AGENDA REPORT
Agenda Item 20
Reviewed:
City Manager
Finance Director
MEETING DATE:
JANUARY 3, 2005
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: ACCEPTANCE OF PUBLIC IMPROVEMENTS AND AUTHORIZATION
TO FILE THE NOTICE OF COMPLETION FOR THE NEWPORT
AVENUE AT EL CAMINO REAL TRAFFIC SIGNAL MODIFICATION /
UPGRADE (CIP NO. 4064)
SUMMARY
Construction of the Newport Avenue at EI Camino Real Traffic Signal Modification / Upgrade
(CIP No. 4064) has been completed to the satisfaction of the City Engineer and is now ready
for City Council acceptance.
RECOMMENDATION
It is recommended that the City Council adopt Resolution No. 05-07 accepting the Newport
Avenue at EI Camino Real Traffic Signal Modification / Upgrade (CIP No. 4064), and
authorizing the recordation of the Notice of Completion, and direct the City Clerk to:
1. Release the Labor and Materials Bond not sooner than thirty-five (35) days after the
date of recordation of the Notice of Completion; and
2. Release the Faithful Performance Bond not sooner than one year after the date of
recordation of the Notice of Completion; and
Assuming no claims or stop payment notices are filed, it is further recommended that the City
Council authorize payment of the final 10% retention in the amount of $18,309.56 to Steiny
and Company, Inc. thirty-five (35) days after the date of recordation of the Notice of
Completion. This amount, plus previous contract payments and one change order totals
$183,095.62, which represents 100% of the final contract cost.
FISCAL IMPACT
The final construction contract cost for the Newport Avenue at EI Camino Real Traffic Signal
Modification Upgrade Project is $183,095.62. The project was funded by Measure "M"
Turnback Funds.
Acceptance of Public Improvements and Authorization to File the Notice of Completion for the
Newport Avenue at EI Camino Real Traffic Signal Modification / Upgrade (CIP No. 4064)
January 3, 2005
Page 2
Design and project construction have increased the City's infrastructure assets by $197,352.00.
The increased infrastructure valuation will be added to the City's infrastructure inventory as
required by Statement 34 of the Governmental Accounting Standards Board (GASB 34). Detailed
cost information is shown on the attached GASB 34 Infrastructure Inventory Valuation Fonm.
BACKGROUND AND DISCUSSION
The construction of the Newport Avenue at EI Camino Real Traffic Signal Modification / Upgrade
(CIP No. 4064) was completed on December 16, 2004. The signal modifications included
installation of separate left-turn phasing for EI Camino Real approaches, new safety lighting for
intersection illumination, new signal poles, mast arms and vehicle heads, new illuminated street
name signs, and the upgrading of existing curb ramps to be in compliance with federal Americans
with Disabilities Act (ADA) requirements.
All of the work for this project has been completed to the satisfaction of the City Engineer, and is
now ready for City Council acceptance.
Tim D. Serlet
Director of Public Works/City Engineer
Dana R. Kasdan
Engineering Services Manager
TDS:DRK:NOC Newport & ECR Traffic Signal & Reso 04-07.doc
Attachments: Resolution No. 05-07
Notice of Completion
Location Exhibit
GASB 34 Infrastructure Inventory Valuation Form
RESOLUTION NO. 05-07
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING THE WORKS OF IMPROVEMENT AND
AUTHORIZING THE RECORDATION OF THE NOTICE OF COMPLETION
FOR THE CONSTRUCTION OF THE NEWPORT AVENUE AT EL CAMINO
REAL TRAFFIC SIGNAL MODIFICATION / UPGRADE (CIP NO. 4064)
WHEREAS, Steiny and Company, Inc., having a contract with the City of Tustin
to construct the hereinafter described public works and improvement; and
WHEREAS, the City Engineer has duly certified to the construction and
completion of said public improvement hereinafter mentioned in a manner satisfactory
to the City Council of the City of Tustin; and
WHEREAS, the City Council finds that said contractor has completed said public
improvement hereinafter more particularly described in accordance with the provisions
of the contract documents and the Notice of Completion, and acceptance of said public
works and improvement should be filed and payment of the balance due said contract
authorized in accordance with the contract documents;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Tustin
that said public works and improvement is found to be complete, and the same is
hereby accepted. Said public works and improvement is more particularly described as
follows:
Newport Avenue at EI Camino Real Traffic Signal Modification / Upgrade
(CIP No. 4064)
BE IT FURTHER RESOLVED that the City Engineer of the City of Tustin is
hereby authorized to execute and file a Notice of Completion for the acceptance of said
public works and improvement described herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of
Tustin held on the 3rd day of January 2005.
