AGENDA REPORT Reviewed:
enda ldm 5
City Manager
Finance Director
MEETING DATE: APRIL 16, 2019
TO: MATTHEW S. WEST, ACTING CITY MANAGER
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE
ADVERTISEMENT FOR BIDS FOR THE ANNUAL ROADWAY REHABILITATION
AND CITYWIDE SIDEWALK REPAIR PROJECT CIP NO. 70018
SUMMARY
The plans and specifications for the Annual Roadway Rehabilitation and Citywide Sidewalk Repair
Project (CIP No. 70018) have been prepared and the project is now ready for bid.
RECOMMENDATION
It is recommended that the City Council
Adopt Resolution No. 19-17 approving the plans and specifications for the Annual
Roadway Rehabilitation and Citywide Sidewalk Repair Project (CIP No. 70018), and
authorize the City Clerk to advertise to receive bids.
2. Approve an additional appropriation of $150,000 from the General Fund — Capital
Improvement Program (Fund 200) for this project.
FISCAL IMPACT
Funding in the amount of $1,456,000 has been appropriated from the General Fund — Capital
Improvement Program (Fund 200) in the Fiscal Year 2018-2019 Capital Improvement Program for
the Annual Roadway Rehabilitation and Citywide Sidewalk Repair Project, CIP No. 70018. The
project is part of the City's on-going Maintenance of Effort (MOE) obligation to maintain eligibility for
Measure M2 funding. The total engineer's estimate is $1,500,000. Additional costs for construction
engineering, materials testing, and inspection are estimated at $100,000 for a total project cost of
$1,600,000. This requires an additional appropriation of $150,000 from the General Fund — Capital
Improvement Program.
CORRELATION TO THE STRATEGIC PLAN
Rehabilitation of roadways and repair of sidewalks contributes to the fulfillment of the City's Strategic
Plan Goal B: Public Safety and Protection of Assets. Specifically, the project implements Strategy
#5, which among other items, is to ensure continuous maintenance and improvement of
transportation facilities.
DISCUSSION AND BACKGROUND
The Annual Roadway Rehabilitation and Citywide Sidewalk Repair Project CIP No. 70018 for Fiscal
Year 2018-2019 includes asphalt concrete pavement repair, asphalt concrete overlay, slurry sealing,
and traffic striping on various streets throughout the City within Zone 7 of the City's Pavement
Management Program. The City is divided into seven pavement management zones with one zone
Annual Roadway Rehabilitation and Citywide Sidewalk Repair Project
April 16, 2019
Page 2
intended to maintain the integrity of City streets. The current phase, Zone 7 (see attached map), is
generally bounded by Edinger Avenue to the north, Tustin Ranch Road to the east, Barranca
Parkway/Warner Avenue to the south, and Costa Mesa Freeway (SR -55) to the west.
Effective July 1, 2017, the Measure M2 Ordinance (Ordinance No. 3) requires each City to maintain a
minimum level of local streets and roads expenditures from the City's General Fund regarding the
Maintenance of Effort (MOE). The City's FY 2018-19 MOE benchmark is $1,455,691. The scope of
work has been established to ensure final expenditures are above this benchmark and that the City's
eligibility to receive Measure M2 funding is not compromised.
CIP No. 70018 also includes the Annual Sidewalk Repair Project which focuses on removal and
replacement of damaged sidewalk to correct tripping hazards at numerous locations throughout the
City based on an annual field survey conducted by the Engineering Division. The field survey
identifies and evaluates locations where tree roots are causing sidewalk and curb and gutter
damage. Under the project, some of these trees will be removed and replaced with trees of an
acceptable species more suitable to the parkway area as recommended by the City's Certified
Arborist. This project also provides improvements throughout the City to comply with the Americans
with Disabilities Act (ADA). These locations are typically requested by citizens or are identified by
City staff to provide for completion of missing segments of sidewalk and curb ramps to improve
pedestrian access.
The tentative schedule for construction of this project is as follows:
• Authorization to Advertise for Bids......................................................04/16/2019
• First Legal Advertisement...................................................................04/18/2019
• Second Legal Advertisement..............................................................04/25/2019
• Bid Opening........................................................................................05/21/2019
• Award of Contract............................................................................... 06/18/2019
• Start Construction................................................................................. July 2019
• Complete Construction.................................................................... October 2019
Since this project involves the replacement and repair of existing facilities with minor modifications,
it is Categorically Exempt under California Environmental Quality Act (CEQA) requirements. A
Notice of Exemption has been prepared for the project, and will be recorded with the County of
Orange.
Do s . Stack, P. E.
D9 ec of Public Works/City Engineer
Attachment 1: Resolution No. 19-17
Attachment 2: Location Map
S:\City Council Items\2019 Council Items\04-16-2019\Approve P&S for Roadway Rehab and Sidewalk Repair (CIP 70018)\Approval of
P&S Roadway Rehab & Sidewalk Repair (CIP 70018) SC.docx
ATTACHMENT 1
Resolution No. 19-17
RESOLUTION NO. 19-17
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA
APPROVING PLANS AND SPECIFICATIONS FOR THE ANNUAL ROADWAY
REHABILITATION AND CITYWIDE SIDEWALK REPAIR PROJECT CIP NO. 70018
AND AUTHORIZING ADVERTISEMENT FOR BIDS
WHEREAS, it is the intention of the City Council of the City of Tustin, California to
contract for the construction of the Annual Roadway Rehabilitation and Citywide Sidewalk
Repair Project CIP No. 70018, FY 2018-2019; and
WHEREAS, the City Engineer has presented plans and specifications for the
construction of said work; and
WHEREAS, the CIP No. 70018 project is categorically exempt from the requirements of
the California Environmental Quality Act (CEQA); Class 1, Section 15301: Existing Facilities;
and
NOW, THEREFORE, BE IT RESOLVED that the plans and specifications presented by
the City Engineer are hereby approved as the plans and specifications for:
FY 2018-2019 Annual Roadway Rehabilitation and Citywide Sidewalk Repair Project
CIP No. 70018
BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to
advertise as required by law for the receipt of sealed bids or proposals for the performance of
the work specified in the aforesaid plans and specifications;
PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin
held on the 16th day of April, 2019.
Charles E. Puckett, Mayor
ATTEST:
Erica N. Yasuda
City Clerk
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS
CITY OF TUSTIN )
I, Erica N. Yasuda, City Clerk and ex -officio Clerk of the City Council of the City of Tustin,
California, do hereby certify that the whole number of the members of the City Council is five;
that the above and foregoing Resolution No. 19-17 was duly and regularly passed and adopted
at a regular meeting of the City Council held on the 16th day of April, 2019 by the following vote:
COUNCILMEMBER AYES:
COUNCILMEMBER NOES:
COUNCILMEMBER ABSTAINED:
COUNCILMEMBER ABSENT:
ERICA N. YASUDA
City Clerk