HomeMy WebLinkAbout16 APPV SPECS & PLANS-LIBRARY PROJ 09-04-07
AGENDA REPORT
Agenda Item
Reviewed:
City Manager
Finance Director
16
~,
MEETING DATE: SEPTEMBER 4, 2007
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: CHRISTINE A. SHINGLETON, ASSISTANT CITY MANAGER
SUBJECT: APPROVAL OF PRE-QUALIFIED GENERAL CONTRACTORS AND
APPROVAL OF PLANS AND SPECIFICATIONS AND AUTHORIZATION TO
ADVERTISE FOR BIDS FOR THE TUSTIN LIBRARY PROJECT
(CIP NO. 1045)
SUMMARY
The general contractors for the Tustin Library Project (CIP No. 1045) have been pre-qualified
and are ready to be approved as eligible to bid the project.
The plans and specifications for the Tustin Library Project (CIP No. 1045) have been
prepared and bids may be solicited from the list of pre-qualified general contractors.
RECOMMENDATION
It is recommended that the City Council:
1. Approve the list of pre-qualified general contractors as identified in Exhibit "A" as eligible
general contractors to bid the project.
2. Adopt Resolution No. 07-69, approving the plans and specifications for the Tustin Library
Project (CIP No. 1045), and authorizing and directing the City Clerk to advertise for bids
and solicit bids from the approved list of pre-qualified general contractors only.
FISCAL IMPACT
The Fiscal Year 2007-2008 Capital Improvement Program (CIP) Budget for the Tustin Library
Project provides total remaining funding for the project of $21,588,428 which includes
remaining architectural and engineering costs, acquisition expenses, project construction
management costs, geotechnical services, reprographics, construction and Furnishings,
Fixtures and Equipment (FF&E). Plans and specifications for the Project include construction
and certain FF&E items; additional FF&E items will be separately bid. The total costs for the
project including all past and future expenditures are projected to be $29,234,676. The
engineer's estimate for the work covered by the plans, specifications and bid documents is
$16,200,000. A more thorough budget analysis will be provided to the City Council with any
future recommendation to award the construction bid.
Approval of Pre-qualified General Contractors and Approval of Plans and Specifications and
Authorization to Advertise for Bids and the Tustin Library Project (CIP No. 1045)
September 4, 2007
Page 2
DISCUSSION
The tentative schedule for construction of the projects is as follows:
City Council Authorization to Advertise for Bids ................................... 09/04/2007
First Legal Advertisement ..................................................................... 09/06/2007
Second Legal Advertisement ............................................................... 09/20/2007
Bid Opening ......................................................................................... 10/25/2007
Award of Contract ................................................................................ 11 /19/2007
Start Construction ............................................................................... 01 /07/2008
Complete Construction ......................................................................... 07/17/2009
Over the last few years the City has worked towards replacing the existing Tustin Branch
Library with a new Tustin Library to be operated by the Orange County Public Library.
Despite rejection of the City's funding request for the project by the State Library Bond Act
Board, the City Council reconfirmed the outstanding merits of the project and committed to
completing the project and securing necessary funding for the project.
This commitment level has been demonstrated by the City Council's direction to staff to
proceed with final .construction design for the new Tustin Library Project by Field Paoli
Architecture in March 2005, the retention of Griffin Structures in December 2006 to provide
project management services for the project including pre-construction constructability
reviews and design coordination assistance, and the recent appropriation of additional
funding for the project as part of the FY 2007-2008 budget adoption.
Given the complexity of the Tustin Library Project, the City elected to utilize apre-
qualification process to ensure that experienced contractors with proven track records and
financial stability would be bidding on the Tustin Library Project.
On April 17, 2007, the Tustin City Council approved the general contractor pre-qualification
package for construction of Tustin Library Expansion. After a public notice process, the City
Clerk on June 6, 2007 received submittals under the pre-qualification process from fourteen
(14) general contractors for the Tustin Library Project.
The pre-qualification process for the Tustin Library was modeled after the Department of
Industrial Relations format without any modifications by the City of Tustin. As a result of
review of the stipulated essential requirements for qualification and the analysis completed
by Griffin Structures and City Public Works and Redevelopment Agency staff, it has been
determined that all fourteen (14) contractors originally submitting pre-qualification submittals
in response to the City's request will be eligible to bid the Tustin Library Project. A list of
these general contractors is provided as an Exhibit "A" to this agenda report.
Approval of Pre-qualified General Contractors and Approval of Plans and Specifications and
Authorization to Advertise for Bids and the Tustin Library Project (CIP No. 1045)
September 4, 2007
Page 3
Under the California Environmental Quality Act Implementing Guidelines, the City Council on
May 6, 2002 approved a Negative Declaration for the project with adoption of Resolution No.
02-49, and recorded a Notice of Determination with the County Recorder on May 30, 2002.
Plans and specifications for the approximate 32,000 square foot Tustin Library Project have
now been completed and the project is ready to bid to the list of pre-qualified general
contractors.
Christine A. Shingleton
Assistant City Manager
Tim D. Serle
Director of Public Works/City Engineer
Attachments: Resolution No. 07-69
Exhibit "A" (List of Qualified General Contractor)
Location Map
S:\City Council Items\2007 Council ItemsWpproval of P&S Tustin Library Expansion (CIP 1045) & Reso 07-69.doc
RESOLUTION NO. 07-69
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA APPROVING PLANS AND SPECIFICATIONS FOR THE
TUSTIN LIBRARY PROJECT (CIP NO. 1045), AND AUTHORIZING
ADVERTISEMENT FOR BIDS TO A LIST OF PRE-QUALIFIED
GENERAL CONTRACTORS
WHEREAS, it is the intention of the City Council of the City of Tustin, California
to contract for the construction of the Tustin Library Project (CIP No. 1045); and
WHEREAS, the City Engineer has presented plans and specifications for the
construction of said work; and
WHEREAS, A Negative Declaration was prepared and adopted on May 6, 2002 and
Notice of Determination was recorded with the County Recorder on May 30, 2002 ;and
NOW, THEREFORE, BE IT RESOLVED that the plans and specifications
presented by the City Engineer are hereby approved as the plans and specifications for:
Tustin Library Project (CIP No. 1045)
BE IT FURTHER RESOLVED that the City Clerk is herby authorized and
directed to advertise as required by law for the receipt of sealed bids or proposals for
the performance of the work specified in the aforesaid plans and specifications;
PASSED AND ADOPTED at a regular meeting of the City Council of the City of
Tustin held on the 4th day of September 2007.
Lou Bone, Mayor
ATTEST:
City Clerk
a
m
w
~. (n
LCD ~/
O 0
r ~
Z Q
H
aZ
~? O
V
V~
~ ~
Ow
GC Z
aw
~~
aW
00 -
J~
a
z~
ci '
=w
~- a
~,
~ ~
x
~ ~
x
~ ~
x
~
x
~
x
x
x
x
x
x
X
X
x
x
~
Z 000
00 OO
Ot.C) ra0
NO OCO
Or ~~
I`r- 00
O~ ~O
tn~ OM
00 0000
0000 Oln
000 OO
OCO NO
Nlf) Or
O~ OO
NN
~+
V lf')I`
rN f~l`
f`i` LnN
r0 OO
~~ ~0
Mr M~
~~ 00
rr tt~
rr 0000
r0 OO
f`M o000
Md' Nd'
rr 0~
I`Cp MM
NN
~~+ Ot.C) OCO 00~ 00 00I` std' I`i` NN I`I` Nti CON MM MM MM
C
p ~t.C)
NO 00
f`I` 0C0
oOM 00
tt~ 0Cfl
O~ OO
0000 In~
0000 rr
MM ~~
~d' NI`
CO d' 00
I`f~ MM
OCfl d'~
CO CD MM
~'~
U 00 00 0000 tt~ 00 d'~ CO CO 00 00 00 OCO d'~ 00 d'~
~~ (pCp rr rr d-~ rr NN rr- ~~ ~~ NN rr rr rr
0 0 I~ 1` 00 00 f` I` 0 0 f` f` O O M M 0 0 0 0 O CO I` I` M M f` I`
O N
Q O ~
i
~
~ r
m O
O
~ •~
(/1
O
N I`
r r p CO ~ N
~ O
~ i
0
N N ~ O
~M ~
C r
~ N
~ N
~~ ~
(n ~ ~~ N~ O
~ C N ~ ~ ~ _ ~ NO C~ Lp mN
-p ~ O
.L O 0
OQ N~
~O >+
(~ 00
~Q 0
..~ p
~0 j
m ~ QO 000 OV0 ~0
a N~ N
Q0 ~U (nN ~~ LU ~~ mQ ~~ Z~ CO UM pQ ~Q
~O NQ ~ O tn0 NCO C) N O
Q NU _
NO CO
~ oQ °~~ UU U
~~
~U
~~
~~U
~rn
~ o
oU
a~ ~
~~
U~
.~nU c
~Q
~
y-
~ N
•C Q -Op
Q LL ~ J O Q O Ur ~~ ~ N O Q '= Q O N
~ U
~ 4
-
V~ M N N
cN/ 1
G .
L
° -p C L
N~ ~
C O a--+ r,
Q \.J 5
Lr N L
W T N
~ O {,yam U
O C U
r ~
~
>> O ~
~ C W
~ N
W
~ N U O ~ lf7 L r N 00 ~ Ln C 0 Q t!') N M N z N > C t.(') Q a-'
~ .C
M~ O U
O (~ 00 C
r N 0 N
CV C N .C
r~ ~ L
r N O N
0 ~ cn
00 O ~ .C
L(7 ~ I` .C
f~ ~ I` ~
I` N 00 N
ti L ~ N
N O ~ ~
f` °
N- InW COCn rQ N- ~--U rO rJ r- r-- N~ r`O LnJ NU
O
i
V
'
N
C
C
a i
~
C
~ ~
c
~
~
°
~
~ N
O
° ~ ~ ° °~ ° ~ -
~ ~ ~ ~ ° o ~ ~
c
a
= O C)
•L ~ c c
~ ~ N z D ~ ~ 0
N (~ N
° W O ~ ~ ~ -~ = ~ D
U ~ ~ N ~ N
~ N
~ .o
s
(~
~
U ~
o ~
cn O
~ O
~ N
_ L
U m O
o cn C
Q N
~ cn _
m
c
~
c
~ Q
U
c
U
~
~ L
~
a ~
~ O
° -
U
d
~ c o Q ~ o
U ~
c a U
N
Z
O
~
~
c
~
o
L
~
~
N
C7
0
U
~
C
o ~
O
:~,
>+ ~ N U p ~ v C U v ~
~ +r
~
~
o
U C)
L C
- O
~ C
o
c
n ~
o O
~ L
~,
LZ
~ °
U L
° r-=~
~ ~
~' ~
~ ~
° L
Q V
L L
~
~ ~
~ ~
° C
U
p - ~ '~ .L O _
U O _
.C ~
N U
V
~
=
m
~
~
~
~
L
U ~ to
C
O
m (q
~
O
.Q
O
.~ O
~
L
O ,
C
~ O
U ~ N
C O
~
U C
U
~
Z O
O
~ O
~ ~
~ ~ a~ -p
~ ~
0 U U
o ~ ~ ~
~ ° _ ~ ~
Y U L ~ C ~ ~
~ ° ~ L 'L'
U W m (n ~ 2 ~ ~ U 2 (n ~ ~ ~ ~
ADMINISTRATION
~~ ~~
~~
' ~,
August 13, 2007
Ms. Christine Shingleton
Assistant City Manager
City of Tustin
300 Centennial Way
Tustin, CA 92780
Subject: Tustin Library -Pre-Qualification of Contractors
Dear Christine,
AUG 2 '7 2001 i
DECEIVED
° vD
AUG 2 7 2007
TUSTIN PUF3LIC 1N(~RKS DEPT.
