Loading...
HomeMy WebLinkAbout10 AGREEMENT WITH COUNTY LIBRARY TO REIMBURSE COSTS OF LIBRARY COOLING TOWER RETROFIT PROJECTff1?"�Y OAGENDA REPOR MEETING DATE: TO FROM JULY 17, 2018 JEFFREY C. PARKER, CITY MANAGER MATTHEW S. WEST, ASSISTANT CITY MANAGER Agenda Item 10 Reviewed: City Manager Finance Director SUBJECT: AGREEMENT WITH COUNTY LIBRARY TO REIMBURSE COSTS OF LIBRARY COOLING TOWER RETROFIT PROJECT SUMMARY: To approve an agreement with the County of Orange and the OC Community Resources/OC Public Libraries for the City to provide up to $140,000 in reimbursements for the costs of a cooling tower retrofit project at the Tustin Library. RECOMMENDATION: Approve and authorize the Mayor to sign the "Funding Agreement Between The City Of Tustin And The County Of Orange For The Tustin Branch Library Cooling Tower Retrofit Project" attached hereto as Exhibit 1, subject to any revisions approved by the City Manager and the City Attorney that do not increase the total reimbursement above $140,000. FISCAL IMPACT: The contract would establish a maximum reimbursement from the City of $140,000. Funds for the project are in this year's approved budget. CORRELATION TO THE STRATEGIC PLAN: By providing for needed repairs to the City -owned public facility (e.g., the library's HVAC system), the agreement would advance Strategic Plan Goal B "Public Safety and Protection of Assets", Strategy 3.b. "Continue capital improvement planning to ensure continuous maintenance and improvement of flood control, park, public, traffic control and transportation facilities." BACKGROUND AND DISCUSSION: The Tustin Library is owned by the City and operated by the County of Orange pursuant to a 40 -year lease. The existing facility was constructed by the City and at City expense. The 31,500 square -foot library is a single -story building founded on a slab on grade with 1327335.1 Agenda Report: Reimbursement Agreement re Library Cooling Tower Retrofit July 17, 2018 Page 2 a large portion of the slab depressed with an 18 -inch covered steel raised floor. The steel framed structure with metal framed exterior walls are clad in a painted stucco finish with the entire north facing wall almost entirely comprised of large expansive windows with smaller window openings at the remaining elevations. Much of the electrical, ducting, and control wiring are located below the floor due to the tall ceilings and expansive window system. Prior to the discovery of the leak in the water supply for the heating and air conditioning system under the raised floor in March 2017, County and City Staff were discussing and evaluating the need for a new cooling tower unit. The current system had always struggled to provide adequate cooling given the large expansive space and patron demand. As a result, a new cooling tower is recommended to address the system as whole and improve cooling conditions with a higher level of chilled supply air. Reimbursement for this new unit will be provided by original construction savings specifically set aside for ongoing facility maintenance and operation. The County proposes to retain Emcor Services to perform the services to upgrade the cooling tower for the facility. (Emcor's proposal is attached as Exhibit 2.) Emcor's proposal anticipates costs totaling $114,930. The attached funding agreement would provide that the City will reimburse the County up to $140,000 for the project. The additional authorization will ensure the work does not need to be halted in order to obtain City Council approval in the event unexpected conditions are discovered during construction that require change orders. If the work is authorized soon, the County anticipates that the project will be completed before the library is re -opened, thus avoiding additional library closures while the cooling system is upgraded. e4 Z � �/�. V, Matt -hew S. West Assistant City Manager Attachment: 1. Funding Agreement Between The City Of Tustin And The County Of Orange For The Tustin Branch Library Cooling Tower Retrofit Project 2. June 28, 2018 Proposal from Emcor Services for Cooling Tower Upgrade 1327335.1 Exhibit I FUNDING AGREEMENT BETWEEN THE CITY OF TUSTIN AND THE COUNTY OF ORANGE FOR THE TUSTIN BRANCH LIBRARY COOLING TOWER RETROFIT PROJECT THIS AGREEMENT made and entered into this day of 2018, by and between the City of Tustin, a California municipal corporation (hereinafter referred to as "CITY") and the County of Orange, a political subdivision of the State of California, and the OC Community Resources/OC Public Libraries ("OCPL"), a County Free Public Library organized pursuant to the provisions of Education Code Sections 19100, et seq. (hereinafter referred to as "COUNTY"). The CITY and COUNTY may be referred to herein individually as a "Party" or collectively as the "Parties." RECITALS, WHEREAS, CITY owns and OCPL operates the Tustin Branch Library, located at 345 E. Main