HomeMy WebLinkAbout13 CIP 7130 EDINGER SMART ST. 03-06-07
AGENDA REPORT
Agenda Item 13
Reviewed:
City Manager
Finance Director
MEETING DATE: MARCH 6,2007
TO: WilliAM A. HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AMENDMENT NO.2 TO CONSULTANT SERVICES AGREEMENT WITH
JACOBS CIVil, INC., FOR ADDITIONAL CONSTRUCTION
MANAGEMENT SERVICES FOR THE NEWPORT AVENUE
EXTENSION/SR-55 RAMP RECONFIGURATION PROJECT (CIP NO.
7130), AND THE EDINGER AVENUE (SMART STREET) WIDENING
PROJECT FROM SR-55 TO ,1400 FEET EAST OF RED Hill AVENUE
(CIP NO. 7147) IN. THE CITY OF T.USTIN .AND FROM RITCHEY
STREET TO SR-55 (CIP NO. 2585) IN THE CITY OF SANTA ANA'
SUMMARY
Amendment No. 2 to the Consultant Services Agreement between the' City' and Jacobs
Civil, Inc. will provide additional Construction Management Services for the Newport
Avenue Extension/SR-55 Ramp Reconfiguration Project (CIP No. 7130) and the Edinger
Avenue (Smart Street) Widening Project (CIP No. 7147 in the City of Tustin and CIP No.
2585 in the City of Santa Ana).
RECOMMENDATION
It is recommended that the City Council approve Amendment No. 2 to the Consultant
Services Agreement with Jacobs Civil, Inc. (Jacobs) to provide additional Construction
Management Services for the Newport Avenue Extension/SR-55 Ramp Reconfiguration
Project (CIP No. 7130) and the Edinger Avenue (Smart Street) Widening Project (CIP No.
7147 in the City of Tustin and CIP No. 2585 in the City of Santa Ana) and authorize the
Mayor and City Clerk to execute the Amendment on behalf of the City.
FISCAL IMPACT
In the FY 2006-2007 Capital Improvement Program budget there is project funding of
$13,787,451 in the Newport Avenue/SR-55 Ramp Reconfiguration Project (CIP No. 7130)
and $6,917,254 in the Edinger Avenue Widening Project (CIP No. 7147). The original
combined construction budget for both projects (FY 2005-2006) was $26,787,134.
Amendment No.2 is in the amount of $1,251 ,839.91 and there is sufficient funding to cover
this cost. However, it is anticipated that an additional budget appropriation will be necessary
to complete construction of both projects. This request will be made as part of the Fiscal
Year 2007-2008 Capital Improvement Program budget process. Additionally, a portion of
the Amendment No.2 cost, estimated at $526,000, will be reimbursed by OCTA under the
Measure "M" "Smart Street" program.
Amendment No.2 to Consultant Services Agreement with Jacobs Civil, Inc., for Additional
Construction Management Services for the Newport Avenue Extension/SR-55 Ramp
Reconfiguration Project (CIP No. 7130), and the Edinger Avenue (Smart Street) Widening
Project from SR-55 to 1400 feet east of Red Hill Avenue (CIP No. 7147) in the City of
Tustin and from Ritchey Street to SR-55 (CIP No. 2585) in the City of Santa Ana
March 6, 2007
Page 2
BACKGROUND
On December 1, 2003, the City Council approved a Consultant Services Agreement in the
not to exceed amount of $2,035,000 with Jacobs for the Newport Avenue Extension/SR-55
Ramp Reconfiguration Project (CIP No. 7130) and the Edinger Avenue (Smart Street)
Widening Project (CIP No. 7147 in the City of Tustin and CIP No. 2585 in the City of Santa
Ana). Several full-time personnel including a Resident Engineer, Office Engineer, Highway
Inspector and Administrative Assistant were originally assigned to staff the project. A
Utilities Inspector was also used to supplement the Highway Inspector during periods when
existing utilities were relocated underground or when new facilities were added.
Additionally, the ,above construction _management team was supplemented with other staff to
perform public outreach activities, materials testing, construction survey 'support, cost
analyst functions, scheduling, quality control, and safety activities.