Griffin Structures, Inc. is forwarding the results of the pre-qualification of general contractors for the Tustin
Library Project. A total of fourteen (14) contractors submitted pre-qualification packages for consideration
by the City of Tustin. '
The pre-qualification process for the Tustin Library project was modeled after the Department of Industrial
Relations format without any modifications by the City of Tustin. The DIR format utilizes two methods
(parts) to determine the pre-qualification status for a perspective contractor. The methods and the results of
each are summarized by the following:
1. Part I: Essential Requirements for Qualification: This section consists of nine (9) questions with
the condition that any one question answered incorrectly automatically disqualifies the
contractor. Attached is Exhibit A which is the results to Part 1 including the answers to
each of the nine (9) questions. In summary, all fourteen (14) contractors satisfy this
major component of the Pre-Qualification process.
2. Part II: List of Scorable Questions. The list of scorable questions is divided into three sections.
The following are the sections and results for each from each of the contractors:
Section I: History of the business and organizational performance.
This section consists of sixteen (16) questions with a possible maximum score of
76. The DIR recommends a minimum score of 57 to pre-qualify. Attached is
Exhibit B which is the results to Section 1 including the answers to each of the
sixteen (16) questions and the corresponding score for each contractor. In
summary, all fourteen (14) contractors scored above the minimum required
score of 57 and therefore satisfies this major component of the Pre-Qualification
process.
GRIFFIN STRUCTURES, INCORPORATED
Corporate Headquarters
385 Second Street
Laguna Beach, California 92651
Tel 949.497.9000 Fax 949.497.8883
CALIFORNIA NEVADA ARIZONA
Section II: Compliance with occupational safety and health laws, workers' compensation
and other labor legislation.
This section consists of eleven (11) questions with a possible maximum score of
53. The DIR recommends a minimum score of 38 to pre-qualify. Attached is
Exhibit C which is the results to Section II including the answers to each of the
eleven (11) questions and the corresponding score for each contractor. In
summary, all fourteen (14) Contractors scored above the minimum required
score of 38 and therefore satisfies this major component of the Pre-Qualification
process.
Section III: Completion of recent projects and quality of performance.
This section includes a series of interview questions, and may also include
questions about recently completed (public or private) construction projects.
For the interview questions, the DIR recommends that a public agency interview
project managers for the owners of two completed projects. DIR recommends a
scoring system that would allow a maximum score of 120 points for each
interview. For these questions, DIR recommends qualification for a contractor
whose score on each of the two interviews is 72 points or more, a denial of pre-
qualification for a contractor whose score on either interview is less than 55
points, and an additional interview with another reference if the score resulting
from one interview is between 55 and 72 points. The approach taken to the
interviews utilized the Model Interview Questions provided by the DIR and also
the recommend scoring for each of the thirteen (13) questions. The Contractors
are required to provide a minimum of six (6) past completed projects. The goal
was to select two projects that closely represented the project being considered
by the City of Tustin. A representative from Griffin Structures contacted the
project's reference and conducted each of the two interviews. The project
reference was not the contractor, but the individual that represented the
ownership of each completed project. The interviews consisted of the DIR
questions being asked and the answers were provided strictly by the project
reference. The scores to each question were not established by Griffm
Structures. Due to the subjective nature of the questions, the scores varied
between individual project references contacted.
Attached is Exhibit D which is the interview questions for two recently
completed projects for each of the fourteen. (14) contractors and the
corresponding scores based on the responses given by the references contacted.
In summary, all fourteen (14) contractors scored above the minimum required
score of 72 for each of the two interviews and therefore satisfies this major
component of the Pre-Qualification process.
In conclusion, all fourteen (14) contractors are pre-qualified in response to the City of Tustin's request for
pre-qualification of bidders commencing with forthcoming public work bid. A copy of the pre-
qualification request package issued to all contractors is attached for reference.
If you have any questions regarding the above and/or the attached results then please feel free to contact
myself at your earliest convenience.
GRIFFIN STRUCTURES, INCORPORATED
Corporate Headquarters
385 Second Street
Laguna Beach, California 92651
Te1949.497.9000 Fax 949.497.8883
CALIFORNIA NEVADA ARIZONA
Griffin Structures, Inc.
GRIFFIN STRUCTURES, INCORPORATED
Corporate Headquarters
385 Second Street
Laguna Beach, Califonva 92651
Tel 949.497.9000 Fax 949.497.8883
CALIFORNIA NEVADA ARIZONA
Vice President
EXHIBIT A
PART I: ESSENTIAL REQUIREMENTS FOR QUALIFICATION
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
PART 1: ESSENTIAL REQUIREMENTS FOR QUALIFICATION
Note: Contractor will immediately be disqualified if the answer to any questions 1 through 5 is "No"
Note: Contractor will immediately be disqualified if the answer to any questions 6,7,8 or 9 is "Yes".
QUESTION
1. Contractor possesses a valid and current Class "B" Califomla Contractor's license for the project or projects for which it intends to submit a bid
RESPONSE YES NO COMMENTS
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.J. DAUM X
S.J. AMOROSO X
SWINERTON X
W.E. O'NEIL X
WOOOCLIFF CORP. X
QUESTION
2. Contractor has a commercial liability insurance polity with a polity limit of at least $2,000,000 per occurrence and $2,000,000 aggregate, commercial automobile
insurance with a limit of at least $1,000,000, and California worker's compensation insurance with a limit of at least $1,000,000.
RESPONSE YES NO COMMENTS
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.J. DAUM X
5.1. AMOROSO X
SWINERTON X
W.E. O'NEIL X
WOODCLIFF CORP. X
QUESTION
3. Contractor has current workers' compensation insurance policy as required by the Labor Code of is legally self-Insured pursuant to Labor Code section 3700 et. seq.
RESPONSE YES NO COMMENTS
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.J. DAUM X
S.J. AMOROSO X
SWINERTON X
W.E. O'NEIL X
WOODCLIFF CORP. X
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
4. Have you attached your latest copy of a reviewed or audited financial statement with accompanying notes and supplemental information.
RESPONSE YES NO COMMENTS •
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.1. DAUM X
S.J. AMOROSO X
SWINERTON X
W.E. O'NEIL X
WOODCLIFF CORP. X
QUESTION
5. Have you attached a notarized statement from an admitted surety insurer (approved by the California Department of Insurance) and authorized to issue bonds
in the State of California, which states a) that your current bonding capacity is sufficient for the project for which you see pre-qualification for a single project.
RESPONSE YES NO COMMENTS
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.J. DAUM X
S.J. AMOROSO X
SWINERTON X
W.E. O'NEiI X
WOODCLIFF CORP. X
QUESTION
6. Has your contractor's license been revoked at any time in the last five years
RESPONSE YES NO COMMENTS
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.J. DAUM X
S.J. AMOROSO X -
SWINERTON X
W.E. O'NEIL X
WOODCLIFF CORP. X
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
7. Hasa surety firm completed a contract on your behalf, or paid for completion because your firm was default terminated by the project owner within
the last (S) years? •
RESPONSE YES NO COMMENTS
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.1. DAUM X
S.J. AMOROSO X
SWINERTON X
W.E. O'NEIL X
WOODCLIFF CORP. X
QUESTION
8. At this time of submitting this pre-qualification form, is your firm ineligible to bid on or be awarded a public works contract, or perform as a subcontractor
on a public works contract, pursuant to either Labor Code section 1777.1 or Labor Code section 1777.7?
RESPONSE YES NO COMMENTS
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.J. DAUM X
S.J. AMOROSO X
SWINERTON X
W.E. O'NEIL X
WOODCUFF CORP. X
QUESTION
9. At any time during the last five years, has your firm, or any of Its owners or officers, been convicted of a crime involving the awarding of a contract of a
government construction project, or the bidding or performance of a govemment contract?
RESPONSE YES NO COMMENTS
BERNARDS X
ERICKSON-HALL X
GKKWORKS X
HOWARD S. WRIGHT X
HARBOR X
MORILLO X
P.H. HAGOPIAN X
PINNER X
PW CONSTRUCTION X
R.1. DAUM X
S.J. AMOROSO X
SWINERTON X
W.E. O'NEIL X
WOODCLIFF CORP. X
EXHIBITB
PART II: LIST OF SCORABLE QUESTIONS
SECTION I: HISTORY OF THE BUSINESS AND
ORGANIZATIONAL PERFORMANCE
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
EXHIBIT B
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
PART II: LIST OF SCORABLE QUESTIONS
SECTION 1: HISTORY OF THE BUSINESS AND ORGANIZATIONAL PERFORMANCE
D.I.R. RECOMMENDS USE OF A PASSING SCORE OF 57 OUT OF A POSSIBLE 76 POINTS
SEE ATTACHED "LIST OF THE SCORABLE QUESTIONS AND THE SCORING INSTRUCTIONS" PROVIDED BY THE D.I.R.
QUESTION
1. How many years has your organization been in business in California as a contractor under your present business name and license number?
RESPONSE YEARS SCORE COMMENTS
BERNARDS 33 5
ERICKSON-HALL 9 5
GKKWORKS 10 5
HOWARD S. WRIGHT 2.S 0 The Howard S. Wright family of affiliated companies has been established for over 120 years.
HARBOR 8 5
MORILLO 30 5
P.H. HAGOPIAN 21 5
PINNER 51 5
PW CONSTRUCTION 23 5
R.J. DAUM 71 5
S.J. AMOROSO 30 5
SWINERTON 119 5
W.E.O'NEIL 22 5
WOODCLIFF CORP. li 5
QUESTION
2. Is your firm currently the debtor in a bankruptry case?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 3
ERICKSON-HALL X 3
GKKWORKS X 3
HOWARD S. WRIGHT X 3
HARBOR X 3
MORILLO X 3
P.H. HAGOPIAN X 3
PINNER X 3
PW CONSTRUCTION X 3
R.J. DAUM X 3
S.J. AMOROSO X 3
SWINERTON X 3
W.E.O'NEIL X 3
WOODCLIFF CORP. X 3
QUESTION
3. Was your firm in bankruptry any time during the last five years?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 3
ERICKSON-HALL X 3
GKKWORKS X 3
HOWARD S. WRIGHT X• 3
HARBOR X 3
MORILLO X 3
P.H. HAGOPIAN X 3
PINNER X 3
PW CONSTRUCTION X 3
R.1. DAUM X 3
S.J. AMOROSO X 3
SWINERTON X 3
W.E.O'NEIL X 3
WOODCLIFF CORP. X 3
EXHIBIT B
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
4. Has any CSLB license held by your firm or its Responsible Managing Employed (RME) or Responsible Managing Officer (RMO) been
suspended within the last five years? •
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X S
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X S
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X S
QUESTION
5. At any time in the last five years, has your firm been assessed and paid liquidated damages after completion of a project, under a construction
contract with either a public or private owner?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X S
MORILLO X 5
P.H. HAGOPIAN X S
PINNER X 5
PW CONSTRUCTION X 0
R.J. DAUM X 5
5.1. AMOROSO X 5
SWINERTON X S
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
QUESTION
Liquidated damages were assessed in the amount of $243,000 due to schedule delays
6. In the last five years has your firm, or any firm with which any of your company's owners, officers or partners was associated, been debarred,
disqualified, removed or otherwise prevented from bidding on, or completing, any government agency or public works project for any reason?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X S
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X S
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J.OAUM X S
5.1. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
EXHIBIT B
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
7. In the last five years, has your firm been denied an award of a public works contract based on a finding by a public agency that your company
was not a responsible bidder? •
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5,
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X ~ S
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X S
R.J. DAUM X 5
S.J. AMOROSO X S
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
QUESTION
8. In the past flue years, has any claim against your firm concerning your firm's work on a construction project, been filed in a court or arbitration?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 0 D.I.R. recommends a score of 0 points if more than 5 such instances.