Street, Tustin, CA ("Library"); and WHEREAS, CITY desires to provide funding to COUNTY in an amount not to exceed One Hundred Forty Thousand Dollars ($140,000) for a cooling tower retrofit project ("Project") at the Library; and WHEREAS, COUNTY is willing to perform the Project at the Library; and WHEREAS, COUNTY and CITY now desire to enter into this Agreement to establish responsibilities for the Project. NOW THEREFORE, in consideration of the foregoing premises and the mutual covenants and promises herein contained, the Parties hereto agree as follows: 1. COUNTY RESPONSIBILITIES: 1.1 Upon completion of the Project, COUNTY shall submit a written invoice to CITY which will include a complete detail of the Project's expenditures. 1.2 COUNTY agrees, at the request of CITY, to make available to a representative of the CITY for examination of its data, financial records and related project reports maintained for the Project activities within ten (10) business days of the written request. The COUNTY shall retain such financial and Project records for at least three (3) years from the date of payment. 1.3 COUNTY shall retain as part of the Project records copies of all warranties provided by COUNTY's contractor(s) and equipment supplier(s) in the implementation of the Project. In the event a need arises for work or materials potentially covered by one or Page 1 of 4 1330638.1 more such warranties, COUNTY shall cooperate with CITY in requesting and coordinating implementation of the work and delivery of the materials. 2. CITY RESPONSIBILITIES: CITY shall make payment to COUNTY within forty-five (45) days of receiving a written invoice from COUNTY upon completion of the Project. City's obligation hereunder shall not exceed One Hundred Forty Thousand Dollars ($140,000). 3. IT IS MUTUALLY AGREED that: 3.1 The obligations and participation of CITY under this Agreement shall be limited solely to the discretionary issuance of funds to COUNTY in accordance with the terms of this Agreement. COUNTY shall cause its contractor(s) to have and maintain liability insurance against bodily injuries and property damage in amounts determined appropriate by the County, and to have and maintain worker's compensation insurance for any injuries during the performance of the Project. All of contractor's liability insurance policies shall be endorsed to name the COUNTY and CITY as additional insureds. Each contractor, and each of its worker's compensation insurers, shall waive all rights of subrogation against the COUNTY and CITY. County shall also cause its contractor(s) to agree to defend and indemnify the COUNTY and CITY and their elected and appointed officials, officers, agents, and employees, against any and all claims, loss, demands, damages, cost, expenses or liability arising out of the Project, except for liability arising out of the sole negligence of the COUNTY or the CITY, or their officers, agents, or employees, including the cost of defense of any lawsuit arising therefrom. 3.2 COUNTY shall be considered an independent contractor and neither COUNTY, its employees, nor anyone working under COUNTY shall be considered an agent or an employee of CITY. Neither COUNTY, its employees, contractors. nor anyone working under COUNTY shall qualify for workers' compensation or other fringe benefits of any kind through CITY. 3.3 Any written notices pursuant to this Agreement may be provided by personal delivery or regular mail and shall be addressed as set forth below or as either party may hereafter designate by written notice and shall be deemed delivered upon personal delivery or seventy-two (72) hours after deposit in the United States Mail. COUNTY OC Public Libraries 1501 E. St. Andrew Place Santa Ana, CA 92705 Attention: County Librarian Page 2 of 4 1330638.1 CITY City of Tustin 300 Centennial Way Tustin, CA 92780 Attention: City Manager 4. MISCELLANEOUS PROVISIONS: 4.1 Non -Discrimination. In the performance of this Agreement, both Parties agree that they will comply with the requirements of Section 1735 of the California Labor Code and not engage nor permit any subcontractors to engage in discrimination in employment of persons because of the race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, marital status, or sex of such persons. Both Parties acknowledge that a violation of this provision shall subject the Parties to penalties pursuant to Section 1741 of the California Labor Code. 4.2 Governing Law and Venue. This Agreement has been negotiated and executed in the State of California and shall be governed by and construed under the laws of the State of California. In the event of any legal action to enforce or interpret this Agreement, the sole and exclusive venue shall be a court of competent jurisdiction located in Orange County, California, and the Parties hereto agree to and do hereby submit to the jurisdiction of such court, notwithstanding Code of Civil Procedure Section 394. Furthermore, the parties specifically agree to waive any and all rights to request that an action be transferred for trial to another county. 