I.
RESOLUTION NO. 3943
A RESOLUTION OF THE CITY OF TUSTIN PLANNING COMMISSION
RECOMMENDING THAT THE CITY COUNCIL FIND THAT THE FINAL
ENVIRONMENTAL IMPACT STATEMENT/FINAL ENVIRONMENTAL
IMPACT REPORT FOR THE DISPOSAL AND REUSE OF MCAS
TUSTIN ("FEIS/FEIR") IS ADEQUATE TO SERVE AS THE PROJECT
EIS/EIR FOR ZONE CHANGE 04-002, TENTATIVE TRACT MAP 16582,
CONCEPT PLAN 03-004, DESIGN REVIEW 04-004, THE
AFFORDABLE HOUSING PLAN AND DENSITY BONUS
APPLICATION, AND THE REQUEST TO TRANSFER AFFORDABLE
HOUSING UNITS FROM PLANNING AREA 21 TO PLANNING AREA 5
AND THAT ALL APPLICABLE MITIGATION MEASURES WILL BE
INCORPORATED INTO THE PROJECT AS REQUIRED BY THE
CALIFORNIA ENVIRONMENTAL QUALITY ACT.
The Planning Commission of the City of Tustin does hereby resolve as follows:
A.
That Zone Change 04-002, Concept Plan 03-004, Tentative Tract Map
16582, Design Review 04-004, the "Affordable Housing Plan and Density
Bonus Application," and the request to transfer affordable housing units
from Planning Area 21 to Planning Area 5 is considered a "Project"
pursuant to the terms of the California Environmental Quality Act; and,
B.
That the FEIS/FEIR was certified by the City Council on January 16, 2001.
The FEIS/EIR is a program EIR under the California Environmental
Quality Act ("CEQA"). The FEIS/FEIR considered the potential
environmental impacts associated with development on the former Marine
Corps Air Station, Tustin, including development of residential uses within
Planning Area 21.
C.
That an initial study checklist, attached as Exhibit A hereto, was prepared
to evaluate the potential environmental impacts associated with the
Project. The initial study checklist demonstrates that all potential impacts
of the Project were addressed by the certified FEIS/FEIR, no additional
impacts have been identified, and all applicable mitigation measures in the
FEIS/FEIR will be implemented through the Mitigation Monitoring Program
for the Project (Attachment 1 of Exhibit A) or as conditions of approval of
the Project.
II.
The Planning Commission hereby recommends that the City Council find that
the project is within the scope of the previously approved Program FEIS/FEIR
and that pursuant to Title 14 California Code of Regulations Sections 15168
(c) and 15162, no new effects could occur and no new mitigation measures
Resolution No. 3943
Page 2
would be required. Accordingly, no new environmental document is required
by CEQA.
PASSED AND ADOPTED by the Planning Commission of the City of Tustin, at a
regular meeting on the 14th day of February, 2005.
Et~~~/-
ELIZABETH A. BINSACK
Planning Commission Secretary
STATE OF CALIFORNIA)
COUNTY OF ORANGE)
CITY OF TUSTIN )
I, ELIZABETH A. BINSACK, the undersigned, hereby certify that I am the Planning
Commission Secretary of the Planning Commission of the City of Tustin, California; that
Resolution No. 3943 duly passed and adopted at a regular meeting of the Tustin
Planning Commission, held on the 14th day of February, 2005.
a~~~L
ELIZABETH A. BINSACK
Planning Commission Secretary
--- -- ------------ ----
--- -~----------------
EXHIBIT A TO RESOLUTION NO. 3943
COMMUNITY DEVELOPMENT DEPARTMENT
300 Centennial Way, Tustin, CA 92780
(714) 573-3100
ENVIRONMENTAL ANALYSIS CHECKLIST
For Projects With Previously Certified/Approved Environmental Documents:
Environmental Impact StatementlEnvironmental Impact Report (EIS/EIR)
for the Disposal and Reuse of Marine Corps Air Station (MCAS) Tustin
This checklist and the following evaluation of environmental impacts (Attachment 1 of Exhibit A of Resolution
No. 3943) takes into consideration the preparation of an environmental document prepared at an earlier stage of
the proposed project. The. checklist and evaluation evaluate the adequacy of the earlier document pursuant to
Section 15162 and 15168 of the California Environmental Quality Act (CEQA) Guidelines.
A.
BACKGROUND
Project Title(s):
Lead Agency:
Development of 465 residential units in Planning Area 21
City of Tustin, 300 Centennial Way, Tustin, California 92780
Lead Agency Contact Person:
Project Location:
Minoo Ashabi
Phone: (714) 573-3126
Planning Area 21, MCAS-Tustin Specific Plan, bounded by Moffett Avenue on
the north, Wamer A venue on the south, Peters Canyon Flood Control Channel on
the west, and Harvard Avenue on the east.
