Loading...
HomeMy WebLinkAbout09 AWARD CONTRACT FOR THE FISCAL YEAR 2017-18 ROADWAY REHABILITATION AND SIDEWALK REPAIR PROJECT, CIP NO. 70017r = AGENDA REPORT P- 4-3 t, MEETING DATE: JUNE 19, 2018 TO: JEFFREY C. PARKER, CITY MANAGER Agenda Item Reviewed. City Manager Finance Director FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER SUBJECT: AWARD CONTRACT FOR THE FISCAL YEAR 2017-18 ROADWAY REHABILITATION AND SIDEWALK REPAIR PROJECT, CIP NO. 70017 SUMMARY Staff is requesting the City Council award a construction contract to the lowest responsive/responsible bidder for the Fiscal Year (FY) 2017-18 Roadway Rehabilitation and Sidewalk Repair Project, CIP No. 70017. RECOMMENDATION It is recommended that the City Council award a construction contract to the lowest responsive/responsible bidder, Hardy & Harper, Inc. in the amount of $1,575,125.40, for the FY 2017-18 Roadway Rehabilitation and Sidewalk Repair Project, CIP No. 70017 and authorize the Mayor and the City Clerk to execute the contract documents on behalf of the City. FISCAL IMPACT Sufficient funds in the amount of $1,656,000 have been budgeted and appropriated in the Fiscal Year 2017-2018 Capital Improvement Program Budget. CIP No. 70017 is part of the City's ongoing Maintenance of Effort (MOE) obligation to maintain eligibility for Renewed Measure M (M2) funding. Funding is provided through a combination of General Fund (Fund 200), Measure M2 Fair Share (Fund 139), and Gas Tax (Fund 130). CORRELATION TO THE STRATEGIC PLAN Rehabilitation of roadways and repair of sidewalks contribute to the fulfillment of the City's Strategic Plan Goal B: Public Safety and Protection of Assets. Specifically, the project implements Strategy #3, which among other items, is to ensure continuous maintenance and improvement of public facilities. DISCUSSION The Roadway Rehabilitation and Sidewalk Repair Project, CIP No. 70017 for Fiscal Year 2017-18 includes asphalt concrete pavement repair, asphalt concrete overlay, slurry sealing, and traffic striping on various streets within Zone 6 of the City's Pavement Management Program. The City is divided into seven pavement management zones with one zone targeted each year for pavement maintenance. Through a rolling seven year cycle, this program is intended to maintain the integrity of City streets. The current phase, Zone 6 (attached map), is generally bounded by Santa Ana Freeway (1-5) to the north, Tustin Ranch Road to the west, Barranca Parkway to the south, and Harvard Avenue/East City Limit to the east. The project also includes citywide sidewalk repair which focuses on removal and replacement of damaged sidewalk at numerous locations throughout the City based on an annual field survey conducted by the Engineering Division. The Engineer's Estimate is $1,455,000. FY 2017-18 Roadway Rehabilitation and Sidewalk Repair Project, CIP No. 70017 June19, 2018 Page 2 Formal bids were publicly opened on May 29, 2018 and reviewed by Public Works. Five (5) bids were received and are summarized below by order of least dollar amount: • Hardy & Harper, Inc ................................... • R.J. Noble Company ................................. • Sequel Contractors, Inc ............................. • All American Asphalt ................................. • Palp, Inc. dba Excel Paving Company....... .................................. $ 1,575,125.40 .................................. $ 1,593,492.65 .................................. $ 1,595,490.85 .................................. $ 1, 659, 908.60 .................................. $ 1,746,388.00 Staff has reviewed the references and the State Contractor's License for Hardy & Harper, Inc. and has determined that they are appropriate for the subject project. It is recommended that the City Council award the construction contract to the lowest responsive/responsible bidder, Hardy & Harper, Inc. for the FY 2017-18 Roadway Rehabilitation and Sidewalk Repair Project, CIP No. 70017 and authorize the Mayor and the City Clerk to execute the contract documents on behalf of the City. Dou s Stack, P. E. Dir6ct of Public Works/City Engineer Attachment: Location Map S:\City Council Items\2018 Council Items\06-19-2018\Award of Contract for Roadway Rehab and Sidewalk Repair (CIP 70017)\Award of Contract for Rdwy Rehab (CIP 70017).docx City of Tustin, CA Citywide Zones A "FOR '�VARRENq 7.1 11 ST 7Ft- Av Z LF Legend Zone 2 3 N ........ e 4 w E 6 7 S Centerline City of Tustin, CA Citywide Zones Map 25 10.1 Bucknarn &Associates July 2013 Source: City of Tustin AutoCAD Dwg Created in ArcGIS 10.1 using ArcMap