4.3 Entire Agreement. This Agreement, and any other documents specifically incorporated into this Agreement, shall constitute the entire agreement between COUNTY and CITY relating to this Project. As used herein, Agreement refers to and includes any documents incorporated herein by reference and any exhibits or attachments. Except with regard to the existing Lease between the City and the COUNTY regarding the Library, this Agreement supersedes and merges all previous understandings, and all other agreements, written or oral, between the parties regarding this Project, and sets forth the entire understanding of the parties regarding the subject matter hereof. The Agreement may not be modified except by a written document signed by both parties. 4.4 Amendments. No alteration or variation of the terms of this Agreement shall be valid unless made in writing and signed by the Parties; no oral understanding or agreement not incorporated herein shall be binding on either of the Parties; and no exceptions, alternatives, substitutes or revisions are valid or binding on either Party unless authorized by either Party in writing_ 4.5 Severability. If any term, covenant, condition or provision of this Agreement is held by a court of competent jurisdiction to be invalid, void, or unenforceable, the remainder of the provisions hereof shall remain in full force and effect and shall in no way be affected, impaired or invalidated thereby. 4.6 Attorney's Fees. In any action or proceeding to enforce or interpret any provision of this Agreement, each Party shall bear their own attorney's fees, costs and expenses. This provision shall not limit the right of either party to recover the costs of a legal defense from one or more contractor(s), provided the defense is required under Section 3.2 above. Page 3 of 4 1330638.1 4.7 Consent to Breach Not Waiver. No term or provision of this Agreement shall be deemed waived and no breach excused, unless such waiver or consent shall be in writing and signed by the Party claimed to have waived or consented. Any consent by any party to, or waiver of, a breach by the other, whether express or implied, shall not constitute consent to, waiver of, or excuse for any other different or subsequent breach 4.8 Authority. The Parties to this Agreement represent and warrant that this Agreement has been duly authorized and executed and constitutes the legally binding obligation of their respective organization or entity, enforceable in accordance with its terms. IN WITNESS WHEREOF, the Parties hereto certify that they have read and understand all the terms and conditions contained herein and hereby cause this Agreement to be executed. City of Tustin Name: ELWYN A. MURRAY Title: MAYOR Dated: ATTEST: M. Name: Erica N. Yasuda Title: City Clerk Dated: County of Orange A Political Subdivision of the State of California Lo Dated: Dylan Wright, Director OC Community Resources APPROVED AS TO FORM DEPUTY COUNTY COUNSEL Dated: Deputy County Counsel Page 4 of 4 1330638.1 Ci ::COR Services Mesa Energy Systems Cooling Tower Upgrade Tustin Library 345 E Main St, Tustin, CA 92780 To: Gary Rivas Project Manager III 1501 East St. Andrew Place Santa Ana, California 92705 6/28/18 Quote # 172672 Agreement Valid for 30 Days 2 CROMWELL • IRVINE, CA 92618 • (949) 460-0460 • FAx (949) 460-8833 LICENSE #611215 (B, C-4, C-10, C-20, C-36, C38) Mesa Energy Systems Inc. is a full service mechanical contractor and energy solutions provider with an in depth background of years of experience in air-conditioning system retrofits and making buildings more efficient throughout California, Arizona, and Nevada. Our ability to provide turnkey projects gives our customers the assurance of quality, precision and professionalism. Tower Upgrade Replacement Scope of Work Per your request EMCOR Service Mesa Energy Systems is pleased to submit the following proposal as required to provide the options for a Cooling Tower replacement as discussed. The Evapco Cooling Tower will support capacity of 300 F GPM / 88 F EWT / 78 F LWT @ 73 FWB. The Tower upgrade is required to match the installed Technical Systems Air conditioners and submittal that shows the air conditioning units were designed for 78 F EWT / 88 F LWT and rated at 47.8 tons each to total 95.6 tons. The Scope of work is as follows. 1. Provide shutdown of the tower and pumps as needed with OCPW Site Technician during normal. 2. Provide disconnect and safe off of electrical and mechanical connections to the tower as required to lift for removal. 3. Provide crane removal of the Evapco tower and systems piping components that will need to be removed to accommodate the new tower as selected and per design. Provide crane Rental 40 -ton crane with trucking and disposal of the removed tower and piping no longer needed. 