Project Sponsor's Name and Address:
Moffett Meadows Partners, LLC
c/o Lennar Communities
25 Enterprise, Suite 300
Aliso Viejo, CA 92656
General Plan Designation:
Zoning Designation:
MCAS Tustin Specific Plan
Low Density Residential, Planning Area 21
Project Description: Approval of Concept Plan 03-004, Tentative Tract Maps 16582, Design Review
04-004, Specific Plan Amendment/Zone Change 04-002 (MCAS Tustin disposition parcels 35 & 36) for
the purpose of developing 465 residential units including 211 single family detached, 68 carriage way
units, 102 triplex units and 84 cluster town units and a request to transfer eight (8) of the Very Low
Income units and seventeen (17) of the Low Income units nom Planning Area 21 to Planning Area 5.
Surrounding Uses:
North: Vacant - Moffett Avenue, residential uses
East: Harvard A venue- City of Irvine, residential uses
South: Vacant - MCAS Tustin Planning Area 22 , residential
West: Peters Canyon Flood Control Channel- Jamboree Road
Previous Environmental Documentation: Program Final Environmental Impact
Statement/Environmental Impact Report (Program FEISÆIR) for the Disposal and Reuse of Marine
Corps Air Station (MCAS) Tustin (State Clearinghouse #94071005) certified by the Tustin City Council
on January 16,2001.
B.
ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED
The environmental factors checked below would be potentially affected by this project, involving at least one
impact that is a "Potentially Significant Impact" as indicated by the checklist in Section D below.
OLand Use and Planning
OPopulation and Housing
OGeology and Soils
OHydrology and Water Quality
OAir Quality
OTransportation & Circulation
OBiological Resources
OMineral Resources
OAgricultural Resources
OHazards and Hazardous Materials
ONoise
OPublic Services
OUtilities and Service Systems
OAesthetics
OCultural Resources
ORecreation
OMandatory Findings of
Significance
C. DETERMINATION:
On the basis ofthis initial evaluation:
0 I find that the proposed project COULD NOT have a significant effect on the environIIient, and a
NEGATIVE DECLARATION will be prepared.
0 I find that although the proposed project could have a significant effect on the environment, there will
not be a significant effect in this case because the mitigation measures described on an attached sheet
have been added to the project. A NEGATIVE DECLARATION will be prepared.
0 I find that the proposed project MAY have a significant effect on the environment, and an
ENVIRONMENTAL IMPACT REPORT is required.
0 I find that the proposed project MAY have a significant effect(s) on the environment, but at least one
effect 1) has been adequately analyzed in an earlier document pursuant to applicable legal standards, and
2) has been addressed by mitigation measures based on the earlier analysis as described on attached
sheets, if the effect is a "Potentially Significant Impact" or "Potentially Significant Unless Mitigated."
An ENVIRONMENTAL IMP ACT REPORT is required, but it must analyze only the effects that
remain to be addressed.
fZI I find that although the proposed project could have a significant effect on the environment, there WILL
NOT be a significant effect in this case because all potentially significant effects 1) have been analyzed
adequately in an earlier EIR pursuant to applicable standards, and 2) have been avoided or mitigated
pursuant to that earlier EIR, including revisions or mitigation measures that are imposed upon the
proposed project.
0 I find that although the proposed project could have a significant effect on the environment, there WILL
NOT be a significant effect in this case because all potentially significant effects 1) have been analyzed
adequately in an earlier NEGATIVE DECLARATION pursuant to applicable standards, and 2) have
been avoided or mitigated pursuant to that earlier NEGATIVE DECLARA nON, including revisions or
mitigation measures that are imposed upon the proposed project.
Preparer: ~~2 J
Ø, Mmoo Mhabd;::7
/~,A
Elizabeth A. Binsack, Community Development Director
Date:
I, 13.o~
Date /-ß -cNT
D. EV ALUA TION OF ENVIRONMENTAL IMPACTS
See Attached
\
EV ALUA TION OF ENVIRONMENTAL IMPACTS
No Substantial
New More Change From
Significant Severe Previous
I. AESTHETICS - Would the project: Impact Impacts Analysis
a) Have a substantial adverse effect on a scenic vista? 0 0 r8I
b) Substantially damage scenic resources, including, but not
limited to, trees, rock outcroppings, and historic buildings
within a state scenic highway? 0 0 r8I
c) Substantially degrade the existing visual character or
quality of the site and its surroundings? 0 0 r8I
d) Create a new source of substantial light or glare which
would adversely affect day or nighttime views in the area? 0 0 r8I
II. AGRICULTURE RESOURCES: In determining
whether impacts to agricultural resources are significant
environmental effects, lead agencies may refer to the
California Agricultural Land Evaluation and Site Assessment
Model (1997) prepared by the California Dept. of
Conservation as an optional model to use in assessing impacts
on agriculture and farmland. Would the project:
a) Convert Prime Farmland, Unique Farmland, or Farmland
of Statewide Importance (Farmland), as shown on the maps
prepared pursuant to the Farmland Mapping and Monitoring
Program of the California Resources Agency, to non-
agricultural use? 0 0 r8I
b) Conflict with existing zoning for agricultural use, or a
Williamson Act contract? 0 0 ~
c) Involve other changes in the existing environment which,
due to their location or nature, could result in conversion of
Farmland, to non-agricultural use? 0 0 r8I
III. AIR OUALlTY: Where available, the significance
criteria established by the applicable air quality management
or air pollution control district may be relied upon to make the
following determinations. Would the project:
a) Conflict with or obstruct implementation of the applicable
air quality plan? 0 0 r8I
b) Violate any air quality standard or contribute substantially
to an existing or projected air quality violation? 0 0 r8I
c) Result in a cumulatively considerable net increase of any
criteria pollutant for which the project region is non-
attainment under an applicable federal or state ambient air
quality standard (including releasing emissions which exceed
quantitative thresholds for ozone precursors)? 0 0 r8I
d) Expose sensitive receptors to substantial pollutant
concentrations? 0 0 181
e) Create objectionable odors affecting a substantial number
of people? 0 0 Ið1
IV. BIOLOGICAL RESOURCES: - Would the project:
a) Have a substantial adverse effect, either directly or
through habitat modifications, on any species identified as a
candidate, sensitive, or special status species in local or
regional plans, policies, or regulations, or by the California
Department ofFish and Game or U.s. Fish and Wildlife
Service?
