HomeMy WebLinkAboutPC RES 3919
RESOLUTION NO. 3919
A RESOLUTION OF THE CITY OF TUSTIN PLANNING COMMISSION
RECOMMENDING THAT THE CITY COUNCIL FIND THAT THE MCAS
PROGRAM ENVIRONMENTAL IMPACT STATEMENTI
ENVIRONMENTAL IMPACT REPORT (MCAS TUSTIN PROGRAM
EIS/EIR) IS ADEQUATE TO SERVE AS THE PROJECT EIS/EIR FOR
VESTING TENTATIVE TRACT MAP 16695, THAT THE MCAS
PROGRAM EIS/EIR (MCAS TUSTIN PROGRAM EIS/EIR) IS
ADEQUATE TO SERVE AS THE PROJECT EIS/EIR FOR CONCEPT
PLAN 04-001, DESIGN REVIEW 04-010, CONDITIONAL USE PERMIT
04-015, AND VARIANCE 04-002, AND THAT ALL APPLICABLE
MITIGATION MEASURES HAVE BEEN INCORPORATED INTO THE
PROJECT AS REQUIRED BY THE CALIFORNIA ENVIRONMENTAL
QUALITY ACT.
The Planning Commission of the City of Tustin does hereby resolve as follows:
I.
II.
The Planning Commission finds and determines as follows:
A.
That Concept Plan 04-001, Vesting Tentative Tract Map 16695, Design
Review 04-010, Conditional Use Permit 04-015, and Variance 04-002 are
collectively considered a "project" pursuant to the terms of the California
Environmental Quality Act;
B.
That the Marine Corps Air Station (MCAS) Tustin Reuse Plan/Specific
Plan Final Environmental Impact Statement/Environmental Impact Report
(FEIS/EIR) was certified by the City Council on January 16, 2001. The
FEIS/EIR considered the potential impacts associated with development
on the former Marine Corps Air Station, Tustin, including development of
commercial uses within Planning Areas 16,17, and 19.
C.
That an initial study checklist, attached as Exhibit A hereto, was prepared
to evaluate the potential impacts associated with the Project. The initial
study checklist demonstrates that all potential impacts of the Project were
addressed by the certified FEIS/EIR, no additional impacts have been
identified, and all applicable mitigation measures in the FEIS/EIR will be
implemented through the Mitigation Monitoring Program for the Project
(Attachment 2 of Exhibit A), Disposition and Development Agreement 04-
02, or as conditions of approval of the Project.
The Planning Commission hereby recommends that the City Council find for
Vesting Tentative Tract Map 16695 and hereby finds for Concept Plan 04-001,
Design Review 04-010, Conditional Use Permit 04-015, and Variance 04-002
that this Project is within the scope of the previously approved MCAS Tustin Final
Resolution No. 3919
Page 2
Program EIS/EIR previously certified on January 16, 2001, that the
environmental effects of the Project are within the scope of the MCAS Tustin
FEIS/EIR and were fully examined in the MCAS Tustin FEIS/EIR; that no
substantial changes are proposed in the Project or have occurred with respect to
circumstances under which the Project is being undertaken since certification of
the MCAS Tustin FEIS/EIR; no new information has become available since the
certification of the MCAS Tustin FEIS/EIR, and pursuant to Public Resources
Code Section 2116 and the requirements of CEQA regulations promulgated with
respect thereto including Title 14 California Code of Regulations Sections 15162
and 15168( c), no additional environmental analysis, action or document is
required by the CEQA.
PASSED AND ADOPTED by the Planning Commission of the City of Tustin, at a
regular meeting on the 26th day of July, 2004.
a~~4.~5~-
ELIZABETH A. BINSACK
Planning Commission Secretary
STATE OF CALIFORNIA)
COUNTY OF ORANGE)
CITY OF TUSTIN )
I, ELIZABETH A. BINSACK, the undersigned, hereby certify that I am the Planning
Commission Secretary of the Planning Commission of the City of Tustin, California; that
Resolution No. 3919 duly passed and adopted at a regular meeting of the Tustin
Planning Commission, held on the 26th day of July, 2004.
a ;"~.A"~ ~ ~-I:
ELIZABETH A. BINSACK
Planning Commission Secretary
~--r--- - - ~-~-