4. Provide installation of the new Evapco cooling tower to include rigging of the base and top sections as required on the new structural base systems as per structural design. Anchor to the structural base. 5. Provide electrical installation as needed to connect the existing VFD and wiring, vibration switch and water level systems. Provide and installed needed conduit and wiring from the POC at each component to the new tower. Provide labor and materials as required for the electrical scope of work. No new electrical breakers, VFD or disconnects will be provided for this replacement. 6. Provide installation of new inlet and outlet tower water piping as needed for the new configuration. Provide flexible connections, pipe and fittings as required for the tower loop. Provide and install water fill piping along with required drains as needed to complete the tower water and drain piping systems. Test water make up and drains as needed. Provide required pipe, valves and fittings as needed with supports and pipe clamps 8. Provide start up and testing of the tower fan, fill system and water flow operation with OCPW Site technician as required. SAN DIEGO • IRVINE • SAN FERNANDO VALLEY / VENTURA • BAKERSFIELD • FRESNO • SACRAMENTO a SAN JOSE • PLEASANTON • SAN FRANCISCO • LAS VEGAS • PHOENIX - 2 - _ tower and pumping systems back into normal BMS or Bypass operation for as directed and accomplished by OCPW Technician. 10. Clean up work area, verify the work listed is complete with OCPW personnel and demobilize. 11. Provide the closeout Documentation with Tower as selected with warranty letter. 12. Provide required labor needed to complete testing as identified in the above during normal business hours 6:00am to 4:30pm to be determined. Evapco UT 19-4HG Installation Pricing Add Cost: Engineering and Permits $ 102,880.00 $ 12,050.00 Exclusions: Structural Upgrade based on design, Cooling Tower not selected in options, VFD Replacement or Upgrade, tower SS Upper Section , tower coating or cleaning, new Tower Nozzles, chemical treatment upgrades that are required for warranty, removal or repair of the Dolphin System, Pump upgrades or repairs, AC unit repair or condenser barrel replacement, DB level increase, Overtime labor, delays or stand by time not in our control, additional work not included above, overhead structural steel revision, Water balance, added trips and expenses due to unforeseen conditions, changes if required will be proposed as requested. Standard insurance applies, regular time as needed. SAN DIEGO • IRVINE • SAN FERNANDO VALLEY/ VENTURA • BAKERSFIELD • FRESNO * SACRAMENTO • SAN JOSE • PLEASANTON 0 SAN FRANCISCO • LAS VEGAS • PHOENIX L Checked items below are included in this proposal, non -checked items are specifically excluded. Engineering, Permits & Bonds Mechanical Engineering (Add) X Structural Engineering (Add) X Electrical Engineering Plan Check Fees Mechanical Permits (Add) X Electrical Permits Structural Permits (Add) X Street Closure Permits Performance Bond Architectural Drawings Rigging and Specialty Rentals Rigging/Forklifte Scissor Lift as Required e Helicopter Other: Additional Services Comfort Air Balance Certified Air Balance Water Balance Certified Water Balance Recover Refrigerant Per EPA Guideline Dispose of old Equipment X Other Other: Project to be Performed at the below Listed Times Normal Business Hours(M-F 6am- X Overtime (other than Normal Business Hours) 4:30pm) Normal Hours and Overtime Other: Specialty Trades Electrical X Abatement Framing of Curb Runners Duct Cleaning Re -roofing of Runners Seismic Upgrades Insulation of New Ducting (As Required) Insulation of New Piping (As Required) Coring X -Ray Prior to Coring Project Completion Start Up and Commissioning eX Factory Start Up Coordination e Operation &Maintenance Manuals X Eddy Current Testing Report Additional Components New Programmable Digital Thermostat Double Wall Flue Pipe as Needed Smoke Detectors in Supply Duct Smoke Detectors in Supply and Return Ducts New HW Pump and Motor Assemblies EMCOR Retains All Salvage Rights Warranties 90 -Day Labor and Materials from Date of Beneficial Use One (1) year Labor and Materials from Date of Beneficial Use X Four (4) Year Manufacturer Extended Compressor Warranty SAN DIEGO • IRVINE • SAN FERNANDO VALLEY / VENTURA • BAKERSFIELD • FRESNO • SACRAMENTO • SAN JOSE • PLEASANTON • SAN FRANCISCO • LAS VEGAS • PHOENIX -4- Concealed Conditions If concealed or unknown conditions of an unusual nature which affect the performance of the work are encountered below the roof line or above the ceiling or in an existing part of the building other than the work, which conditions are not ordinarily found to exist or which differ materially from those generally recognized as inherent in work of the character provided