b) Have a substantial adverse effect on any riparian habitat
or other sensitive natural community identified in local or
regional plans, policies, regulations or by the California
Department ofFish and Game or U.S. Fish and Wildlife
Service?
c) Have a substantial adverse effect on federally protected
wetlands as defined by Section 404 of the Clean Water Act
(including, but not limited to, marsh, vernal pool, coastal, etc.)
through direct removal, filling, hydrological interruption, or
other means?
d) Interfere substantially with the movement of any native
resident or migratory fish or wildlife species or with
established native resident or migratory wildlife corridors, or
impede the use of native wildlife nursery sites?
~) Conflict with any local policies or ordinances protecting
oiological resources, such as a tree preservation policy or
ordinance?
t) Conflict with the provisions of an adopted Habitat
Conservation Plan, Natural Community Conservation Plan, or
other approved local, regional, or state habitat conservation
plan?
V. CULTURAL RESOURCES: - Would the project:
a) Cause a substantial adverse change in the significance of
a historical resource as defined in § 15064.5?
b) Cause a substantial adverse change in the significance of
an archaeological resource pursuant to § 15064.5?
c) Directly or indirectly destroy a unique paleontological
resource or site or unique geologic feature?
d) Disturb any human remains, including those interred
outside of formal cemeteries?
VI. GEOLOGY AND SOILS: - Would the project:
i) Expose people or structures to potential substantial
adverse effects, including the risk ofloss, injury, or death
involving:
New
Significant
Impact
No Substantial
Change From
Previous
Analysis
More
Severe
Impacts
0
0
~
0
0
~
0
0
~
0
0
IZJ
0
0
~
0
0
~
0 0 ~
0 0 ~
0 0 ~
0 0 IZJ
No Substantial
New More Change From
Significant Severe Previous
Impact Impacts Analysis
i) Rupture of a known earthquake fault, as delineated on the
most recent Alquist-Priolo Earthquake Fault Zoning Map
issued by the State Geologist for the area or based on other
substantial evidence of a known fault? Refer to Division of
Mines and Geology Special Publication 42. 0 0 ~
ii) Strong seismic ground shaking? 0 0 ~
Hi) Seismic-related ground failure, including liquefaction? 0 0 ~
iv) Landslides? 0 0 ~
b) Result in substantial soil erosion or the loss of topsoil? 0 0 ~
c) Be located on a geologic unit or soil that is unstable, or
that would become unstable as a result of the project, and
potentially result in on- or off-site landslide, lateral spreading,
subsidence, liquefaction or collapse? 0 0 ~
d) Be located on expansive soil, as defined in Table 1 8- 1 -B
of the Uniform Building Code (1994), creating substantial
risks to life or property? 0 0 ~
e) Have soils incapable of adequately supporting the use of
septic tanks or alternative wastewater disposal systems where
sewers are not available for the disposal of waste water? 0 0 ~
VII. HAZARDS AND HAZARDOUS MATERIALS:
Would the project:
a) Create a significant hazard to the public or the
environment through the routine transport, use, or disposal of
hazardous materials? 0 0 ~
b) Create a significant hazard to the public or the
environment through reasonably foreseeable upset and
accident conditions involving the release of hazardous
materials into the environment? 0 0 ~
c) Emit hazardous emissions or handle hazardous or acutely
hazardous materials, substances, or waste within one-quarter
mile of an existing or proposed school? 0 0 ~
d) Be located on a site which is included on a list of
hazardous materials sites compiled pursuant to Government
Code Section 65962.5 and, as a result, would it create a
significant hazard to the public or the environment? 0 0 ~
e) For a project located within an airport land use plan or,
where such a plan has not been adopted, within two miles of a
public airport or public use airport, would the project result in
a safety hazard for people residing or working in the project
area? 0 0 ~
f) For a project within the vicinity of a private airstrip,
would the project result in a safety hazard for people residing
or working in the project area? 0 0 ~
No Substantial
New More Change From
Significant Severe Previous
~) Impair implementation of or physically interfere with an Impact Impacts Analysis
idopted emergency response plan or emergency evacuation
plan? 0 0 ~
h) Expose people or structures to a significant risk of loss,
injury or death involving wildland fires, including where
wildlands are adjacent to urbanized areas or where residences
are intermixed with wildlands? 0 0 ~
VIII. HYDROLOGY AND WATER OUALITY: - Would
the project:
a) Violate any water quality standards or waste discharge
requirements? 0 0 ~
b) Substantially deplete groundwater supplies or interfere
substantially with groundwater recharge such that there would
be a net deficit in aquifer volume or a lowering of the local
groundwater table level (e.g., the production rate of pre-
existing nearby wells would drop to a level which would not
support existing land uses or planned uses for which permits
have been granted)? 0 0 ~
c) Substantially alter the existing drainage pattern of the site
or area, including through the alteration of the course of a
---stream or river, in a manner which would result in substantial