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
QUESTION
9. In the past five years, has your firm made any claim against a project owner concerning work on a project or payment for a contract, and filed
that claim in court of arbitration?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORIlLO X 0 D.I.R. recommends a score of 0 points if more than 2 such instances.
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
EXHIBIT B
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
10. At any time during the past five years, has any surety company made any payments on your firm's behalf as a result of a default, to satisfy
any claims made against a performance or payment bond issued on yoer firm's behalf in connection with a construction project, either public or private?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X S
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
QUESTION
11. In the last five years, has any insurance carrier, for any form of insurance, refused to renew the insurance polity for your firm?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X S
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X S
R.J. DAUM X 5
S.J. AMOROSO X S
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
QUESTION
12. Has your firm, or any of its owners, officers, or partners ever been found liable in a civil suk, or found guilty in a criminal action,
for making any false claim or material representation to any public agenry or entity?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X S
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X S
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
EXHIBIT B
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
13. Has your firm, or any of its owners, officers, or partners ever been convicted of a crime involving any federal, state, or local law
related to construction? •
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5 '
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
QUESTION
14. Has your firm, or any of its owners, officers, or partners ever been wnvided of a federal or state crime of fraud, theft, or any other act
of dishonesty?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEiI X 5
WOODCUFF CORP. X 5
QUESTION
15. If your firm was required to pay a premium of more than one percent for a performance and payment bond on any project(s) on which
your firm worked at any time during the last three years, state the percentage that your firm was required to pay.
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X S
6KKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5 •
PW CONSTRUCTION X 3
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
EXHIBIT B
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
16. During the last five years, has your firm ever been denied bond credit by a surety company, or has there ever been a period of time when
your firm had no surety bond in place during a public construction project when one was required?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X S
SWINERTON X S
W.E.0'NEIL X 5
WOODCLIFF CORP. X 5
SCORING RESULTS SCORE PASS FAIL
BERNARDS 76 X
ERICKSON-HALL 76 X
GKKWORKS 76 X
HOWARD 5. WRIGHT 71 X
HARBOR 76 X
MORILLO 71 X
P.H. HAGOPIAN 76 X
PINNER 76 X
PW CONSTRUCTION 69 X
R.J. DAUM 76 X
S.J. AMOROSO 76 X
SWINERTON 71 X
W.E.0'NEIL 76 X
WOODCLIFF CORP. 76 X
A LIST OF THE SCORABLE QUESTIONS AND THE SCORING INSTRUCTIONS
The scorable questions arise in three different areas:
(I) History of the business and organizational performance;
(II) Compliance with occupational safety and health laws, workers' compensation and
other labor legislation; and
(III) Completion of recent projects and qualm of performance.
The interview questions (interviews by the public agency of project managers on projects
completed recently by the contractor) are included in group III. In apre-qualification
procedure for a single proTct, this last category would also include a scoring of the
number of recently completed projects that are similar to the project on which pre-
qualification is at issue.
Note: Not all questions in the questionnaire are scorable; some questions simply ask for
information about the contractor firm's structure, officers and history. This document
includes only those questions that are "scorable." The question numbers in this document
are the numbers used in the questionnaire. Thus, the questions included here begin with
question number 6, and there are a few breaks in the numerical sequence.
The Scores Needed for Prequalification
To prequalify, a contractor would be required to have a passing grade within each of the
three large categories referred to above.
For Section I, "History of the business and organizational performance,"
DIR recommends use of a passing score of 57 on this portion of the questionnaire (of a
maximum score of 76 on this portion of the questionnaire).
For Section II, Compliance with occupational safety and health laws, workers'
compensation and other labor le 'station DIR recommends use of a passing score of 38
on this portion of the questionnaire (of a maximum score of 53 points on this portion of
the questionnaire).
Section III, Completion of recent projects~qualit~ f performance, includes a series of
interview questions, and may also include questions about recently completed (public or
private) construction projects. For the interview questions, DIIZ recommends that a
public agency interview project managers for the owners of two completed projects.
DIR recommends a scoring system that would allow a maximum score of 120 points for
each interview. For these questions, DIR recommends qualification for a contractor
whose score on each of two interviews is 72 points or more; a denial ofpre-qualification
for a contractor whose score on either interview is less than 55 points; and an additional
19
interview with another referenee if the score resulting from one interview is between 55
points and 72 points.
DIR makes no recommendation about how to score a contractor's answers about
recently completed past projects. Because of the wide range of projects that a public
agency maybe planning, and the similarly wide range in the skills, abilities, and
experience that a public agency will consider most important for a pending project, it is
impossible to propose a useful model scoring system to apply to the answers given about
a contractor's completed projects.
4uestions about History of the Business and Organizational Performance
(16 questions)
1. How many years has your organization been in business in California as a contractor under
your present business name and license number? years
3 years or more = 2 points
4 years = 3 points S years = 4 ptS
6 years or more = S points
2. Is your firm currently the debtor in a bankruptcy case?
^ Yes ^ No
"No" = 3 points" "Yes" = 0 points
3. Was your firm in bankruptcy any time during the last five years? (This question refers
only to a bankruptcy action that was not described in answer to question 7, above).
^ Yes ^ No
"No" = 3 points" "Yes" = 0 points
4. Has any CSLB license held by your firm or its Responsible Managing Employee (RME)
or Responsible Managing Officer (RMO) been suspended within the last five years?
^ Yes ^ No
No = S points Yes = 0 points
20
A
5. At any time in the last five years, has your firm been assessed and paid liquidated
damages after completion of a project, under a construction contract with either a public
or private owner?
^ Yes ^ No
No projects with liquidated damages of more than $50,000, or one project with liquidated
damages = S points
Two projects with liquidated damages of more than $50,000 = 3 points
Any other answer: no points
6. In the last five years has your firm, or any firm with which any of your company's owners,
officers or partners was associated, been debarred, disqualified, removed. or otherwise
prevented from bidding on, or completing, any government agency or public works project
for any reason?
NOTE: "Associated with" refers to another construction firm in which an owner,
partner or officer of your firm held a similar position, and which is listed in response
to question 1 c or 1 d on .this form. .
^ Yes ^ No
No = S points Yes = 0 points
7. In the last five years, has your firm been denied an award of a public works contract based
on a finding by a public agency that your company was not a responsible bidder?
^ Yes ^ No
No = S points Yes = 0 points
NOTE: The following two questions refer only to disputes between your firm and the
owner of a project. You need not include information about disputes between your
firm and a supplier, another contractor, or subcontractor. You need not include
information about "pass-through" disputes in which the actual dispute is between a
sub-contractor and a project owner. Also, you may omit reference to all disputes
about amounts of less than $50,000. r
21
8. In the past five years, has any claim a~;air=st your firm concerning your firm's work on a
construction project, been filed in court or arbitration?
^ Yes ^ No
If the~rm's average gross revenue for the last three years was less than
$SO million, scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating 2 such instances.
0 points for "Yes" if more than 2 such instances.
If your firm's average gross revenue for the last three years was more than $SO
million, scoring is as follows:
S points for either "No" or "Yes" indicah'ng 1, 2, or 3 such instance
3 points for "Yes" indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances.
9. In the past five years, hay your firm made any claim against a project owner concerning
work on a project or payment for a contract, and filed that claim in court or
arbitration?
^ Yes ^ No
If your firm's average gross revenues for the last three years was less than $SO million
scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating 2 such instances.
0 points for "Yes" if more than 2 such instance
If your~rm's average gross revenues for the last three years was more than $SO
million, scoring is as follows:
S points for either "No" or "Yes" indicating 1, 2, or 3 such instances.
3 points for "Yes" indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances
22
10. At any time during the past five years, has any surety company made any payments on
your firm's behalf as a result of a default, to satisfy any claims made against a
performance or payment bond issued on your firm's behalf in connection with a
construction project, either public or private?
^ Yes ^ No
S points for either "No" or "Yes" indicating 1 such claim.
3 points for "Yes" indicating no more than 2 such claims
Subtract five points for "Yes" if more than 2 such. claims
11. In the last five years, has any insurance carrier, for any form of insurance, refused to
renew the insurance policy for your firm? .
^ Yes ^ No
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating 2 such instances.
0 points for "Yes" or if more than 2 such instances. .
12. Has your firm, or any of its owners, officers, or partners ever been found liable in a civil
suit, or found guilty in a criminal action, for making any false claim or material
misrepresentation to any public agency or entity?
^ Yes ^ No
No = S points Yes = subtract S points
13. Has your firm, or any of its owners, officers or partners ever been convicted of a crime
involving any federal, state,' or local law related to construction?
^ Yes ^ No
No = S points Yes = subtract S points
14. Has your firm or any of its owners, officers or partners ever been convicted of a federal or
state crime of fraud, theft, or any other act of dishonesty?
^ Yes ^ No
No = S points Yes = subtract S points
23
15. If your firm was required to pay a premium of more than one per cent for a performance
and payment bond on any project(s) on which your firm worked at any time during the
last three years, state the percentage that your firm was required to pay. You may
provide an explanation for a percentage rate higher than one per cent, if you wish to do
so.
S points if the rate is no more than one per cent
3 points if the rate was no higher than 1.10 per cent
0 points for any other answer.
16. During the last five years, has your firm ever been denied bond credit by a surety company,
or has there ever been a period of time when your firm had no surety bond in place during a
public construction project when one was required?
^ Yes ^ No
No = S points Yes = 0 points
4uestions about compliance with safety, workers compensation,
prevailing wage and apprenticeship laws.
(11 questions)
1. Has CAL OSHA cited and assessed penalties against your firm for any "serious," "willful"
or "repeat" violations of its safety or health regulations in the past five years?
Note: If you have filed an appeal of a citation and the Occupational Safety and Health
Appeals Board has not yet ruled on your appeal, you need not include information
about it.
^ Yes ^ No
If the firm's average gross revenues for the last three years was less than $SO million,
.scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating 2 such instances.
0 points for "Yes" if more than 2 such instances.
If the~rm's average gross revenues for the last three years was more than $SO million,
scoring is as follows:
S points for either "No" or "Yes" indicating 1, 2, or 3 .such instance
3 points for "Yes" indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances.
24
2. Has the federal Occupational Safety and Health Administration cited and assessed
penalties against your firm in the past five years?
Note: If you have filed an appeal of a citation and the appropriate appeals Board
has not yet ruled on your appeal, you need not include information about it.
^ Yes ^ No
If yes, attach a separate signed page describing each citation.
If the firm's average gross revenues for the last three years was less than $SO million,
scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating 2 such instances.
D points for "Yes" or if more than 2 such instances.
If the firm's average gross revenues for the last three years was more than DSO
million, scoring is as follows:
S points for either "No" or "Yes" indicating 1, 2, or 3 such instances.
3 points for "Yes" indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances:
3. Has the EPA or any Air Quality Management District or any Regional Water Quality
Control Board cited and assessed penalties against either your firm or the owner of a
project on which your firm was the contractor, in the past five years?
