for Legacy Road from
Valencia Avenue to the TUSD 40 -acre southerly property line shall be in the amount of 9.8%
assuming Legacy Road is extended further by the City as a public road southerly to Warner
Plans and Specifications Approval for Moffett Drive and Legacy Road Extension
May 16, 2017
Page 2
Avenue. If Legacy Road is not extended further as a public road then reimbursement shall be in
the amount of 100% as it would serve the school project only.
CORRELATION TO THE STRATEGIC PLAN
The construction of Moffett Drive from future Legacy Road to Park Avenue and Legacy Road
from Valencia Avenue to future Moffett Drive contributes to the fulfillment of the City's Strategic
Plan Goal A: Economic and Neighborhood Development. Specifically, the project
implementation of Strategy 1, which among other items, is to develop critical phases of Tustin
Legacy.
DISCUSSION AND BACKGROUND
On August 25, 2015 the City of Tustin and TUSD entered into a Site Conveyance Agreement for
the eventual construction of the Legacy Magnet School. On October 18, 2016 the First
Amendment to that Site Conveyance Agreement was entered into by the parties which
stipulated among other things that the Moffett Drive and Legacy Road extensions would be
constructed including all utility connections and to provide construction access for TUSD by
August 31, 2018 or such other time as agreed to by the parties. Pursuant to the requirements of
the Site Conveyance Agreement, an as -graded certification and as -graded geotechnical report
for the 40 -acre site were transmitted to TUSD on May 1, 2017.
The Moffett Drive work from future Legacy Road to Park Avenue and Legacy Road work from
Valencia Avenue to future Moffett Drive consist of clearing and grubbing, construction of
underground utility work, roadway improvements and traffic signals installation. This work
according to the tentative schedule below allows the City to continue to meet its obligations to
TUSD for the Legacy Magnet School.
The tentative schedule for construction of the project is as follows:
• Authorization to Advertise for Bids .............................
• First Legal Advertisement ..........................................
• Second Legal Advertisement .....................................
• Bid Opening..............................................................
• Tentative Award of Contract ......................................
• Tentative Start Construction .....................................
• Estimated Completion of Construction .......................
Dougla. Stack, P.E.
Dir for of Public Works/City Engineer
Attachment 1: Resolution No. 17-08
Attachment 2: Location Map
...........................05/16/2017
...........................05/25/2017
...........................06/01 /2017
...........................06/27/2017
........................... 07/18/2017
........................... 08/14/2017
...........................06/01 /2018
QlUsems dstacktAppDala\Loc RMicrosaff\Wndows\Tempomry Intemet FileslComent.OullooklULT2ZMF01Approve PS for Moflell Ddve (70230) Legacy Road (70231) Exlension.docx
ATTACHMENT 1
Resolution No. 17-08
RESOLUTION NO. 17-08
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA APPROVING PLANS AND SPECIFICATIONS FOR THE
MOFFETT DRIVE (CIP NO. 70230) AND LEGACY ROAD (CIP NO. 70231)
EXTENSION ROADWAY CONSTRUCTION PROJECT AND AUTHORIZING
ADVERTISEMENT FOR BIDS
WHEREAS, it is the intention of the City Council of the City of Tustin, California to
contract for the construction of the Moffett Drive (CIP No. 70230) from future Legacy Road to
Park Avenue and Legacy Road (CIP No. 70231) from Valencia Avenue to future Moffett Drive
Extension Roadway Construction Project; and
WHEREAS, the City Engineer has presented plans and specifications for the
construction of said work; and
WHEREAS, on January 16, 2001, the City of Tustin certified the Program Final
Environmental Impact Statement/Environmental Impact Report (FEIS/EIR) for the reuse and
disposal of MCAS Tustin. On December 6, 2004, the City Council adopted Resolution No. 04-
76, approving a Supplement to the FEIS/EIR for the extension of Tustin Ranch Road between
Walnut Avenue and the future alignment of Valencia North Loop Road. On April 3, 2006, the
City Council adopted Resolution No. 06-43 approving an Addendum to the FEIS/EIR. On May
13, 2013, the City Council adopted Resolution No. 13-32 approving the 2nd Addendum to the
FEIS/EIR. The FEIS/EIR along with its Addendums and Supplement is a program EIR under the
California Environmental Quality Act (CEQA). The FEIS/EIR, Addendum and Supplement
considered the potential environmental impacts associated with development on the former
Marine Corps Air Station, Tustin; and
WHEREAS, an environmental checklist was prepared and certified by the City Council
through Resolution Nos. 15-16 and 16-35 for the proposed project that concluded no additional
environmental impacts would occur from approval of the project. The Environmental Analysis
Checklist concludes that it can be seen with certainty that there is no possibility that the activity
in question may have a significant effect on the environment because all potentially significant
effects 1) have been analyzed adequately in an earlier EIR pursuant to applicable standards,
and 2) have avoided or mitigated pursuant to that earlier EIR, including revisions or mitigation
measures that are imposed upon the proposed project; and
NOW, THEREFORE, BE IT RESOLVED that the plans and specifications presented by
the City Engineer are hereby approved as the plans and specifications for:
Moffett Drive (CIP No. 70230) and Legacy Road (CIP No. 70231) Extension Roadway
Construction Project
BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to
advertise as required by law for the receipt of sealed bids or proposals for the performance of
the work specified in the aforesaid plans and specifications;
PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin
held on the 16th day of May 2017.
Dr. Allan Bernstein
Mayor
ATTEST:
Erica N. Rabe, City Clerk
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS
CITY OF TUSTIN )
I, Erica N. Rabe, City Clerk and ex -officio Clerk of the City Council of the City of Tustin,
California, do hereby certify that the whole number of the members of the City Council is five;
that the above and foregoing Resolution No. 17-08 was duly and regularly passed and adopted
at a regular meeting of the City Council held on the 16`h day of May 2017 by the following vote:
COUNCILMEMBER AYES:
COUNCILMEMBER NOES:
COUNCILMEMBER ABSTAINED:
COUNCILMEMBER ABSENT:
Erica N. Rabe,
City Clerk
ATTACHMENT 2
Location Map
LOCATION MAP
Moffett Drive and Legacy Road
Extension Roadway
Construction Project
TUSTIN
PROJECT LOCATION
Moffett Drive (CIP No. 70230)
and Legacy Road (CIP No.
70231) Extension Roadways
Construction Project
FlLE: Moffett k Legacy Extension CIP 70230 h 70231.dwg
TUsnN
RANCH
LALe'1pq 1„
MOFFETT DRIVE
L PROJECT
LOCATK
NA