~rosion or siltation on- or off-site? 0 0 ~
d) Substantially alter the existing drainage pattern of the site
or area, including through the alteration of the course of a
stream or river, or substantially ipcrease the rate or amount of
surface runoff in a manner which would result in flooding on-
or off-site? 0 0 ~
e) Create or contribute runoff water which would exceed the
capacity of existing or planned stormwater drainage systems
or provide substantial additional sources of polluted runoff? 0 0 ~
f) Otherwise substantially degrade water quality? 0 0 ~
g) Place housing within a I DO-year flood hazard area as
mapped on a federal Flood Hazard Boundary or Flood
Insurance Rate Map or other flood hazard delineation map? 0 0 ~
h) Place within a lOO-year flood hazard area structures
which would impede or redirect flood flows? 0 0 ~
i) Expose people or structures to a significant risk of loss,
injury or death involving flooding as a result of the failure of a
levee or dam? 0 0 ~
) Inundation by seiche, tsunami, or mudflow? 0 0 ~
:X. LAND USE AND PLANNING - Would the project:
a) Physically divide an established community? 0 0 ~
No Substantial
New More Change From
Significant Severe Previous
b) Conflict with any applicable land use plan, policy, or Impact Impacts Analysis
regulation of an agency with jurisdiction over the project
(including, but not limited to the general plan, specific plan,
local coastal program, or zoning ordinance) adopted for the
purpose of avoiding or mitigating an environmental effect? 0 0 ~
c) Conflict with any applicable habitat conservation plan or
natural community conservation plan? 0 0 ~
X. MINERAL RESOURCES - Would the project:
a) Result in the loss of availability of a known mineral
resource that would be of value to the region and the residents
of the state? 0 0 ~
b) Result in the loss of availability of a locally-important
mineral resource recovery site delineated on a local general
plan, specific plan or other land use plan? 0 0 ~
XI. NOISE -
Would the project result in:
a) Exposure of persons to or generation of noise levels in
excess of standards established in the local general plan or .----
noise ordinance, or applicable standards of other agencies? 0 0 ~
b) Exposure of persons to or generation of excessive
groundbome vibration or groundbome noise levels? 0 0 ~
c) A substantial permanent increase in ambient noise levels
in the project vicinity above levels existing without the
project? 0 0 ~
d) A substantial temporary or periodic increase in ambient
noise levels in the project vicinity above levels existing
without the project? 0 0 ~
e) For a project located within an airport land use plan or,
where such a plan has not been adopted, within two miles of a
public airport or public use airport, would the project expose
people residing or working in the project area to excessive
noise levels? 0 0 ~
f) For a project within the vicinity of a private airstrip,
would the project expose people residing or working in the
project area to excess noise levels? 0 0 ~
XII. POPULATION AND HOUSING - Would the project:
a) Induce substantial population growth in an area, either ,-----
directly (for example, by proposing new homes and
businesses) or indirectly (for example, through extension of
roads or other intrastructure)? 0 0 ~
b) Displace substantial numbers of existing housing,
necessitating the construction of replacement housing
elsewhere? 0 0 ~
--~--------- ---- -----
No Substantial
New More Change From
Significant Severe Previous
Impact Impacts Analysis
;) Displace substantial numbers of people, necessitating the
construction of replacement housing elsewhere? 0 0 181
XIII. PUBLIC SERVICES
a) Would the project result in substantial adverse physical
impacts associated with the provision of new or physically
altered governmental facilities, need for new or physically
altered governmental facilities, the construction of which
could cause significant environmental impacts, in order to
maintain acceptable service ratios, response times or other
performance objectives for any of the public services:
Fire protection? 0 0 181
Police protection? 0 0 181
Schools? D D 181
Parks? D 0 181
Other public facilities? 0 0 181
-XIV. RECREATION -
:1) Would the project increase the use of existing
neighborhood and regional parks or other recreational
facilities such that substantial physical deterioration of the
facility would occur or be accelerated? D 0 181
b) Does the project include recreational facilities or require
the construction or expansion of recreational facilities which
might have an adverse physical effect on the environment? 0 D 181
XV. TRANSPORTATION/TRAFFIC - Would the project:
a) Cause an increase in traffic which is substantial in relation
to the existing traffic load and capacity of the street system
(i.e. result in a substantial increase in either the number of
vehicle trips, the volume to capacity ratio on roads, or
congestion at intersections)? 0 D 181
b) Exceed, either individually or cumulatively, a level of
service standard established by the county congestion
management agency for designated roads or highways? 0 D 181
c) Result in a change in air traffic patterns, including either
an increase in traffic levels or a change in location that results
in substantial safety risks? D D 181
1) Substantially increase hazards due to a design feature (e.g.