NOTE: If you have filed an appeal of a .citation and the Appeals Board has not yet
ruled on your appeal, or if there is ~a court appeal pending, you need not include
information about the citation. -
^ Yes ^ No
If the firm's average gross revenues for the last three years was less than $SO million,
scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating 2 such instances.
0 points for "Yes" or if more than 2 such instances
If the firm's average gross revenues for the last three years was more than $SO million,
scoring is as follows:
S points for either "No" or "Yes" indicating 1, 2, or 3 such instances.
3 points for "Yes"indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances.
25
4. How often do you require documented safety meetings to beheld for construction
employees and field supervisors during the course of a project?
3 points for an answer of once each week or more often.
0 points for any other answer
5. List your firm's Experience Modification Rate (EMR) (California workers' compensation
insurance) for each of the past three premium years:
NOTE: An Experience Modification Rate is issued to your firm annually by your
workers' compensation insurance carrier.
Current year:
Previous year:
Year prior to previous year:
If your EMR for any of these three years is or was 1.00 or higher, you may, if you wish,
attach a letter of explanation.
NOTE: An Experience Modification Rate is issued to your firm annually by your
workers' compensation insurance carrier.
S points for three year average EMR of . 95 or less
3 points for three year average of EMR of more than .9S but no more than 1.00
0 points for any other EMR
6. Within the last five years, has there ever been a period when your firm had employees but
was without workers' compensation insurance or state-approved self-insurance?
^ Yes ^ No
S points for either "No" or "Yes" indicating l such instance.
0 points for any other answer.
26
7. Has there been more than one occasion during the last five years on which your firm was
required to pay either back wages or penalties for your own firm's failure to comply with the
state's prevailing wage laws?
^ Yes ^ No
NOTE: This question refers only to your owa firm's violation of prevailing wage laws,
not to violations of the prevailing wage laws by a subcontractor.
If your firm's average gross revenues for the last three years was less'than DSO million,
scoring is as follows:
S points for either "No, " or "Yes" indicating either 1 or Z such instance.
3 points for "Yes" indicating 3 such instances
0 points for "Yes" and more than 3 such instances.
If your firm's average gross revenues for the last three years was more than $SO
million, scoring is as follows:
S points for either "No" or "Yes" indicating no more than 4 such instances.
3 points for "Yes" indicating either S or 6 such instances.
0 points for "Yes" and more than 6 such instances.
8. During the last five years, has there been more than one occasion on which your own firm
has been penalized or required to pay back wages for failure to comply with the federal
Davis-Bacon prevailing wage requirements?
^ Yes ^ No
If your firm's average gross revenues for the last three years was less than $SO million,
scoring is as follows:
S points for either "No, " or "Yes" indicating either 1 or Z such instance.
3 points for "Yes" indicating 3 such instances.
0 points for "Yes" and more than 3 such instances.
If your firm's average gross revenues for the last three years was more than $SO
million, scoring is as follows:
S points for either- "No" or "Yes" indicating no more than 4 such instances.
3 points for "Yes" indicating either S or 6 such instances.
0 points for "Yes" and more than 6 such instances.
27
9. Provide the name, address and telephone number of the apprenticeship program
sponsor(s) (approved by the California Division of Apprenticeship Standards) that will
provide apprentices to your company for use on any public work project for which you
are awarded a contract by the City of Tustin.
S points if at least one approved apprenticeship program is listed.
0 points for any other answer.
10. If your firm operates its own State-approved apprenticeship program:
(a) Identify the craft or crafts in which your firm provided apprenticeship training in
the past year.
(b) State the year in which each such apprenticeship program was approved, and
attach evidence of the most recent California Apprenticeship Council approval(s)
of your apprenticeship program(s).
(c) State the number of individuals who were employed by your firm as apprentices
at any time during the past three years in each apprenticeship and the number of
persons who, during the past three years, completed apprenticeships in each craft
while employed by your firm.
S points if one or more persons completed an approved apprenticeship while employed
by your firm.
0 points if no persons completed an approved apprenticeship while employer by your
firm.
28
1 1. At any time during the last five years, has your firm been found to have violated any
provision of California apprenticeship laws or regulations, or the laws pertaining to use of
apprentices on public works?
NOTE: You may omit reference to any incident that occurred prior to January 1,.
1998 if the violation was by a subcontractor and your firm, as general contractor on
a project, had no knowledge of the subcontractor's violation at the time they
occurred.
^ Yes ^ No.
If yes, provide the date(s) of such findings, and attach copies of the Department's final
decision(s).
If your firm's average gross revenues for the last three years was less than $SO million,
scoring is as follows:
S points for either "No,"or "Yes" indicatiing either 1 or 2 such instance.
3 points for "Yes" indicating 3 such instance
0 points for "Yes" and more than 3 such instance
If your firm's average gross revenues for the last three years was more than $SO
million, scoring is as follows:
S points for either "No" or "Yes" indicating no more than 4 such instances.
3 points for "Yes" indicating either S or 6 such instance
0 points for "Yes" and more than 6 such instances.
29
EXHIBIT C
PART II: LIST OF SCORABLE QUESTIONS
SECTION II: COMPLIANCE WITH OCCUPATIONAL SAFETY
AND HEALTH LAWS, WORKERS'S COMPENSATION AND
OTHER LABOR LEGISLATION
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
EXHIBIT C
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
PART II: LIST OF SCORABLE QUESTIONS
SECTION II: COMPLIANCE WITH OCCUPATIONAL SAFETY AND HEALTH LAWS, WORKERS COMPENSATION AND OTHER LABOR LEGISLATION
DIR RECOMMENDS USE OF A PASSING SCORE OF 38 OUT OF A POSSIBLE 53 POINTS
SEE ATTACHED "LIST OF THE SCORABLE QUESTIONS AND THE SCORING INSTRUCTIONS" PROVIDED BY THE D.I.R.
QUESTION
i. Has CAL OSHA cited and assessed penalties against your firm for any "serious", "willful" or "repeat" violations of its safety or health regulations
in the past five years?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X S
HARBOR X 5
MORILLO X 5 Appeal was filed and Cal/OSHA agreed that previous violation was not Contractor's liability.
P.H. HAGOPIAN X 5
PINNER X S
PW CONSTRUCTION X S
R.J. DAUM X 5
5.1. AMOROSO X S
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
QUESTION
2. Has the federal Occupational Safety and Health Administration cited and assessed penalties against your firm in the past five years
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X S
PW CONSTRUCTION X 0 A total of seven (7) citations were issued. DIR recommends (0) points for more than 5 instances.
R.J. DAUM X S
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X S
QUESTION
3. Has the EPA or any Air Quality Ma nagement District or any Regional Water Quality Control Board cited and assessed penalties against either your firm
or the owner of a project on which your firm was the contractor, in the past five years
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X S
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X S
EXHIBIT C
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
4. How often do you require documented safety meetings to be held for construction employees and field supervisors during the course of a project?
RESPONSE SCORE COMMENTS
BERNARDS WEEKLY 3
ERICKSON-HALL WEEKLY 3
GKKWORKS WEEKLY 3
HOWARD 5. WRIGHT WEEKLY 3
HARBOR WEEKLY 3
MORILLO WEEKLY 3
P.H. HAGOPIAN WEEKLY 3
PINNER WEEKLY 3
PW CONSTRUCTION WEEKLY 3
R.1. DAUM WEEKLY 3
S.J. AMOROSO WEEKLY 3
SWINERTON 81-MONTHLY 0 DIR recommends (3) points for once a week and (0) points for any other answer
W.E. O'NEIL WEEKLY 3
WOODCLIFF CORP. WEEKLY 3
QUESTION
5. List your firm's EMR for each of the past three premium years.
RESPONSE CURRENT PREVIOUS PRIOR AVG. SCORE COMMENTS
BERNARDS 0.73 0.67 0.98 0.79 5
ERICKSON-HALL 0.88 0.88 1.05 0.94 5
GKKWORKS 0.69 0.69 0.69 0.69 5
HOWARD S. WRIGHT 0.54 0.54 0.67 0.58 5
HARBOR 0.82 ~ 0.82 0.90 0.85 5
MORILLO 1.12 0.85 0.83 0.93 5
P.H. HAGOPIAN 0.89 0.89 0.86 0.88 5
PINNER 0.69 0.69 1.06 0.81 5
PW CONSTRUCTION 0.81 0.87 1.00 0.89 5
R.J. DAUM 1.11 0.85 0.72 0.89 5
S.J. AMOROSO 0.63 0.67 0.83 0.71 5
SWINERTON 0.42 0.42 0.43 0.42 5
W.E.0'NEIL 0.83 •0.95 0.89 0.89 5
WOODCLIFF CORP. 1.00 1.00 0.98 0.99 3
QUESTION
6. Within the last five years, has there ever been a period when your firm had employees but was without workers' compensation insurance
or state approved self-insurance?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
EXHIBIT C
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
7. Has there been more than once occasion during the last five years on which your firm was required to pay either back wages or penalties for your own
firm's failure to comply with the state's prevailing wage laws?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X S
HARBOR X S
MORILLO X S
P.H. HAGOPIAN X S
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.1. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X S
QUESTION
8. Ouring the last flue years, has there been more than one occasion on which your own firm has been penalized or required to pay back wages for failure
to comply wRh the federal Davis-Bacon prevailing wage requirements?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X S
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X S
SWINERTON X 5
W.E.0'NEIL X 5
WOODCLIFF CORP. X 5
QUESTION
9. Provide the name, address and telephone number, of the apprenticeship program sponsor(s) that will provide apprentices to your company
for use on any public work project for which you are awarded a contract by the City of Tustin
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 0 Contractor does not utilize an apprenticeship program due to no self performing work.
ERICKSON-HALL X 5
GKKWORKS X 0 Contractor does not utilize an apprenticeship program due to no self performing work.
HOWARD S. WRIGHT X 0 Contractor does not utilize an apprenticeship program due to no self performing work.
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X S
PW CONSTRUCTION X 5
R.J. DAUM x 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E. O'NEIL X 5
WOODCLIFF CORP. X 5
EXHIBIT C
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
QUESTION
10. If your firm operates its own State-approved apprenticeship program:
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 0
ERICKSON-HALL X 0
GKKWORKS X 0
HOWARD S. WRIGHT X 0
HARBOR X 0
MORILLO X 0
P.H. HAGOPIAN X 0
PINNER X 0
PW CONSTRUCTION X 0
R.J. DAUM X 0
S.J. AMORO50 X 0
SWINERTON X 0
W.E.O'NEiI X 0
WOODCLIFF CORP. X 0
QUESTION
11. At any time during the last five years, has your firm been found to have violated any provision of California apprenticeship laws or regulations, or the
laws pertaining to use of apprentices on public works?
RESPONSE YES NO SCORE COMMENTS
BERNARDS X 5
ERICKSON-HALL X 5
GKKWORKS X 5
HOWARD S. WRIGHT X 5
HARBOR X 5
MORILLO X 5
P.H. HAGOPIAN X 5
PINNER X 5
PW CONSTRUCTION X 5
R.J. DAUM X 5
S.J. AMOROSO X 5
SWINERTON X 5
W.E.O'NEIL X 5
WOODCLIFF CORP. X 5
SCORING RESULTS SCORE PASS FAIL COMMENTS
BERNARDS 43 X
ERICKSON-HALL 48 X
GKKWORKS 43 X
HOWARD S. WRIGHT 43 X
HARBOR 48 X
MORILLO 48 X
P.H. HAGOPIAN 48 X
PINNER 48 X
PW CONSTRUCTION 43 X
R.J. DAUM 48 X
S.J. AMOROSO 48 X
SWINERTON 45 X
W.E.O'NEIL 48 X
WOODCLIFF CORP. 46 X
A LIST OF THE SCORABLE (}UESTIONS AND THE SCORING INSTRUCTIONS
The storable questions arise in three different areas:
(I) History of the business and organizational ,performance;
(II) Compliance with occupational safety and health laws, workers' compensation and
other labor le 'sly ation; and
(III) Completion of recent projects and quality of perforrnarice.
