HomeMy WebLinkAboutMAIN ST W 225 12/04/1994To: Planning Dept.
Subject: Proposed new wheelchair ramp
`Dustin Presbyterian Church
225 W. Main St., Tustin, CA
for the:
12-4-94
The attached drawing defines the proposed new wheelchair
ramp and handrails. The handrails are identical to the
existing handrail on the church front steps except the
vertical bars are closer spaced.
The drawing also shows proposed modifications to the
courtyard where tree roots have lifted some of the concrete.
We propose removing the offer,;ling trees and the lifted and
damaged concrete. We propose replacing the two trees with
ficus benjamina which have very invasive root systems. We
will surround each root ball with a two foot deep plastic
cylinder. Outside the cylinder will be a six or eight inch
wide ditch full of crushed pock. This rock filled ditch
will be fed from an existing watering system so that the
trees will be deep watered. This will protect our new
concrete from the tree's root systems.
We propose replacing the existing wooden benches with
slumpstone walls with capping stones. The slumpstone will be
uncolored and the cap stones have a whiter tone than plain
cement. (the present planters on the west side of the
courtyard have slumpstone walls and caps that are a pale
salmon color. This color is not presently available.).
Finally we plan to paint the vertical walls of the new ramp
the same white as the walls of the church. The legs of the
handrail that overlap this wall will also be painted white.
These walls will be behind the ferns, pittosporum and
rhapiolepis that we will replace in that planter after the
new ramp is completed.
We believe this new ramp will be much safer, meet present
code requirements and still blend in well with our 65 year
old church building.
Please see three attached photos showing two views of the
courtyard/ramp area and a picture of the kind of ficus tree
we plan to plant in the courtyard.
TUSTIN PRESBYTERIAN CHURCH
12-16-94
Bids and other costs to build a new wheelchair ramp and to repair and
replant the courtyard.
WHEELCHAIR RAMP
$1200 Bid to demolish existing ramp and concrete wall. Remove debris.
$2500 Not to exceed bid to install new concrete ramp and steps.
Contractor: Jim Berkstresser - Santa Ana
$1280 Bin on wrought iron railing to match that on the front steps of
the church. Bid includes painting - satin black.
Contractor: Bob's Ornamental Metals - Orange
COURTYARD REPAIRS
$2400 Bid to demolish that part of the courtyard that has been lifted
by tree roots. Bid includes removal of two trees including the
tree stumps. Remove debris.
$2350 Install new concrete. Note that the red tile areas by the two
center trees will be replaced by concrete.
$1000 Install one 12 foot long by 18 inch high cement block bench with
2 foot long capping stones. Install four 6 foot long by 18 inch
high cement block benches with 2 foot long capping stones. (see
12" x 12" sample capping stone and drawing in church office).
Contractor: Jim Berkstresser - Santa Ana.
$500 Cost of two Ficus Benjamina trees in 30" tubs and two plastic
root shields. (trees will be installed by the SWAT team)
$11,230 total