SUBJECT: AUTHORIZATION TO ADVERTISE FOR BIDS FOR F.Y. '83-'84 SIDEWALK
AND CURB REPAIR PROGRAM
RECOMMENDATION:
It is recommended that the City Council, at their meeting of June 6, 1984, adopt the
attached Resolution approving the plans and specifications for subject project and
directing the City Clerk to advertise for bids.
RAC.Kr,Rniimn
Subject project encompasses repair of concrete sidewalk, drive aprons, and curb
and gutter at 156 locations throughout the City.
The Engineers estimate for this project is $54,500.00. There is presently
$49,100.00 budgeted for the project. Additional funds will need to be'transferred
from Account 2915., Street & Alley Repair, if the low bid exceeds the budgeted
amount.
The tentative schedule for this project is as tabulated below:
City Council Authorization to Advertise --------------------------
June 6, 1984
1st Legal Advertisement ------------------------------------------
June 14.,
1984
2nd Legal Advertisement ------------------------------------------
June 21.,
1984
Open Bids --------------------------------------------------------
July 10,
1984
City Council Awards Contract -------------------------------------
July 16,
1984
Begin Construction -----------------------------------------------
August 1,
1984
Complete Construction --------------------------------------------
September
30., 1984
Z4,Qci 6a.,uZ
Dale A. Wick
Assistant City Engineer
DAW:jr