The interview questions (interviews by the public agency of project managers on projects
completed recently by the contractor) are included in group III. In apre-qualification
procedure for a single project, this last category would also include a scoring of the
number of recently completed projects that are similar to the project on which pre-
qualification is at issue.
Note: Not all questions. in the questionnaire are storable; some questions simply ask for
information about the contractor firm's structure, officers and history. This document
includes only those questions that are "storable." The question numbers in this document
are the numbers used in the questionnaire. Thus, the questions included here begin with.
question number 6, and there are a few breaks in the numerical sequence.
The Scores Needed for Prequalification
To prequalify, a contractor would be required to have a passing grade within each of the
three large categories. referred to above.
For Section I, "History of the business and organizational performance,"
DIR recommends use of a passing score of 57 on this portion of the questionnaire (of a
maximum score of 76 on this portion of the questionnaire).
For Section II, Compliance with occupational safety and health laws, workers'
compensation and other labor legislation DIR recommends use of a passing score of 38
on this portion of the~questionnaire (of a maximum score of 53 points on this portion of
the questionnaire).
Section III, Completion of recent projects and quality of performance, includes a series of
interview questions, and may also include questions about recently completed (public or
private) construction projects. For the interview questions, DIR recommends that a
public agency interview project managers for the owners of two completed projects.
DIR recommends a scoring system that would allow a maximum score of 120 points for
each interview. For these questions, DIR recommends qualification for a contractor
whose score on each of two interviews is 72 points or more; a denial ofpre-qualification
for a contractor whose score on either interview is less than 55 points; and an additional
19
interview with another reference if the score resulting from one interview is between 55
points and 72 points.
DIR makes no recommendation about how to score a contractor's answers about
recently completed past projects. Because of the wide range of projects that a public
agency maybe planning, and the similarly wide range in the skills, abilities, and
experience that a public agency will consider most important for a pending project, it is
impossible to propose a useful model scoring system to apply to the answers given about
a contractor's completed projects.
Questions about History of the Business and Organizational Performance
(16 questions)
1. How many years has your organization been in business in California as a contractor under
your present business name and license number? years
3 years or more = 2 points
4 years = 3 points S years = 4 pts
6 years or more = S points
2. Is your firm currently the debtor in a bankruptcy case?
^ Yes ^ No
"No" = 3 points" "Yes" = 0 points
3. Was your firm in bankruptcy any time during the last five years? (This question refers
only to a bankruptcy action that was not described in answer to question 7, above).
^ Yes ^ No
"No" = 3 points" "Yes" = 0 points
4. Has any CSLB license held by your firm or its Responsible Managing Employee (RME)
or Responsible Managing Officer (RMO) been suspended within the last five years?
^ Yes ^ No
No = S points Yes = 0 points
~0
5. At any time in the last five years, has your firm been assessed and paid liquidated
damages after completion of a project, under a construction contract with either a public
or private owner?
^ Yes ^ No
No projects with liquidated damages of more than $50,000, or one project with liquidated
damages = S points
Two projects with liquidated damages of more than $50,000 = 3 points
Any other answer: no points
6. In the last five years has your firm, or any firm with which any of your company's owners,
officers or partners was associated, been debarred, disqualified, removed or otherwise
prevented from bidding on, or completing, any government agency or public works project
for any reason?
NOTE: "Associated with" refers to another constrµction firm in which an owner,
partner or officer of your firm held a similar position, and which is listed in response
to question lc or ld on.this form. .
^ Yes ^ No
No = S points Yes = 0 points
7. In the last five years, has your firm been denied an award of a public works contract based
on a finding by a public agency that your company was not a responsible bidder?
^ Yes ^ No
No = S points Yes = 0 points
* * * * *'
NOTE: The following two questions refer only to disputes between your firm and the
owner of a project. You need not include. information about disputes between your
firm and a supplier, another contractor, or subcontractor. You need not include
information about "pass-through" disputes in which the actual dispute is between a
sub-contractor and a project owner. Also, you may omit reference to all disputes
about amounts of less than 550,000.
21
8. In the past five years, has any claim asst your firm concerning your firm's work on a
construction project, been filed in court or arbitration?
^ Yes ^ No
If the firm's average gross revenue for the last three years was less than
$SO million, scoring is as follows:
S points for either "No" or "Yes'.' indicating 1 such instance.
3 points for "Yes" indicating 2 such instances.
0 points for "Yes" if more than 2 such instances.
If your firm's average gross revenue for the last three years was more than $SO
million, scoring is as follows:
S points for either "No" or "Yes" indicadng 1, 2, or 3 such instances.
3 points for "Yes" indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances.
9. In the past five years, hay your firm made any claim against a project owner concerning
work on a project or payment for a contract, and fled that claim in court or
arbitration?
^ Yes ^ No
If your firm's average gross revenues for the last three years was less than $SO million
scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3~ points for "Yes" indicating 2 such instances.
0 points for "Yes" if more than 2 such instances.
If your firm's average gross revenues for the last three years was more than $SO
million, scoring is as, follows:
S points for either "No" or "Yes" indicating 1, 2, or 3 such instances:
3 points for "Yes" indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances. r
22
r
10. At any time during the past five years, has any surety company made any payments on
your firm's behalf as a result of a default, to satisfy any claims made against a
performance or payment bond issued on your firm's behalf in connection with a
construction project, either public or private?
^ Yes ^ No
S points for either "No" or "Yes" indicating 1 such claim.
3 points for "Yes" indican'ng no more than 2 such claims
Subtract five points for "Yes" if more than 2 such claims
11. In the last five years, has ~ any insurance carrier, for any form of insurance, refused to
renew the insurance policy for your firm?
^ Yes ^ No
S points for either "No" or "Yes" indicating 1 such instances
3 points for "Yes" indicating 2 such instances.
0 points for "Yes" or if more than 2 such instances.
12. Has your firm, or any of its owners, officers, or partners ever been found liable in a civil
suit, or found guilty in a criminal action, for making any false claim or material
misrepresentation to any public agency or entity?
^ Yes ^ No
No = S points Yes = subtract S points
13. Has your firm, or any of its owners, officers or partners ever been convicted of a crime
involving any federal, state,' or local law related to construction?
^ Yes ^ No
No = S points Yes = subtract S points
14. Has your firm or any of its owners, officers or partners ever been convicted of a federal or
state crime of fraud, theft, or any other act of dishonesty?
^ Yes ^ No
No = S points Yes = su= act S points
23
s
15. If your firm was required to pay a premium of more than one per cent for a performance
and payment bond on any project(s) on which your firm worked at any time during the
last three years, state the percentage that your firm was required to pay. You may
provide an explanation for a percentage rate higher than one per cent, if you wish to do
so.
S points if the rate is no more than one per cent
3 points if the rate was no higher than 1.10 per cent
0 points for any other answer.
16. During the last five years, has your firm ever been denied bond credit by a surety company,
or has there ever been a period of time when your firm had no surety bond in place during a
public construction project when one was required?
^ Yes ^ No
No = S points Yes = 0 points
Questions about compliance with safety. workers compensation.
prevailfng wage and apprenticeship laws.
(11 questions)
1. Has CAL OSHA cited and assessed penalties against your firm for any "serious," "willful"
or "repeat" violations of its safety or health regulations in the past five years?
Note: If you have filed an appeal of a citation and the Occupational Safety and Health
Appeals Board has aot yet ruled on your appeal, you need not include information
about it.
^ Yes ^ No
If the firm's average gross revenues for the last three years was less than $SO million,
scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating 2 such instances.
0 points for "Yes" if more than 2 such instances.
If the firm's average gross revenues for the last three years was more than DSO million,
scoring is as follows:
S points for either "No" or "Yes" indicating 1, 2, or 3 .such instances.
3 points for "Yes" indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances.
24
t
2. Has the federal Occupational Safety and Health Administration cited and assessed
penalties against your firm in the past five years?
Note: If you have filed an appeal of a citation and the appropriate appeals Board
has not yet ruled on your appeal, you need not include information about it.
^ Yes ^ No
If yes, attach a separate signed page describing each citation.
If the firm's average gross revenues for the last three years was less than DSO million,
scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating. 2 such instances.
0 points for "Yes" or if more than 2 such instances:
If the firm's average gross revenues for the last three years was more than DSO
million, scoring is as follows:
S points for either "No" or "Yes" indicating 1, 2, or 3 such instances.
3 points for "Yes" indicating either 4 or S such instances.
0 points for "Yes" if more than S such instance,
3. Has the EPA or any Air Quality Management District or any Regional Water Quality
Control Board cited and assessed penalties against either your firm or the owner of a
project on which your firm was the contractor, in the past five years?
NOTE: If you have filed an appeal of a citation and the Appeals Board has not yet
ruled on your appeal, or if there is ~a court appeal pending, you need not include
information about the citation. -
^ Yes ^ No
If the firm's average gross revenues for the last three years was less than DSO million,-
scoring is as follows:
S points for either "No" or "Yes" indicating 1 such instance.
3 points for "Yes" indicating 2 such instance
0 points for "Yes" or if more than 2 such instances
If the firm's average gross revenues for the last three years was more than DSO million,
scoring is as follows:
S points for either "No" or "Yes" indicating 1, 2, or 3 such instance
3 points for "Yes"indicating either 4 or S such instances.
0 points for "Yes" if more than S such instances.
25
,..
4. How often do you require documented safety meetings to be held for construction
employees and field supervisors during the course of a project?
3 points for an answer of once each week or more often.
0 points for any other answer
5. List your firm's Experience Modification Rate (EMR) (California workers' compensation
insurance) for each of the past three premium years:
NOTE: An Experience Modification Rate is issued to your firm annually by your
workers' compensation insuraace carrier.
Current year:
Previous year:
Year prior to previous year:
If your EMR for any of these three years is or was 1.00 or higher, you may, if you wish,
attach a letter of explanation.
NOTE: An Experience Modification Rate is issued to your firm annually by your
workers' compensation insurance carrier.
S points for three year average EMR of . 9S or less
3 points for three year average of EMR of more than .9S but no more than 1.00
0 points for any other EMR
6. Within the last five years, has there ever been a period when your firm had employees but
was without workers' compensation insurance or state-approved self-insurance?
^ Yes ^ No
S points for either "No" or "Yes" indicating 1 such instance.
0 points for any other answer.
26
7. Has there been more than one occasion during the last five years on which your firm was
required to pay either back wages or penalties for your own finm's failure to comply with the
state's prevailing wage laws?
^ Yes ^ No
NOTE: This question refers only to your own firm's violation of prevailing wage taws,
not to violations of the prevailing wage taws by a subcontractor.
If your firm's average gross revenues for the last three years was less'than $SO million,
scoring is as follows:
S points for either "No, " or "Yes" indicating either 1 or 2 such instance.
3 points for "Yes" indicating 3 such instances.
0 points for "Yes" and more than 3 such instances:
If your firm's average gross revenues for the last three years was more than $SO
million, scoring is as follows:
S points for either "No" or "Yes" indicating no more than 4 such instances.
3 points for "Yes" indicating either S or 6 such instances.
0 points for "Yes" and more than 6 such instances.
