� � rAGENDA REPORT
MEETING DATE: FEBRUARY 6, 2018
TO: JEFFREY C. PARKER, CITY MANAGER
Agenda Item
Reviewed:
City Manager
Finance Director
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: AWARD CONTRACT FOR THE PETERS CANYON CHANNEL
IMPROVEMENTS CONSTRUCTION PROJECT, CIP NO. 50040
SUMMARY
Staff is recommending that the City Council award the construction contract for the Peters
Canyon Channel Improvements Construction Project, CIP No. 50040 to the lowest responsive /
responsible bidder, KEC Engineering.
RECOMMENDATION
It is recommended that the City Council award the construction contract for the Peters Canyon
Channel Improvements Construction Project, CIP No. 50040 to the lowest
responsive/responsible bidder, KEC Engineering, in the amount of $12,843,929.90 and
authorize the Mayor and the City Clerk to execute the contract documents on behalf of the City.
The engineer's estimate was $16,100,000.00.
FISCAL IMPACT
Sufficient funds in the amount of $20,631,000 have been budgeted for this project in the Fiscal
Year 2017-2018 Capital Improvement Program budget. The total estimated expenditure for the
construction of this project is $13,850,057.90. The project is funded through Legacy Backbone
Infrastructure Fees (Fund 187), Community Facilities District 14-1 (Fund 443), and MCAS Tax
Allocation Bonds (Fund 561).
Project expenditures include:
• Construction Contract................................................................. $ 12,843,929.90
• Geotechnical Engineering and Materials Testing ...........................$ 430,000.00
• Construction Management and Inspection ...................................$ 412,128.00
• Construction Engineering/Support................................................$ 164,000.00
• Estimated Expenditures...........................................................$ 13,850,057.90
The remaining budgetary appropriation will be set aside as project contingency for potential
unforeseen conditions that may arise necessary to complete the work within the approved
project scope and budget.
Award Contract for Peters Canyon Channel Improvements, CIP No. 50040
February 6, 2018
Page 2
CORRELATION TO THE STRATEGIC PLAN
The construction of Peters Canyon Channel Improvements contributes to the fulfillment of three
goals in the City's Strategic Plan. First is contribution to the fulfillment of the City's Strategic
Plan Goal A: Economic and Neighborhood Development; specifically implementation of Strategy
#1 which, among other items, is to develop critical phases of Tustin Legacy. Secondly is
implementation of Goal B, Strategy #3 to ensure public safety and protection of assets through
continuous maintenance and improvement of public facilities. Lastly the agreement also
addresses Goal D, Strategy #2 by working collaboratively with agencies to address issues of
mutual interest and concern.
DISCUSSION AND BACKGROUND
The City, the Orange County Flood Control District (OCFCD), and the County of Orange
entered in to Cooperative Agreement D02-119 dated March 11, 2003 to establish terms and
conditions under which certain Peter's Canyon Channel Flood Control Improvements are to be
scheduled, engineered, financed, constructed, operated, and maintained. Amendment No. 3 to
Cooperative Agreement D02-119, approved on July 5, 2017 and signed by the County on
August 4, 2017 increased the residential certificate of occupancy limit of 1,200 units, established
in the second amendment to the agreement with the OCFCD and the County of Orange, by an
additional 200 units to 1,400 units. Prior to that limit being reached, a contract for the
construction of the Peter's Canyon Channel Improvements is required to be awarded and
construction commenced.
The Peters Canyon Channel Improvement project from north of Edinger Avenue to just north of
Warner Avenue consists of widening the channel by approximately thirty feet along the eastern
edge and construction of a concrete channel lining. The project will also provide improvements to
the pedestrian and bicycle trail on the east side of the channel.
The City Council adopted Resolution No. 17-54 approving the plans and specifications and
authorized and directed the City Clerk to advertise for Project bids on November 7, 2017. The
Project was advertised and the bids were opened on December 19, 2017 and evaluated.
Eleven (11) bids were received by the noticed deadline and are summarized as follows:
• USS CAL BUILDERS, Inc . ..........................................
• KEC Engineering.........................................................
• Ortiz Enterprises, Inc ...................................................
• OHL USA, Inc..............................................................
• Bosco Constructors, Inc . .............................................
• Sukut Construction, LLC ..............................................
• Reyes Construction, Inc . .............................................
• Los Angeles Engineering, Inc ......................................
• SEMA Construction, Inc . .............................................
• Innovative Construction Solutions ...............................
• Environmental Construction, Inc ..................................
................$ 10,729,000.00
................$ 12,843,929.90
................$ 13,684,319.20
................ $ 14, 384, 600.60
................$ 14,444,444.00
................ $ 14, 584,256.50
................ $ 14, 832, 554.00
................$ 15,498,000.00
................$ 16,873,603.40
................$ 18,518,278.00
................ $ 20, 843, 797.00
On December 22, 2017, USS CAL BUILDERS, Inc. submitted a letter requesting withdrawal of
their bid due to a clerical error regarding bid item no. 27. This letter was submitted timely within
five (5) business days of the bid opening. After consultation with the City Attorney's office, staff
recommends accepting the withdrawal of USS CAL BUILDER's bid, return of their bid bond, and
Award Contract for Peters Canyon Channel Improvements, CIP No. 50040
February 6, 2018
Page 3
awarding the construction contract to the next lowest responsive/responsible bidder, KEC
Engineering. _
uglAs. S,fack, P.E.
e or fVublic Works/City Engineer
Attachment(s):
1. Location Map
2. USS CAL BUILDERS' Withdrawal Letter
ATTACHMENT 1
Location Map
LOCATION MAP
Peters Canyon Channel
Improvements Constructic
Project
TUSTIN
RANCH
TUSTM LEGACY
PROJECT LOCATION
Peters Canyon Channel
(CIP No. 50040) Improvements
Construction Project
r
FILE: CIP 50040 Peters Canyon Channel.dwg
NO SCALE
ATTACHMENT 2
USS Cal Builders' Withdrawal Letter
Department of Public Works - Engineering
Douglas S. Stack
City of Tustin
300 Centennial Way
Tustin, CA 92780
RE: Withdrawal of Bid
Project Title: Peters Canyon Channel Improvements Construction Project
Contract Identification: CIP NO. 50040
Project Location: Peters Canyon Channel, City of Tustin
To Whom It May Concern:
USS CAL BUILDERS INC. ("USS") submitted a bid in the amount of $10,279,000.00 for the above referenced
project on December 19t", 2017, CIP NO. 50040 (the "Project"). Please be advised that this written request is
being submitted on December 22nd, 2017 within five (5) business days of the bid opening.
USS is requesting that it be allowed to withdraw its bid since a clerical error was made in writing down the
correct figure for the line item noted below.
In writing down the total amount, my assistant mistakenly input inaccurate information. On Item 27 —
PROTECT IN PLACE EDINGER BRIDGE (SHORING). Instead of writing down $1,000,000.00 he wrote down
$10,000.00 as indicated in the bid submittal. This clerical mistake resulted in the bid being materially different
than what it was intended.
As you can see from the above:
1) A mistake was made.
2) We gave the public entity written notice within five working days, excluding Saturdays, Sundays, and
state holidays, after the opening of the bids of the mistake, specifying in the notice in detail how the
mistake occurred.
3) The mistake made the bid materially different than it was intended to be.
4) The mistake was made in filling out the bid and not due to error in judgment or to carelessness in
inspecting the site of the work, or in reading the plans or specifications.
Thank you for your understanding and we look forward to working with you in the future.