,harp curves or dangerous intersections) or incompatible uses
(e.g., farm equipment)? 0 0 181
e) Result in inadequate emergency access? 0 0 181
f) Result in inadequate parking capacity? 0 D ~
No Substantial
New More Change From
Significant Severe Previous
Impact Impacts Analysis
g) Conflict with adopted policies, plans, or programs
supporting alternative transportation (e.g., bus turnouts,
bicycle racks)? 0 0 ~
XVI. UTILITIES AND SERVICE SYSTEMS -
Would the project:
a) Exceed wastewater treatment requirements of the
applicable Regional Water Quality Control Board? 0 0 ~
b) Require or result in the construction of new water or
wastewater treatment facilities or expansion of existing
facilities, the construction of which could cause significant
environmental effects? 0 0 ~
c) Require or result in the construction of new storm water
drainage facilities or expansion of existing facilities, the
construction of which could cause significant environmental
effects? 0 0 ~
d) Have sufficient water supplies available to serve the
project from existing entitlements and resources, or are new or
expanded entitlements needed? 0 0 ~
e) Result in a determination by the wastewater treatment
provider which serves or may serve the project that it has
adequate capacity to serve the project's projected demand in
addition to the provider's existing commitments? 0 0 ~
f) Be served by a landfill with sufficient permitted capacity
to accommodate the project's solid waste disposal needs? 0 0 .~
g) Comply with federal, state, and local statutes and
regulations related to solid waste? 0 0 ~
XVII. MANDA TORY FINDINGS OF SIGNIFICANCE
a) Does the project have the potential to degrade the quality
of the environment, substantially reduce the habitat of a fish or
wildlife species, cause a fish or wildlife population to drop
below self-sustaining levels, threaten to eliminate a plant or
animal community, reduce the number or restrict the range of
a rare or endangered plant or animal or eliminate important
examples of the major periods of California history or
prehistory? 0 0 ~
b) Does the project have impacts that are individually
limited, but cumulatively considerable? ("Cumulatively
considerable" means that the incremental effects of a project
are considerable when viewed in connection with the effects
of past projects, the effects of other current projects, and the
effects of probable future projects)? 0 0 ~
c) Does the project have environmental effects which will
cause substantial adverse effects on human beings, either
directly or indirectly? 0 0 ¡:gj
ATTACHMENT 1 TO EXHIBIT A OF RESOLUTION NO. 3943
EVALUATION OF ENVIRONMENTAL IMPACTS
CONCEPT PLAN 03-004, TENTATIVE TRACT MAPS 16582
DESIGN REVIEW 04-004, SPECIFIC PLAN AMENDMENT/ZONE CHANGE 04-002,
AFFORDABLE HOUSING PLAN AND DENSITY BONUS AND TRANSFER OF
AFFORDABLE UNITS
(MCAS TUSTIN DISPOSITION PARCELS 35 & 36)
PLANNING AREA 21 - MCAS TUSTIN SPECIFIC PLAN
BACKGROUND
The fonDer Marine Corps Air Station (MCAS) Tustin was officially closed on July 2, 1999 as a
result of recommendations of the Federal Base Closure and Realignment Commission. The City
was designated as the Local Redevelopment Authority (LRA) for the reuse of MCAS Tustin and,
acting as such, approved a Reuse Plan that provided for future land uses at the fonDer MCAS Tustin
on October 1996 and subsequently amended on September 1998 ("the Reuse Plan"). The Reuse Plan
was subsequently reviewed and approved by the United States Department of Housing and Urban
Development (HUD) as consistent with federal law regarding the homeless.
In accordance with the provisions of the. National Environmental Policy Act ("NEP A") of 1969, as
amended, and the California Environmental Quality Act ("CEQA"), the federal government and
City prepared a Joint Final Program Environmental Impact StatementlEnvironmental Impact
Report for the Reuse and Disposal of MCAS Tustin. On January 16, 2001, the City of Tustin
certified the Final Joint Program Environmental Impact StatementlEnvironmental Impact Report
for the disposal and reuse of MCAS- Tustin (referenced as FEIS/EIR herein).
The project is within the MCAS Tustin Specific Plan. The land was purchased by the developers
directly from the Department of Navy through a land auction.
The project site is comprised of 86.26 acres (gross) within a portion of Planning Area 21 of the
MCAS Tustin Specific Plan and generally bounded by the Moffett A venue to the north, a local
drainage channel and Warner A venue in the City of Irvine to the south, Harvard A venue and City of
Irvine residential developments to the east, and Peters Canyon Flood Channel and Jamboree Road
to the west.