8. During the last five years, has there been more than one occasion on which your own firm
has been penalized or required to pay back wages for failure to comply with the federal
Davis-Bacon prevailing wage requirements?
^ Yes ^ No
If your firm's average gross revenues for the last three years was less than $SO million,
,scoring is as follows:
S points for either "No, " or "Yes" indicating either 1 or Z such instance.
3 points for "Yes" indicating 3 such instances.
0 points for "Yes" and more than 3 such instances.
If your firm's average gross revenues for the last three years was more than $SO
million, scoring is as follows:
S points for either "No" or "Yes" indicating no more than 4 such instances.
3 points for "Yes" indicating either S or 6 such instances. _~,
0 points for "Yes" and more than 6 such instances.
27
9. Provide the name, address and telephone number of the apprenticeship program
sponsor(s) (approved by the California Division of Apprenticeship Standards) that will
provide apprentices to your company for use on any public work project for which you
are awarded a contract by the City of Tustin.
S points if at least one approved apprenticeship program is listed.
0 points for any other answer.
I0. If your firm operates its own State-approved apprenticeship program:
(a) Identify the craft or crafts in which your firm provided apprenticeship training in
the past year.
(b) State the year in which each such apprenticeship program was approved, and
attach evidence of the most recent California Apprenticeship Council approval(s)
of your apprenticeship program(s). .
(c) State the number of individuals who were employed by your firm as apprentices
at any time during the past three years in each apprenticeship and the number of
persons who, during the past three years, completed apprenticeships in each craft
while employed by your firm.
S points if one or more persons completed an approved apprenticeship while employed
by your firm.
0 points if no persons completed an approved apprenticeship while employer by your
firm.
28
s
1 t . At any time during the last five years, has your firm been found to have violated any
provision of California apprenticeship laws or regulations, or the laws pertaining to use of
apprentices on public works?
NOTE: You may omit reference to any incident that occurred prior to January 1,
1998 if the violation was by a subcontractor and your firm, as general contractor on
a project, had no knowledge of the subcontractor's violation at the time they
occurred.
^ Yes ^ No.
If yes, provide the date(s) of such findings, and attach copies of the Department's final
decision(s).
If your firm's average gross revenues for the last three years was less than $SO million,
scoring is as follows:
S points for either "No,"or "Yes" indicating either 1 or 2 such instance.
3 points for "Yes" indicating 3 such instance
0 points for "Yes" and more than 3 such instances.
If your firm's average gross revenues for the last three years was more than $SO
million, scoring is as follows:
S points for either "No" or "Yes" indicating no more than 4 such instances.
3 points for "Yes" indicating either S or 6 such instances.
0 points for "Yes" and more than 6 such instances.
29
EXHIBIT D
MODEL INTERVIEW QUESTIONS
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
Tustin Library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS ANO QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: BERNARDS
REFERENCE # 1 REFERENCE # 2
GIUESTION Dr. Pat Godfrey, Fullerton Paul Mang, Ocean Park
School District (714) 447-7400 Hotels, CourtyaM by Marriott
- Valencia (805) 432-8225
Brief description of the project $65 mil new school from ground 141 room 3 story hotel with
up -acted as CM banquet rooms and kitchen
facilities, included all sitework,
pools and spa. Acted as CM
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresobed on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to be deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 9 9
ersonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 9 8
su rvision? Max. 10 ints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on 9 8
the 'ob? Max. 10 ints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other paperwork, including change order paperwork and scheduling 9 10
u ates? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 9 9
schedule that our a enc usiness roved? Max. 10 ints
7 Was the project completed on time? (10 points if the answer is "Yes°).
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 8 8
the contractor res nsible for the dale in com letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 7 9
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 8 10
contractor integrated the change order work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of turning in Operation & Maintenance manuals, completing as- 8 ~
built drawings, providing required training and taking care of warranty items? (Max. 10
oints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were -
an unusually high number of claims, given the nature of the project, or unusual 8 10
difficul in resolvin them. Max. 10 'nts
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 10 8
interviewed knows of no such difficulties, the score on this question should be "10.°)
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work 9
overall? Max. 10 ints
TOTAL SCORE: 103 !i'6
PASS PASS
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: ERICKSON-HALL
REFERENCE # 1 REFERENCE # 2
QUESTION Cherokee Point Elementary La Mesa Fire Station #11
School Roger Garza (619) 571- Matt Souttsre (619) 667-1171
8719
Brief description of the project 60,000 sf elementary school w/ 2 Fire Station 8 Emergency Ops
playgrounds, steel construction center. 21,000 sf steel bldg w
wood framing, included all site
development work, complex
'ob
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to be deducted is 5 oints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 9 9
rsonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 10 8
su rvision? Max. 10 ints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on 10 9
the 'ob? Max. 10 ints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other papennrork, including change order paperwork and scheduling 10 9
u etas? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 10 8
schedule that our a nc business a roved? Max. 10 ints
7 Was the project completed on time? (10 points if the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 10 7
the contractor res nsible for the dale in com lotion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to pertorm change order work. 10 7
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 9 9
contractor integrated the change onier work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of turning in Operation & Maintenance manuals, completing as- 9 5
built drawings, providing required training and taking care of warranty items? (Max. 10
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual - 9 8
difficu in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 10 10
interviewed knows of no such difficulties, the score on this question should be "10.")
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work 10 9
overall? Max. 10 oints
TOTAL SCORE: 116 98
PASS PASS
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION 111: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: GKKWORKS
REFERENCE # 1 REFERENCE # 2
QUESTION Carl Heimberger, City of Carl Hstmbsrgsr, City of
Anaheim 14 765-4306 Anaheim 14 765-4306
Brief description of the project West Anaheim Youth Center - Haskett Branch Library -
was a police facility, community Construction of new library
center and gymnasium
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to be deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 6 9
ersonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate ~ 8
su rvision? Max. 10 ints
4 On a scale of 1-10, with 10-being the best, was there adequate equipment provided on ~ 9
the 'ob? Max. 10 'nts
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other papennrork, including change order paperwork and scheduling 8 9
u ates? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project H 9
schedule that our a en business a roved? Max. 10 ints
7 Was the project completed on time? (10 points ff the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 4 10
the contractor res nsible for the dale in com lotion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 8 8
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor perforrned the work after a change order was issued, and 'how well the 8 9
contractor integrated the change order work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of fuming in Operation 8~ Maintenance manuals, completing as- 6 6
built drawings, providing required training and taking care of warranty items? (Max. 10
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 6 7
difficul in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 6 ~
interviewed knows of no such difficulties, the score on this question should be "10.")
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work 8 9
overall? Max. 10 ints
TOTAL SCORE: 78 101
PASS PASS
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS ANO QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: HARBOR CONSTRUCTION
REFERENCE # 1 REFERENCE # 2
QUESTION Louis Cunningham, Oxnard Hal Arbogast, City of
Union High School (805) 385- Cerritos, Cerritos Senior
2562 Center S62 860-0311
Brief description of the project Modernization of 4 high schools 5,000 sf addition to an existing
facility that remained in service
during construction, incl all
trades 8~ some site work
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more _2 0
than 120. days ago? (1 point for each is deducted from overall score; maximum
amount to be, deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 8 8
rsonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate ~ 8
su rvision? Max. 10 ints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on 9 7.5
the 'ob? Max. 10 ints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other papenerork, including change order papennrork and scheduling 9 7
u ales? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 8 9
schedule that our a nc business roved? Max. 10 ints
7 Was the project completed on time? (10 points if the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 10 10
the contractor res nsibie for the dale in corn letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 5 7
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 8 8 5
contractor integrated the change order work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of turning in Operation & Maintenance manuals, completing as- 9 8
built drawings, providing required training and taking care of warranty items? (Max. 10
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 5 8
difficul in resoivin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 10 10
interviewed knows of no such difficulties, the score on this question should be "10.")
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work 9 8
overall? Max. 10 ints
TOTAL SCORE: 95 99
PASS PASS
Tustin Library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: HOWARD S. WRIGHT CONSTRUCTORS
REFERENCE # 1 REFERENCE # 2
GIUESTION Steve Cary, Washington Kelty Saito, South Park RPO,
Mutual, Irvine Campus LLC, Eileven (503) 502-8700
E:x nsion 206 500-3362
Brief description of the project Construction of an 89,000 sf bldg Construction of 176 condo
and 1,600 car parking garage units in a 13 story bldg w/ retail
on ground floor and parking
beneath.
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to be deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 6 8
ersonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 10 8
su rvision? Max. 10 oints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on 10 7
the 'ob? Max. 10 oints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other paperwork, including change order paperwork and scheduling 9 8
u ates? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 8 8
schedule that our a enc business a roved? Max. 10 ints
7 Was the project completed on time? (10 points ff the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 9 10
the contractor res nsible for the dela in com lotion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 8 7
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 8 8
contractor integrated the change order work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of turning in Operation 8- Maintenance manuals, completing as- 8 8
built drawings, providing required training and taking care of warranty items? (Max. 10
ints '
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 10 7
difficul in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 10 10
interviewed knows of no such difficulties, the score on this question should be "10.")
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work 10 8
overall? Max. 10 ints
TOTAL SCORE: 106 97
PASS PASS
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: MORILLO CONSTRUCTION, INC.
REFERENCE # 1 REFERENCE # 2
CtUEST10N Gary Attridge, Azusa Unified, Nabih Balady, City of LA,
Gladstone & Valleydale ES, Pacan Park Gymnasium,
(949) 500-2625 (213) 97&1900
Brief description of the project Elementary school modernization Approx 9,000 sf indoor
project gymnasium, incl BB court.
Steel & concrete structure with
CMU & nice arch details, also
all sitework
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to tie deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate ~ 9
rsonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate ~ 9
su ervision? Max. 10 ints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on 9 10
the 'ob? Max. 10 ints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other papennrork, including change order paperwork and scheduling 5 10
u ates? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 4 8
schedule that our a nc usiness a roved? Max. 10 ints
7 Was the project completed on time? (10 points if the answer is "Yes").
Or, if the answer is °no," on a scale of 1-10, with 10 being the best, to what extent was 10 10
the contractor res nsible for the dela in com letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 4 7.5
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 6 10
contractor integrated the change order work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
. performing in the area of turning in Operation & Maintenance manuals, completing as- ~ 8 5
built drawings, providing required training and taking care of warranty items? (Max. 10
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 6 8
difficul in resolvin them. Max. 10 oints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the persori being 10 ~
interviewed knows of no such difficulties, the score on this question should be "10.")
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work 9 9
overall? Max. 10 oints
TOTAL SCORE: 84 106
PASS PASS
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PRQJECTS:AND QUALITY.OF PERFORMANCE - ~ - ~ -. •
DIR RECOMMENDS A SCORING SYSTEM Tt•WOULD~ALLOW •A MAXIMUM SCORE OF I20 POINTSfOR EACH INTERVIEW: FOR ~'HESE QUESTIONS, DIR ~ ~:
RECOMMENDS QUALIFICATION FORA CQNTR~iCTOR WHOSE SCORE CAN EACHiNTERVtEW IS 72 POIN,TS.OR MORE, A DENIAt~OF RRE-QtlAi1F1.CAT10N _•; ., ,
FOR A.CONTRACTOR WHOSE.SCORE ON Et~IER iNTER1/fEW IS LESS THAN 55 pOtNTS, AND AN ADDITIONAL WI'[H ANOTHER REFEREi~CE IF;•THE•SCORE ' .' " ~ ,
RESULTING FRAM ONE INTERVIEW IS BETWI(EElit 55 POINTS AND 72 POINTS. '.
CONTRACTOR: P.H. HAGOPIAN CONTRACTOR, INC.