for in this Agreement, notice by the observing party shall be given promptly to the other party, if possible before conditions are disturbed and in no event later than fourteen days after first observance of the conditions. The Contract Sum shall be equitably adjusted for such concealed or unknown conditions by Change Order upon claim made within fourteen days after claimant becomes aware of the conditions. Regulatory Chanqes Mesa Energy Systems Inc. shall be compensated for changes in the Work necessitated by the enactment or revision of codes, laws or regulations subsequent to the execution of this Agreement. Hazardous Materials OC Community Resources hereby agrees to indemnify, defend and hold harmless Mesa Energy Systems, Inc. and its agents, employees, consultants and subcontractors from and against any claim, damage, allegation, suit, cause of action, cost, loss, expense or injury in connection with Hazardous Materials not introduced to the Project by the Indemnified Parties, including, without limitation, all costs of remediation, experts, consultants or other costs in connection with Hazardous Materials associated with the Project. Unforeseen Conditions OC Community Resources understands and agrees that Mesa Energy Systems, Inc. shall not be liable for added costs or time delays caused by unforeseen conditions at the Project, including, without limitation, unanticipated rerouting of existing piping, fire sprinklers or gas piping. In the event that the fire sprinklers, water, electrical conduit or gas piping are required to be relocated, Mesa shall not be responsible for such work. Mesa Energy Systems, Inc. or a subcontractor under the control and supervision of OC Community Resources shall perform such work. NFPA 70E Mesa technicians are trained to understand the specific hazards associated with electrical energy according to NFPA 70E, Standard for Electrical Safety in the Workplace. They are trained in safety- related work practices and procedural requirements as necessary to provide protection from the electrical hazards associated with their respective job or task assignments. Documented safe work practices include lockout/tagout and energy isolation. Category 2 personal protective equipment is issued for electrical hazards while working on voltages between 50 and 480 volts. Mesa's policy is to remove the energized electrical hazard by working on de -energized circuits and by using the written lockout/tagout policies and procedures when feasible. SAN DIEGO • IRVINE 0 SAN FERNANDO VALLEY / VENTURA • BAKERSFIELD • FRESNO • SACRAMENTO • SAN JOSE • PLEASANTON • SAN FRANCISCO • LAS VEGAS 0 PHOENIX -5- O A. Unless stated otherwise in this agreement, services provided under this agreement will be performed during normal working hours of 7 a.m. to 5 p.m., Monday through Friday. B. The guarantees and services provided under the scope of this agreement are conditioned upon OC Community Resources operating and maintaining systems/equipment. OC Community Resources will do so in according to industry -accepted practices, or in consideration of our recommendations. C. OC Community Resources will provide and permit reasonable access to all areas where work is to be performed. Mesa Energy Systems, Inc. will be allowed to start and stop equipment as necessary to perform its services and be permitted use of existing facilities and building services. D. Any repairs or services resulting from power failures, freezing, roof leaks through curbs or equipment, or air side corrosion will be paid for by the OC Community Resources in accordance with Mesa Energy Systems, Inc.'s currently established rates. E. The agreement does not include responsibility for system design deficiencies, such as, but not limited to poor air distribution, water flow imbalances, system equipment and component obsolescence, electrical failures, unserviceable equipment, and operating the system(s), unless otherwise stated in this Agreement. F. Mesa Energy Systems, Inc. will not be liable for delays or failure to obligate due to fire, flood, strike, lockout, freezing, unavailability of material, riots, acts of god, or any cause beyond reasonable control. G. Mesa Energy Systems, Inc. is not responsible for the removal or disposal of any hazardous materials or any cost associated with these materials unless otherwise noted in this Agreement. H. The agreement does not include repairing any damage resulting from improper/inadequate water treatment or filter service not supplied by Mesa Energy Systems, Inc. I. This agreement does not include any services occasioned by improper operation, negligence, vandalism, or alterations, modifications, abuse, or misuse, or repairs to equipment not performed by Mesa Energy Systems, Inc. Unless otherwise agreed, also excluded is the furnishing of materials and supplies for painting or refurbishing existing equipment. J. Mesa