The proposed project would develop 465 residential units including 211 single family detached,
68 carriage way units, and 184 condominium units on two parcels. Parcel 35 is located within
City of Tustin and contains 326 units and Parcel 36 is located within City of Irvine and contains
139 units. Three of the units traverse city boundary lines. Parcel 36 is proposed to be annexed to
City of Tustin. The annexation request and the Specific Plan Amendment/Zone Change to adopt
land use and development standards for Parcel 36 will be considered separately by the City
Council.
In accordance with the requirements of the MCAS Tustin Specific Plan Section 3.4.2.G and
3.4.3.H a total of 59 affordable units would be required as follows:
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
Page 2
Planning Affordable Units RHNA Total Required
Area (15%)
21 20 Very Low 6 Low 20 Very Low
Parcel 35 11 Low 12 Moderate 17 Low
18 Moderate 30 Moderate
21 Subject to
Parcel 36 requirements of City
of Irvine
Total 41 18 59
* Required number of Very Low, Low, Moderate Income units, and Regional Housing Need
Assessment (RHNA) units subject to requirements of City of Tustin for Parcel 35 and City of
Irvine for Parcel 36.
Twelve (12) of the Very Low Income units required for Parcel 35 are required to be transferred
by the developer to two homeless service providers (Human Options and Orange County
Interfaith Shelter) pursuant to the MCAS Tustin Specific Plan requirements.
The project includes development of 6.19 acres of parkland recreational sites including 2.35
acres accessible for public and facility improvements for which parkland credit is eligible and
recommended in accordance with the requirements of the Quimby Act and the City's
Subdivision requirements. Access to the public park site would be provided by public access
easements from Moffett A venue and Harvard A venue with recordation of an easement requiring
public access in perpetuity to the park site for the general public on Tentative Tract Map 16582.
A portion of the site would also include private recreational amenities available to the residents
of the development.
The subject site is located in Planning Area 21. As part of the analysis of the MCAS Tustin
FEIRIEIS for the MCAS Tustin Specific Plan, Planning Area 21 was identified as a Low Density
Residential (LDR) site, with a development potential of 1-7 dwelling units per acre and
authorized for up to 861 units (Table 3-2 of MCAS Tustin Specific Plan). With development of
Parcel 34 (Tract 16507) within Planning Area 21, 189 residential units have already been
approved by the City within Planning Area 21. The currently proposed project includes
construction of 465 units, which combined with the 189 units on Parcel 34 is 207 dwelling units
less than the 861 units assumed for Planning Area 21 in the FEISIEIR. All related environmental
impacts of such development were addressed in the FEISÆIR and implementation and
mitigation measures were incorporated as conditions of approval for the other entitlement
portions of the project as identified in the Mitigation Monitoring Program Matrix (Attachment 2
of Exhibit A of Resolution No. 3943).
The following information provides background support for the conclusions identified in the
Environmental Analysis Checklist.
TI.
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, 'IT 16582, DR 04-004, Density Bonus
Page 3
I.
AESTHETICS - Would the project:
a) Have a substantial adverse effect on a scenic vista?
b) Substantially damage scenic resources, including, but not limited to, trees, rock
outcroppings, and historic buildings within a state scenic highway?
c) Substantially degrade the existing visual character or quality of the site and its
surroundings?
d) Create a new source of substantial light or glare, which would adversely affect
day or nighttime views in the area?
The project is not located on a scenic highway nor will it affect a scenic vista. The project
would be consistent with the pennitted uses identified within the MCAS Tustin Specific
Plan. Development of low-density within Planning Area 21 that were considered within the
FEISIEIR and will have no negative aesthetic effect on the site when mitigation measures
identified in the FEISIEIR are incorporated with approval of the project. All exterior design
is required to be in compliance with Section 2.17.3(A) - Urban Design Guidelines for
Residential Development of MCAS Tustin Specific Plan, and the Landscape Concept
Section 2.17.2 as they relate to design of Moffett A venue, Harvard A venue, and primary
street corners and project entries. The proposal includes a design review, which requires
that the design of the project is cohesive and in harmony with surrounding uses. All
exterior lighting would be designed to reduce glare, create a safe night environment, and
avoid impacts to surrounding properties in compliance with Section 2.17.3 (A) of the
MCAS Tustin Specific Plan and the City's Security Ordinance. The proposed project will
result in no substantial changes to the environmental impacts previously evaluated with the
certified Program FEISIEIR.
Mitigation/Monitoring Required: Mitigation measures have been adopted by the Tustin
City Council in the FEISIEIR as identified in the Mitigation and Implementation Measures
matrix (Attachment 2); these measures would be included as conditions of approval for the
project.