REFERENCE # 1 REFERENCE # 2
_
- QUESTION Mark Bauer, Capistrano Unified 6olb•tenz, PJHM-A~Aftects,
School District, Canyon Vista .Laguna Niguel Elementary
(949) 234-9543. School, (949) 496.8191
Brief description of the project New construction of an Stick framed with some steel,
elementary school Type Vstructure - 30
classrooms
• :1 •~ Are there any outstanding stow notices, hens, or cleians-by the contractoF that are _ , , ,• ,, -
- ~ currently unresolved omc~atrapts for which notices of con}pietion were. recorded more _ - ~
_ •
than 120•days ago?. (1,poirrt,for each is deducted.frocn overaA score# maximwn ~
- ~ _ _
0 •
_ - _. , ••
amount to be deducted is 5 oints
- 2 On a scale~of-1-10, with.l0 t~ingthe best, did~he•eontractorprovide.adequatflt ~• -., :. -
ersonnel? Max. 10 oints 10 9
. 3 On a scaio~of 1-10, with 10•beingthe best, did the contractor provide.adequate;. ~ " •~ ~~' n
su rvision? Max. 10 ints 10 9
R. 4' On a scale of 1-10, with 10~being the•best,.~was there adeq~te equipment provided on 10, ..
,- '`~ ~. -`
the 'ob? Max. 10 ints 7
~...5 On a scale of 1-10, with 10•being the best, was the aontractCr:timely in providing ~ ; ,, ~ ~: - T~ - -
• ~ reports and other paperwork, including change order ~papennrork.and scheduling t0 - - - 9 i ; - .. ..
u dates? Max. 10 oints
• •• .6 On a scale of 1-10, with 10 being the best, did U1e contactor. adhere to-the-pmrect - -
' w
•
chedule that our a enc usiness a roved? hlax. i0 int8 -"•.. - • • . . ~ 10 9
'
~ .
•:7 - Was the project• completed on time? {a0' points if.the answer ie"~1!es"). -:~~.. - ~ ,
Or, if the answer is "no," orna scale of 1-14, wrtb.'10 tieing the`t~est~ to: uhat:8xtent was 10 10 ~~ = .: ; . `••
the contractor res nsible~ for. the dale in com lotion? • - : , •, ; , . .
8 •. Orr a scale,vf 1-10, with 10 being the best, rate the contractor-oa the timely •? ~;.. _
- _ submission of reasonable cost and time estimates to ,perfoma~:change• order. tiwtk. ~ 10 = • -. - - - 9- - . ~ : ,
Max. 10 ints
9 On a scale of 1-10, with 10~being the best, rate the. contractor on:hbv~wetr~t#.ie•~, :~ ~ _ - ;= • - -
• , • ~ contractor performed the work after a change on~er• .was•issued, and•:how wail .tlae
~
• :. contractor. iptegrated the change •order work into the existing: wodc. •(MaFx.:l~,points). ~ 10 • _ g- • -
: v
_ -10 •.. On•a scale of 1-10, with• ]0 being: the best, rate•how has•the ~ntractoFbeera.: •,. _ • , ~ . ~ ,
~
-
- ~ - performing.in the area of ffirraing.in Opbration 8 Maintenance maneals;.completing as -
-
- -. ~
,
- •
-~:~ built drawings, .providing requiredtraining•and taking care of wacrant~iitems2=Max. 10 _ . - i0 .
,
• ~ . - ~ 9 •
ints '
1 t • . - On a scale of 1-10, with 10 bi~ing-the best, rate the.cunt"r+sctor.on•whetkrerthere.lwere • - • .-
~. °' an unusually high number of-~cFaims, given th+s nature.of_tfie proje~t,•or unusual. . • 10 g-
• .
difficul in resolvin them. Max. 10 ints _ _
~. 7 2 ~ ~ On- a scale- of .1-10, with 10~being the highest, rate'the contractoF with respect tb-tlmely . • - • _ - •
. yments by the contractor to either subcohtrActors or suppliers:: (If. the•persoe being .. - •
• -
interviewed knows of no~uch difficulties, the score on this.questioe•~rouhi~tie °10.°) ~~ , 10
- 10
- - , _
13 - • On a scale of 1-10, with 10 being the hest
how would'you
rate the-
quatt~y.of
the•wor•Ir : : ~ ~
,
.
,
.
overall? Max. 10 ints 10 .9
TOTAL SCORE: 120 108
PASS PASS
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: PINNER CONSTRUCTION COMPANY, INC.
REFERENCE # 1 REFERENCE # 2
GIUESTION Marine Scisncs~s Research Physical Sdiences Building -
Building - UCSB Gary Banks UCR Chi Kwan ((951) 827-
805 893-5684 4201
Brief description of the project 4 story building totaling approx 130,000 sf building constructed
60,000 to 65,000 sf, research between 2002 and 2005
facil'
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to be deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate ~ 8
rsonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate ~ ~
su rvision? Max. 10 ints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on 8 8
the 'ob? Max. 10 ints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other paperwork, including change order papennrork and scheduling 6 7
u ates? Max. 10 oints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 4 ~
schedule that our a enc usiness a roved? Max. 10 ints
7 Was the project completed on time? (10 points if the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 4 6
the contractor res nsible for the dale in com letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 6 6
. Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 7 8
contractor integrated the change order work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of fuming in Operation & Maintenance manuals, completing as- 8 6
built drawings, providing required training and taking care of warranty items? (Max. 10
oints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 8 6
difficul in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 10 10
interviewed knows of no such difficulties, the score on this question should be "10.")
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work ~ ~
overall? Max. 10 oints
TOTAL SCORE: 82 86
PASS PASS
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: PW CONSTRUCTION, INC.
REFERENCE # 1 REFERENCE # 2
QUESTION Jerry Hills, Jackson Fred Diamond, Community
Elementary School (714) 480- Day School, (626) 912-0665
5747
Brief description of the project Modernization project, approx New campus ground up
$10 mil ran e
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to be deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 9 10
rsonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 9 10
su rvision? Max. 10 oints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on
' 9 10
the
ob? Max. 10 oints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other paperwork, including change order paperwork and scheduling 9 10
u ates? Max. 10 ints
6 On a scale- of 1-10, with 10 being the best, did the contractor adhere to the project 10 1
schedule that our a nc business a roved? Max. 10 ints 0
7 Was the project completed on time? (10 points if the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 10 10
the contractor re nsible for the dela in corn letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 9 10
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 8 1
contractor integrated the change order work into the existing work. (Max. 10 points). 0
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of turning in Operation 8~ Maintenance manuals, completing as- 9
built drawings, providing required training and taking care of warranty items? (Max. 10 10
oints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 10 10
difficul in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 10
interviewed knows of no such difficulties, the score on this question should be "10.") 10
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work
overall? Max. 10 ints 9 10
TOTAL SCORE: 111 120
PASS PAS$
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN S5 POINTS AND 72 POINTS.
CONTRACTOR: RJ DAUM CONSTRUCTION COMPANY
REFERENCE # 1 REFERENCE # 2
GIUESTION Steven. Rabin (310) 224-4205- Giovanni Garbeliini LA
Southern Calffomia Regional Southwest College (213) 798-
Occupational Center 1821
Brief description of the project 2 story building with brick veneer, 60,000 sf 3 story building
included a career center, several (Type II), concrete & structural
offices & a dozen or so steel w/ stucco '
classrooms
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0
than 120 days ago? (1 point for each is deducted from overall score; maximum 0
amount to be deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate
rsonnel? Max. 10 ints 9 10
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate
su rvision? Max. 10 ints g 10
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on
the 'ob? Max. 10 ints 10
- 10
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
. reports and other paperwork, including change order paperwork and scheduling 9 9
u ates? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project
schedule that our a enc usiness a roved? Max. 10 ints 8 8
7 Was the project completed on time? (10 points if the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 8 8
the contractor res nsible for the dale in corn letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 9 10
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the
contractor integrated the change order work into the existing work. (Max. 10 points). 9 10
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
pertorming in the area of turning in Operation & Maintenance manuals, completing as-
built drawings, providing required training and taking care of warranty items? (Max. 10 unable to answer 8
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual unable to answer 10
difficu in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being
interviewed knows of no such difficulties, the score on this question should be "10.") 10 10
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work
overall? Max. 10 oints 10 10
TOTAL SCORE: 91 113
PASS PASS
Tustin library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: S.J. AMOROSA CONSTRUCTION CO., INC.
REFERENCE # 1 REFERENCE # 2
' GIUESTION Bob Haun, City of Alameda, Jack Schaefer, Contre Costa
Alameda Free Librery (510) 747 Community College, San
4310 Ramon Valley Center (925)
2291000 x1280
Brief description of the project 45,800 sf new library and green College center -80,000 sf with
structure classrooms, physical & life
sciences labs & computer
center
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to be deducted is 5 ints
2 On a scale of 1-10; with 10 being the best, did the contractor provide adequate 10 9
ersonnel? Max. 10 ints
3 On a scale of 1-10, .with 10 being the best, did the contractor provide adequate 10 9
su rvision? Max. 10 ints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on 8 8
the 'ob? Max. 10 oints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other paperwork, including change order paperwork and scheduling . 8 9
u ates? Max. 10 oints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 9 10
schedule that our a en usiness a roved? Max. 10 ints
7 Was the project completed on time? (10 points if the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 10 10
the contractor res nsible for the dela in corn letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 8 9
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor pertormed the work after a change order was issued, and how well the 9 9
contractor integrated the change order work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of turning in Operation 8~ Maintenance manuals, completing as- 8 9
built drawings, providing required training and taking care of warranty items? (Max. 10
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 9 9
difficul in resolvin them. Max. 10 oints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 10 10
interviewed knows of no such difficulties, the score on this question should be "10.")
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work 10 9
overall? Max. 10 oints
TOTAL SCORE: 109 110
PASS PASS
Tustin Library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: SWINERTON BUILDERS
REFERENCE # 1 REFERENCE # 2
QUESTION Denise Scribner, City of Long Long Beach Public
Beach, MacArthur Library (582) Safety/Police BldgiJenise
570-8257 Scribner, City of Lonq
Beach 582 57Q-8258
Brief description of the project 16,000 sf 1 story library building Seismic hazard mitigation &
to LEED Silver cart renovation of police facilities &
tenant im rovements
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 pant for each is deducted from overall score; maximum
amount to be deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 10 10 .
ersonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate 9 9
su ervision? Max. 10 ints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on
' 10 10
the
ob? Max. 10 ints
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other paperwork, including change order paperwork and scheduling 10 10
u tes? Max. 10 infs.