Energy Systems, Inc. shall not be required to furnish any items of equipment, labor, or make special tests recommended or required by insurance companies, Federal State Municipal or other authorities except as otherwise included in this Agreement. K. In the event either party must commence a legal action in order to enforce any rights under this contract, the successful party shall be entitled to all court costs and reasonable attorney's fees as determined by the court for prosecuting and defending the claim, as the case may be. L. Mesa Energy Systems, Inc. shall not be liable for the operation of the equipment nor for injuries to persons or damage to property, except those directly due to the negligent acts or omissions of its employees and in no event shall it be liable for consequential or speculative damages. It shall not be liable for expense incurred in removing, replacing or refinishing any part of the building structure necessary to the execution of this Agreement. It shall not be held liable for any loss by reason of strikes or labor troubles affecting its employees who perform the service called for herein, delays in transportation, delays caused by priority or preference rating, or orders or regulations established by any government, authority, or by unusual delays in procuring supplies or for any other cause beyond its reasonable control. M. Only Mesa Energy Systems, Inc.'s personnel or agent are authorized to perform the work included in the scope of this agreement. Mesa Energy Systems, Inc. may, at its option, cancel or waive its obligations under this Agreement should non -authorized individuals perform such work. N. This Agreement and all rights hereunder shall not be assignable unless approved by Mesa Energy Systems, Inc. In the event of additional freight, labor, or material costs resulting from a OC Community Resources request to avoid delays with respect to equipment warranties, or accelerated delivery of parts and supplies, the Customer agrees to pay these additional costs at Mesa Energy Systems, Inc.'s currently established rates. O. Mesa Energy Systems, Inc.'s scope of work shall not include the identification, detection, abatement, encapsulation or removal of asbestos or products or materials containing asbestos or similar hazardous substances. In the event Mesa Energy Systems, Inc. encounters such material in performing its work, Mesa Energy Systems, Inc. will have the right to discontinue work and remove its employees until the hazard is corrected or its determined no hazard exists. P. This Agreement contains the entire Contract and the parties hereby agree that this Agreement has been agreed to and the entire Agreement is then accepted and approved by an authorized person for both parties, and no statement, remark, agreement or, understanding, oral or written, not contained herein, will be recognized or enforced. Q. This agreement does not include the disposal of hazardous waste, any charges incurred for their proper disposal will be born by the customer as an extra to the contract price. R. OC Community Resources agrees that in the event that there shall have been passed a federal and/or state law which shall compel Mesa Energy Systems, Inc. to contribute to a federal and/or state health plan for its employees, then the terms of this Agreement shall be subject to adjustment to the extent that the cost of such mandated contributions increase by Mesa Energy Systems, Inc.'s cost of performing this contract. S. OC Community Resources acknowledges and agrees that any purchase order issued by OC Community Resources in accordance with this Agreement, is intended only to establish payment authority for OC Community Resources internal accounting purposes. No purchase order shall be considered to be a counteroffer, amendment, modification, or other revision to the terms of this agreement. No term or condition included in the OC Community Resources purchase order will have any force or effect. SAN DIEGO • IRVINE • SAN FERNANDO VALLEY/ VENTURA • BAKERSFIELD • FRESNO • SACRAMENTO • SAN JOSE 0 PLEASANTON 9 SAN FRANCISCO 0 LAS VEGAS 0 PHOENIX 35% Mobilization Balance Progress Billings This Retrofit Related Proposal is valid for 30 days. Please feel free to contact me with any questions that you may have at 949-254-3114. Sincerely, Director of Business Development Aaron_fletcher@emcorgroup.com Execution of Contract Below: This agreement defines the understanding of services between Mesa Energy Systems Inc. and County of Orange Public Works. This agreement shall begin on Customer's Acceptance Date, or upon receipt of a Letter of Intent. Customer Acceptance: EMCOR Services / Mesa Acceptance: Signature Signature Printed Name Printed Name Title Date Title Date SAN DIEGO • IRVINE • SAN FERNANDO VALLEY / VENTURA 0 BAKERSFIELD • FRESNO • SACRAMENTO • SAN JOSE • PLEASANTON • SAN FRANCISCO • LAS VEGAS • PHOENIX - 7 - _