Sources:
FEISIEIR for Disposal and Reuse of MCAS Tustin
MCAS Tustin Specific Plan (pages 2-152 to 2-166)
Tustin Security Ordinance
Tustin General Plan
AGRICULTURE RESOURCES: In determining whether impacts to agricultural
resources are significant environmental effects, lead agencies may refer to the
California Agricultural Land Evaluation and Site Assessment Model (1997)
prepared by the California Dept. of Conservation as an optional model to use in
assessing impacts on agriculture and farmland. Would the project:
a) Convert Prime Farmland, Unique Farmland, or Farmland of Statewide
Importance (Farmland), as shown on the maps prepared pursuant to the
Farmland Mapping and Monitoring Program of the California Resources
Agency, to non-agricultural use?
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
Page 4
b) Conflict with existing zoning for agricultural use or a Williamson Act contract?
c) Involve other changes in the existing environment which, due to their location or
nature, could result in conversion of Farmland to non-agricultural use?
The project would not convert prime farmland, unique farmland or farmland of statewide
importance as shown on maps prepared pursuant to the Fannland Managing and
Monitoring Program of the California Resources Agency, to non-agricultural use. Also, the
property is not zoned for agricultural use or a Williamson Act Contract, nor does the
proposed use involve other changes in the existing environment that could result in the
conversion of farmland to non-agricultural use. The project site is not zoned or used as
agricultural land; consequently, no substantial change is expected from the analysis
previously completed in the FEIS/EIR for MCAS Tustin.
Mitigation/Monitoring Required: No mitigation is required.
Sources:
Field Observations
FEISIEIR for Disposal and Reuse of MCAS Tustin (page-145 to 3-154)
MCAS Tustin Specific Plan
Tustin General Plan
III.
AIR QUALITY: Where available, the significance criteria established by the
applicable air quality management or air pollution control district may be relied
upon to make the following determinations. Would the project:
a) Conflict with or obstruct implementation of the applicable air quality plan?
b) Violate any air quality standard or contribute substantially to an existing or
projected air quality violation?
c) Result in a cumulatively considerable net increase of any criteria pollutant for
which the project region is non-attainment under an applicable federal or state
ambient air quality standard (including releasing emissions that exceed
quantitative thresholds for ozone precursors)?
d) Expose sensitive receptors to substantial pollutant concentrations?
e) Create objectionable odors affecting a substantial number of people?
As documented in the FEISIEIR, the project is part of larger project that was projected to
result in air quality impacts. A Statement of Overriding Consideration for the FEISIEIR was
adopted by the Tustin City Council on January 16, 2001. Since the project will construct
207 fewer units than previously analyzed in the FEISIEIR, no significant impact beyond
what was analyzed in the adopted FEISÆIR is anticipated.
Mitigation/Monitoring Required: Specific mitigation measures have been adopted by the
Tustin City Council in certifying the FEISIEIR. However, the FEISÆIR also concluded that
Reuse Plan related operational air quality impacts were significant and impossible to fully
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, TT 16582, DR 04-004, Density Bonus
Page 5
mitigate. A Statement of Oveniding Consideration for the FEISÆIR was adopted by the
Tustin City Council on January 16,2001.
Sources:
Field Observations
FEISÆIR for Disposal and Reuse of MCAS Tqstin (pages 3-143
throughl53, 4-207 through 4-230 and pages 7-41 through 7-42)
MCAS Tustin Specific Plan (pages 3-145 through 3-154)
Tustin General Plan
IV.
BIOLOGICAL RESOURCES: . Would the project:
a) Have a substantial adverse effect, either directly or through habitat
modifications, on any species identified as a candidate, sensitive, or special status
species in local or regional plans, policies, or regulations, or by the California
Department of Fish and Game or U.S. Fish and Wildlife Service?
b) Have a substantial adverse effect on any riparian habitat or other sensitive
natural community identified in local or regional plans, policies, regulations, or
by the California Department of Fish and Game or U.S. Fish and Wildlife
Service?
c) Have a substantial adverse effect on federally protected wetlands as defined by
Section 404 of the Clean Water Act (including, but not limited to, marsh, vernal
pool, coastal, etc.) through direct removal, filling, hydrological interruption, or
other means?
d) Interfere substantially with the movement of any native resident or migratory
fish or wildlife species or with established native resident or migratory wildlife
corridors, or impede the use of native wildlife nursery sites?
e) Conflict with any local policies or ordinances protecting biological resources,
such as a tree preservation policy or ordinance?
f) Conflict with the provisions of an adopted Habitat Conservation Plan, Natural
Community Conservation Plan, or other approved local, regional or state
habitat conservation plan?
The FEISÆIR found that implementation of the Reuse Plan and MCAS Tustin Specific Plan
would not result in impacts to federally listed threatened or endangered plant or animal
species. The proposed project is within the scope of development considered with the
analysis of the FEISÆIR for MCAS Tustin. The FEISÆIR determined that implementation
of the Reuse Plan and MCAS Tustin Specific Plan (including the proposed project) could
impact jurisdictional waters/wetlands and the southwestern pond turtle or have an impact on
jurisdictional waters/wetlands. The project site is not located in an area that would affect the
southwestern pond turtle or have an impact on jurisdictional waters or wetlands. No
substantial change is expected from the analysis previously completed in the FEISÆIR for
MCAS Tustin.