Another important feature of the services to be performed was a constructability review prior
to soliciting bid~. Since the two subject projects were designed by two different engineering
firms, and both sets of contract documents were combined into one construction contract, it
was imperative that both sets of documents be compatible. Jacobs conducted a
constructability review of the two sets of documents as they related to construction details,
traffic control and staged construction, multi-agency coordination, disruptions to the public
and utility coordination before combining the two sets of documents into one construction
contract for bidding purposes.
Construction started in November 2005 and has progressed smoothly. Jacobs was required
to have a public outreach program and they have done an excellent job updating the City's
website which includes the latest information that may affect the motoring public. Night work
is scheduled, when possible, to further reduce the inconvenience to motorists and the
adjacent businesses. Their efforts in meeting with the adjacent 'businesses to coordinate
the contractor's work schedule has resulted in very few questions or complaints.
The personnel assigned by Jacobs to the City for the subject projects have performed quite
well. The Resident Engineer has been very pro-active in recognizing potential construction
problems and resolving issues in an expedited manner and with a cost savings approach.
There have been several unforeseen construction issues, including very poor soil conditions
in Valencia Avenue, major utility conflicts in Edinger Avenue and Red Hill Avenue, and some
delay due to working around existing utility poles. Jacobs has been very responsive in
dealing with these issues. Jacobs has also kept public complaints to a minimum with their
public outreach efforts.
However, due to the circumstances beyond the control of Jacobs, additional services are
required from them. Below is a list of the significant impacts that have affected Jacobs
staffing:
Amendment No.2 to Consultant Services Agreement with Jacobs Civil, Inc., for Additional
Construction Management Services for the Newport Avenue Extension/SR-55 Ramp
Reconfiguration Project (CIP No. 7130), and the Edinger Avenue (Smart Street) Widening
Project from SR-55 to 1400 feet east of Red Hill Avenue (CIP No. 7147) in the City of
Tustin and from Ritchey Street to SR-55 (CIP No. 2585) in the City of Santa Ana
March 6, 2007
Page 3
. Jacobs' original cost proposal and approved budget was based on 18 months for
construction. However, because of the complicated coordination efforts required of
the contractor, such as coordination with Caltrans on the ramp reconstruction and
with the Southern California Edison Company with undergrounding the existing
overhead utilities, the specifications were written to give the contractor 24 months
to construct the project. This extends the amount of time required for construction
management services.
. As a result of delays attributed to the Caltrans permitting process and acquisition of
required right-of-way, the project did not begi,n until November 2005 instead of the
anticipated start date of April 2004. Cost of living adjustments occurred during this
time period for Jacob's labor rate and the amendment covers these' costs.
. Jacobs' Notice to Proceed was given on December 11, 2003 in anticipation of a April
2004 construction start date. Due to the delay in beginning the "project and
requests for additional work to be performed- by the City, preconstruction service
hours totaled 1,162, exceeding the original' 880 hour budget. During this period of
time, Jacobs attended utility coordination meetings, attended meetings with
Caltrans to resolve their design issues, performed additional review of plans and
specifications made at the request of Caltrans and other agencies, and performed
a second check of the revised Engineer's estimate. These functions were outside
of their original scope of work.
. Jacobs was requested to provide a supplemental geotechnical investigation for
Valencia Avenue and Newport Avenue to provide subsurface information for the
proposed sanitary sewer and storm drain installation. During construction of the
sanitary sewer improvements, groundwater and extremely poor soil conditions
caused the new facilities to settle more than allowable. A second investigation was
necessary to try and determine why settling was occurring and re-design the
bedding for the sanitary sewer improvements. These investigations were outside
of the original scope of work.
. The City was requested to procure the services of the California Highway Patrol
during major freeway lane closures on SR-55. Jacobs agreed to coordinate and
provide these services. This work was not in the original scope of work.
· Jacobs has performed design services for the fire service line modification at 15171
Del Arno Avenue. This work was not in the original scope of work. It was
discovered that the property owner had constructed fire service improvements on
their property but within the future Del Amo Avenue City right-of-way acquired for
CIP No. 7130.
· Additional personnel have been employed on the project to perform administration
and inspection work due to the complicated nature of construction phasing
required for the project.