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 10 10
schedule that our a enc usiness a roved? Max. 10 ints
7 Was the project completed on time? (10 points if the answer is "Yes°).
Or, if the answer is °no," on a scale of 1-10, with 10 being the best, to what extent was 10 10
the contractor res nsible for the dale in corn letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 10 10
Max. 10 oints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 10 10
contractor integrated the change order work into the existing vuork. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
pertorming in the area of turning in Operation & Maintenance manuals, completing as- 8
built drawings, providing required training and taking care of warranty items? (Max. 10 9
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 10 10
difficul in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 10 10
interviewed knows of no such difficulties, the score on this question should be "10.°)
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work
overall? Max. 10 ints 10 10
TOTAL SCORE: 118 118
PASS PASS
Tustin Library
Pre-Qualification of Contractors Summary
13-Aug-07
PART 11: LIST OF SCORABLE QUESTIONS
SECTION III: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WRH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: W.E. O'NEIL CONSTRUCTION COMPANY
REFERENCE # 1 REFERENCE # 2
(QUESTION John Smock, US Army Corps Tim Lindholm, MTA, Division
of Engineers, Joint Strike 8 Transportation Bidg (213)
Fighter Phase 1 do II (661) 277- 922-7297
2856
Brief description of the project $30 mil conversion of existing 3 story admin & ops bldg w/
hangar & constr of outbuildings sheriff's office. Glass bldg w/
LEED silver cart
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more
than 120 days ago? (1 point for each is deducted from overall score; maximum 0 0
amount to be deducted is 5 ints
2 On a scale of 1-10, with. l0 being the best, did the contractor provide adequate
rsonnel? Max. 10 ints 10 9
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate
su nrision? Max. 10 oints 10 9
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on
the 'ob? Max. 10 ints 10 10
5 On a scale of 1-10, with 10 being the best, was the contractor timely in providing
reports and other paperwork, including change order paperwork and scheduling 10 7
u ales? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project
schedule that our a en business a roved? Max. 10 ints 10 8
7 Was the project completed on time? (10 points if the answer is "Yes°).
Or, if the answer is "no,° on a scale of 1-10, with 10 being the best, to what extent was 10 5
the contractor res nsible for the data in com lotion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 10 9
Max. 10 ints
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the
contractor integrated the change order work into the existing work. (Max. 10 points). 10 9
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of turning in Operation & Maintenance manuals, completing as-
built drawings, providing required training and taking care of warranty items? (Max. 10 10 Not Done Yet
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 10 g
difficul in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being
interviewed knows of no such difficulties, the score on this question should be "10.") 10 10
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work
overall? Max. 10 oints 10 10
TOTAL SCORE: 120 95
PASS PASS
Tustin Library
Pre-Qualification of Contractors Summary
13-Aug-07
PART II: LIST OF SCORABLE QUESTIONS
SECTION ill: COMPLETION OF RECENT PROJECTS AND QUALITY OF PERFORMANCE
DIR RECOMMENDS A SCORING SYSTEM THAT WOULD ALLOW A MAXIMUM SCORE OF 120 POINTS FOR EACH INTERVIEW. FOR THESE QUESTIONS, DIR
RECOMMENDS QUALIFICATION FOR A CONTRACTOR WHOSE SCORE ON EACH INTERVIEW IS 72 POINTS OR MORE, A DENIAL OF PRE-QUALIFICATION
FOR A CONTRACTOR WHOSE SCORE ON EITHER INTERVIEW IS LESS THAN 55 POINTS, AND AN ADDITIONAL WITH ANOTHER REFERENCE IF THE SCORE
RESULTING FROM ONE INTERVIEW IS BETWEEN 55 POINTS AND 72 POINTS.
CONTRACTOR: WOODCLIFF CORPORATION
REFERENCE # 1 REFERENCE # 2
QUESTION Vince Johnson, Lakeview Mike Hopkins, DSA
Elementary School, (3i0) 902- Inspector, Thurgood
2514 Marshall ES, (805) 290.6144.
Responses to questions 1 &
12 provided by Use Winegar
(805) 487-3918 x241
Brief description of the project Elementary school -60,000 sf on Elementary School
a 10 ac site
1 Are there any outstanding stop notices, liens, or claims by the contractor that are
currently unresolved on contracts for which notices of completion were recorded more 0 0
than 120 days ago? (1 point for each is deducted from overall score; maximum
amount to be deducted is 5 ints
2 On a scale of 1-10, with 10 being the best, did the contractor provide adequate ~ 8
ersonnel? Max. 10 ints
3 On a scale of 1-10, with 10 being the best, did the contractor provide adequate ~ ~
su rvision? Max. 10 ints
4 On a scale of 1-10, with 10 being the best, was there adequate equipment provided on 9 ~
the 'ob? Max. 10 oints
5 On a scale of 1-1Q with 10 being the best, was the contractor timely in providing
reports and other paperwork, including change order paperwork and scheduling 5 5
u ales? Max. 10 ints
6 On a scale of 1-10, with 10 being the best, did the contractor adhere to the project 5 4
schedule that our a enc usiness roved? Max. 10 ints
7 Was the project completed on time? (10 points if the answer is "Yes").
Or, if the answer is "no," on a scale of 1-10, with 10 being the best, to what extent was 4 0
the contractor res nsible for the dela in com letion?
8 On a scale of 1-10, with 10 being the best, rate the contractor on the timely
submission of reasonable cost and time estimates to perform change order work. 8 8
Max. 10 ants
9 On a scale of 1-10, with 10 being the best, rate the contractor on how well the
contractor performed the work after a change order was issued, and how well the 8 8
contractor. integrated the change order work into the existing work. (Max. 10 points).
10 On a scale of 1-10, with 10 being the best, rate how has the contractor been
performing in the area of fuming in Operation & Maintenance manuals, completing as- ~ 4
built drawings, providing required training and taking care of warranty items? (Max. 10
ints
11 On a scale of 1-10, with 10 being the best, rate the contractor on whether there were
an unusually high number of claims, given the nature of the project, or unusual 7 8
difficul in resolvin them. Max. 10 ints
12 On a scale of 1-10, with 10 being the highest, rate the contractor with respect to timely
payments by the contractor to either subcontractors or suppliers. (If the person being 6 10
interviewed knows of no such difficulties, the score on this question should be "10.")
13 On a scale of 1-10, with 10 being the best, how would you rate the quality of the work 8 ~
overall? Max. 10 ints
TOTAL SCORE: 81 76
PASS PASS
EXHIBIT E
CONTRACTOR I N FO R MATT O N
TUSTIN LIBRARY PRE-QUALIFICATION OF CONTRACTORS
EXHIBIT E
TUSTIN LIBRARY PRE-QUALIFICATION
CONTRACTOR INFORMATION
BERNARDS BROS., INC. PINNER CONSTRUCTION CO., INC.
618 San Fernando Road 1255 So. Lewis Street
San Fernando, CA 91340 Anaheim, CA 92805
Phone: 818-898-1521 Phone: 714-490-4000
Fax: 818-361-9208 Fax: 714-490-4016
Contact Person: Steve Pellegren Contact Person: John Pinner
CA License No. 302007 CA License No. 166010
ERICKSON-HALL CONSTRUCTION CO. PW CONSTRUCTION INC.
500 Corporate Drive 1905 E. Route 66, Suite 200
Escondido, CA 92029 Glendora, CA 91740
Phone: 760-796-7700 Phone: 626-857-1955
Fax: 760-796-7750 Fax: 626-857-1946
Contact Person: Dave Erickson Contact Person: Christina Fiol
CA License No. 751343 CA License No. 479948
GKKWORKS R.J. DAUM CONSTRUCTION COMPANY
2355 Main Street, Suite 220 11581 Monarch Street
Irvine, CA 92614 Garden Grove, CA 92841
Phone :949-250-1500 Phone: 714-894-4300
Fax: 949-955-1662 Fax: 714-894-4449
Contact Person: Charles Merrick Contact Person: Helen Monahan
CA License No. 774456 CA License No. 127760
HARBOR CONSTRUCTION CO., INC. S.J. AMOROSO CONSTRUCTION CO., INC.
15550 Rockfield Blvd., B-100 275 E. Baker Street, Suite B
Irvine, CA 92618 Costa Mesa, CA 92626
Phone :949-457-1888 Phone: 714-433-2326
Fax: 949-457-9888 Fax: 714-433-2329
Contact Person: Donald E. Desjardin Contact Person: Brian DerMatoian
CA license No. 761803 CA License No. 331024
HOWARD S. WRIGHT CONSTRUCTORS, LP SWINERTON BUILDERS
2121 Alton Parkway, Suite 150A 17731 Mitchell North, Suite 200
Irvine, CA 92606 Irvine, CA 92614
Phone :949-608-3474 Phone: 949-622-7000
Fax: 949-567-1915 Fax: 949-477-3085
Contact Person: Joe Martino Contact Person: Sam Laham
CA License No. 860938 CA License No. 92
MORILLO CONSTRUCTION W.E. O'NEIL CONSTRUCTION CO.OF CALIFORNIA
227 N. Holliston Ave. 5245 Pacific Concourse Drive, #260
Pasadena, CA 91106 Los Angeles, CA 90045
Phone :626-796-3800 Phone: 310-643-7900
Fax: 626-792-4669 Fax: 310-643-6541
Contact Person: Antoine B. Morillo Contact Person: Shaun Guertin
CA License No. 326965 CA License No. 494031
P.H. HAGOPIAN CONTRACTOR WOODCLIFF CORPORATION
778 W. Town & Country Road 1849 Sawtelle Blvd. Suite 610
Orange, CA 92868 Los Angeles, CA 90025
Phone :714-633-1222 Phone: 310-312-1400
Fax: 714-633-1459 Fax: 310-312-1403
Contact Person: Paul H. Hagopian Contact Person: Babak Nehoray
CA License No. 408967/492286 CA License No. 719883
X
L
C7
Z "B" ST.
m N
.. ~
C
Z
r
W
r~
x
Z
Cn
O
Z
~D
O
fTl
I_n
Z
O
O
U1
r ~
O ~
n O
D
~ ~
m
\~ ~
~o ~
~ 'pT
~a~
Fs~~
0
N
-1
"A" ST.
D_
Z "B" ST.
~ ~
m ~ ~ ~ PEPPER-
m C7 TREE PARK
"C" ST.
m
0
z
v
N
EL CAMINO ~ REAL
~ ~
0
S. PROSPECT AV.
\F
a
l J
O
C
07
~_
Z
HALL
m
€~
CENTENNIAL WY.
~~~~ o rr 09'2.
0
_ Orange County Public Library
V M 1501 E. ST. ANDREW PLACE, SANTA ANA, CA 92705 (714) 566-3000
(~ `4.. ~Y; ti4'
9ZIF04~
Helen Fried
ACTING COUNTY LIBRARIAN
u
u
ADMINISTRATION
August 21, 2007
AUG 2 7 2007
Ms. Christine Shingleton, Assistant City Manager
City of Tustin -City Hall
300 Centennial Way
Tustin, CA 92780
Subject: New Tustin Library Construction
Dear Ms. Shingleton;
DECEIVED
Orange County Public Library has reviewed the plans as submitted by the architects,
Field Paoli. We appreciate the involvement the City of Tustin afforded us during the
planning process and we are very satisfied with the plans to construct the new Tustin
Branch Library. We look forward to partnering with the City of Tustin by providing the
best library service we can.
Sincerely,
!~l
~~
Helen Fried
Acting County Librarian
ALISO VIEJO ~ BREA • COSTA MESA • COSTA MESA/MESA VERDE • COSTA MESA TECHNOLOGY • CYPRESS • DANA POINT • EL TORO • FOOTHILL RANCH
FOUNTAIN VALLEY • GARDEN GROVE/CHAPMAN • GARDEN GROVE REGIONAL • WEST GARDEN GROVE • IRVINE/I-IERITAGE PARK REGIONAL • IRVINE/UNIVERSITY PARK
1RVINE/WHEELER RANCH • LA HABRA • LA PALMA • LADERA • LAGUNA BEACH • LAGUNA HILLS TECHNOLOGY • LAGUNA NIGUEL • LAGUNA WOODS • LOS ALAMITOS/ROSSMOOR
RANCHO SANTA MARGARITA • SAN CLEMENTE • SAN JUAN CAPISTRANO REGIONAL • SEAL BEACH/MARY WILSON • SILVERADO • STANTON • TUSTIN • VILLA PARK • WESTMINSTER
Tustin Library
Project Manual
August 27, 2007
Bid Set
Available For Review In City Clerk's Office