Lou Bone, Mayor
ATTEST:
City Clerk
RECORDING REQUESTED BY &
WHEN RECORDED MAIL TO:
City of TustiniCity Clerk's Office
300 Centennial Way
Tustin, CA 92780
EXEMPT FROM RECORDING FEES PURSUANT
TO GOVERNMENT CODE SECTION 6103
SPACE ABOVE THIS LINE FOR
RECORDERS USE
CITY CLERK
NOTICE OF COMPLETION
NOTICE is hereby given that:
1. The City of Tustin is the owner in fee of the improvements hereinafter described in Paragraph 3.
2. The full name and the full address of the City of Tustin is: Citv of Tustin. 300 Centennial Wav.
Tustin. California 92780
3. The work of improvement is generally described as follows: Newport Avenue at EI Camino Real
Traffic Signal Modification / Upgrade (ClP No. 4064)
4. The work of improvement was completed on: December 16. 2004
5. The name of the contractor, if any, for such work of improvement was: Steinv and Companv. Inc.
6. The property on which said work of improvement was completed is in the City of Tustin, County of
Orange, State of California and is described as follows: Traffic Signal at Newport Avenue and EI
Camino Real
Acceptance Date: January 3. 2005
CITY OF TUSTIN, a municipal corporation
BY:
CITY ENGINEER
VERIFICATION
I am the City Engineer of the City of Tustin, a municipal corporation, owner, and have been authorized by
resolution of the City Council to execute this notice on behalf of said City; I have read the foregoing and
know the contents thereof; and I certify that the same is true of my own knowledge, except as to those
matters which are therein stated upon my information and belief, and as to those matters I believe them to
be true. I declare under penalty of perjury that the foregoing is true and correct. Executed at Tustin,
California, on the - day of ,2005.
CITY ENGINEER, CITY OF TUSTIN
z
~
::::>
l-
LL
a
~
(}
œ!
/
z
~~
:::J
¡.-.
~/
<W
0/
,f¡/
¿,'r /
I
~/
-'\
---..j,
1Y31:1 ONIINY:) 13
lS
"8,,
~
~
(j
z
n..
Q
w
0
«
~
=>
z
0
~
Q
u.
ëi
0
:::!:
...J
«
z
c¡
¡¡j
0
IT:
u..
g
...J
«
UJ
a:
0
z
:::!O
«
0
...J
UJ
~
UJ
::>
z
~
b:
0
n..
~
z
III
~
z
t>
UJ
""')
0
a:
n..
CITY OF TUSTIN
GASB 34
INFRASTRUCTURE INVENTORY VALUATION FORM
Department: Public Works
Prepared by: Jon Drauqelis
Date Prepared: December 22. 2004
Division:
Enqineerinq
Phone/Extension: (714) 573-3164
Description of the Asset: Traffic Siqnal Modification / Upqrade: Newport at EI Camino Real
Date: 0 Acquired ~ Constructed 0 Removed: I I
December 16, 2004
Basis of Valuation: (Please check one) .
~
0
Actual Cost (should include design, construction mgmt, fees, transportation, etc.)
Estimated Cost
If Estimated Cost, describe the method used:
Quantity:
(Example: 35,000 SF of concrete sidewalk)
Description
Quantitv
Total Amount
Traffic Signal
Sidewalk
TOTAL
loS.
700 S.F.
$187,482.00
$9.870.00
$197,352.00
Source of Document /Information:
Actual Contract Cost
Total Valuation Amount I
$197,352.00