Amendment No.2 to Consultant Services Agreement with Jacobs Civil, Inc., for Additional
Construction Management Services for the Newport Avenue Extension/SR-55 Ramp
Reconfiguration Project (CIP No. 7130), and the Edinger Avenue (Smart Street) Widening
Project from SR-55 to 1400 feet east of Red Hill Avenue (CIP No. 7147) in the City of
Tustin and from Ritchey Street to SR-55 (CIP No. 2585) in the City of Santa Ana
March 6, 2007
Page 4
Based on the additional scope of services outlined above, Jacobs has submitted a request
for additional compensation in the amount of $1 ,252,839.91. Staff has reviewed Jacob's
request and found it to be fair and reasonable based upon the significant amount of work
they are expected to perform. It is, therefore, recommended that the City Council approve
Amendment No. 2 to the Consulting Services Agreement with Jacobs Civil, Inc. for the
Newport Avenue Extension/SR-55 Ramp Reconfiguration Project (CIP No. 7130) and the
Edinger Avenue (Smart Street) Widening Project (CIP No. 7147 in the City of Tustin and CIP
No. 2585 in the City of Santa Ana). The City Attorney has reviewed the amendment and
has signed it "Approved As To Form".
Dana R. Kasdan
Engineering Se'rvices Manager
C7;:::;O ~
,Tim D. .Serlet
Director of Public Works/City Engineer
~
Attachment: Amendment No.2
S:\Councilltems\2007\Ament #2 to CSA with Jacobs CIP 7130.doc.
AMENDMENT NO.2
TO
CONSULTANT SERVICES AGREEMENT
THIS AMENDMENT NO. 2 TO CONSULTANT SERVICES AGREEMENT
("Amendment No.2") is made and entered into this day of , 2007,
by and between the CITY OF TUSTIN, a municipal corporation, hereinafter referred to
as "City", and JACOBS CIVil, INC. a. Missouri corporation, hereinafter referred to as
"Consultant. "
RECIT ALS
WHEREAS, City and Consultant entered into the Consultant Services Agreement
dated December 1, 2003, (the "Agreement") for professional construction management
services for the Newport Avenue/SR-55 Ramp Reconfiguration Project (CIP No. 7130)
and the Edinger Avenue Widening Project (CIP No. 7147); and
WHEREAS, City and Consultant desire to amend Section 4 of the Agreement to
include additional professional construction management services for the Newport
Avenue/SR-55 Ramp Reconfiguration Project (CIP No. 7130) and the Edinger Avenue
Widening Project (CIP No. 7147).
NOW, THEREFORE, in consideration of the mutual promises, covenants, and
conditions contained herein, and upon the terms and conditions hereinafter set forth, the
parties agree as follows:
AGREEMENT
1. Section 4. ComDensation, of the Agreement is hereby amended in its entirety
to read as follows:
A. The compensation to be paid under this Agreement shall be
as set forth in Exhibit "B" to the Agreement dated December
1 , 2003 and the letter from Jacobs Civil, Inc. dated
December 20, 2006, attached hereto, which shall not exceed
a total cost of $3,286,839.91.
B. Consultant shall submit detailed invoices, based upon the
actual work performed, accompanied by backup
documentation as requested by the City.
1
C. Progress payments for work completed shall be paid by the
City as the work progresses, within thirty (30) days of receipt
of Consultant's invoice.
D. Consultant shall provide City with a monthly itemization of all
work performed, and the fees accrued thereon, in complete
and sufficient detail to fully apprise City thereof.
E. City shall notify Consultant within ten (10) business days
after receipt of an invoice if it disputes all or some element of
the invoice. City and Consultant shall promptly attempt to
effect a resolution of any dispute. Not withstanding the
foregoing, City shall pay the undisputed portion of any
invoice.
2. Except as expressly amended herein, all other provisions of the Agreement
remain in full force and effect.
IN WITNESS WHEREOF, this Amendment No.2 was executed by the parties on the
day and year written above.
"CITY"
CITY OF TUSTIN
Lou Bone, Mayor
ATTEST:
Pamela Stoker, City Clerk
APP~ftf16 AS TO FfrM:
11irAI/~/ {/
Do~~ti'(~!f;~~;;;~::y
I
/
"CONSUL TANT"
JACOBS CIVil, INC
/' ,/
.~ t
\. /,(' L.... ~'.~"'.:~
~\-...,~':,. - -f
'.~ '. ..,- ; / <~f;; ",- .... : ,-' '/
SherrySweltzet, Vice President
S:\CSA & RFP\2006\Amend # 2 CSA 7130 Jacobs.doc
2