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
Page 6
Mitigation/Monitoring Required: No mitigation is required.
Sources:
Field Observations
FEISÆIR for Disposal and Reuse of MCAS Tustin (pages 3-75 through 3-
82,4-103 through 4-108, and 7-26 through 7-27)
MCAS Tustin Specific Plan (pages 3-145 to 3-154).
Tustin General Plan
v.
CULTURAL RESOURCES: - Would the project:
a) Cause a substantial adverse change in the significance of a historical resource as
defined in §15064.5?
b) Cause a substantial adverse change in the significance of an archaeological
resource pursuant to § 15064.5?
c) Directly or indirectly destroy a unique paleontological resource or site or unique
geologic feature?
d) Disturb any human remains, including those interred outside formal cemeteries?
Numerous archaeological surveys have been conducted at the former MCAS Tustin site. In
1988, the State Office of Historic Preservation (SHPO) provided written concurrence that all
open spaces on MCAS Tustin had been adequately surveyed for archaeological resources.
Although one archaeological site (CA-ORA-381) has been recorded within the Reuse Plan
area, it is believed to have been destroyed. It is possible that previously unidentified buried
archaeological or paleontological resources within the project site could be significantly
impacted by grading and construction activities. No substantial change is expected from the
analysis previously completed in the FEISÆIR for MCAS Tustin.
Mitigation/Monitoring Required: Mitigation measures have been adopted by the Tustin City
Council in the FEISÆIR; these measures would be included as conditions of approval for
the project.
Sources:
Field Observations
FEISÆIR for Disposal and Reuse of MCAS Tustin (pages 3-68 through 3-
74,4-93 through 4-102 and 7-24 through 7-26)
MCAS Tustin Specific Plan (pages 3-145 to 154).
Tustin General Plan
VI.
GEOLOGY AND SOILS: - Would the project:
a) Expose people or structures to potential substantial adverse effects, including the
risk of loss, injury, or death involving:
. Rupture of a known earthquake fault, as delineated on the most recent
Alquist-Priolo Earthquake Fault Zoning map, issued by the State Geologist
for the area or based on other substantial evidence of a known fault? Refer
to Division of Mines and Geology Special Publication 42.
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
Page 7
. Strong seismic ground shaking?
. Seismic-related ground failure, including liquefaction?
.
Landslides?
b) Result in substantial soil erosion or the loss of topsoil?
c) Be located on a geologic unit or soil that is unstable, or that would
become unstable as a result of the project, and potentially result in on-
or off-site landslide, lateral spreading, subsidence, liquefaction or
collapse?
d) Be located on expansive soil, as defined in Table 18-1-B of the Uniform Building
Code (1994), creating substantial risks to life or property?
e) Have soils incapable of adequately supporting the use of septic tanks or
alternative wastewater disposal systems where sewers are not available for the
disposal of wastewater?
The FEISÆIR indicates that impacts to soils and geology resulting from implementation of
the Reuse Plan and MCAS Tustin Specific Plan would "include non-seismic hazards (such
as local settlement, regional subsidence, expansive soils, slope instability, erosion, and
mudflows) and seismic hazards (such as surface fault displacement, high-intensity ground
shaking, ground failure and lurching, seismically induced settlement, and flooding
associated with dam failure." However, the FEISÆIR for MCAS Tustin concluded that
compliance with state and local regulations and standards, along with established
engineering procedures and techniques, would avoid unacceptable risk or the creation of
significant impacts related to such hazards. No substantial change is expected for
development of the project from the analysis previously completed in the FEISÆIR for
MCAS Tustin.
Mitigation/Monitoring Required: As identified in the FEISÆIR, compliance with existing
rules and regulations would avoid the creation of potential impacts. No mitigation is
required.
Sources:
Field Observations
FEISÆIR for Disposal and Reuse of MCAS Tustin (pages 3-88 through 3-
97,4-115 through 4-123 and 7-28 through 7-29)
MCAS Tustin Specific Plan (Pages 3-145 to 154).
Tustin General Plan
VII.
HAZARDS AND HAZARDOUS MATERIALS: - Would the project:
a) Create a significant hazard to the public or the environment through the routine
transport, use or disposal of hazardous materials?
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, 'IT 16582, DR 04-004, Density Bonus
Page 8
b) Create a significant hazard to the public or the environment through reasonable
foreseeable upset and accident conditions involving the release of hazardous
materials into the environment?
c) Emit hazardous emissions or handle hazardous or acutely hazardous materials,
substances, or waste within one-quarter mile of an existing or proposed school?
d) Be located on a site which is included on a list of hazardous materials sites
compiled pursuant to Government code Section 65962.5 and, as a result, would it
create a significant hazard to the public or the environment?
e) For a project located within an airport land use plan or, where sucþ a plan has
not been adopted, within two miles or a public airport or public use airport,
would the project result in a safety hazard for people residing or working in the
project area?
0 For a project within the vicinity of a private airstrip, would the project result in
a safety hazard for people residing or working in the project area?
g) Impair implementation of or physically interfere with an adopted emergency
response plan or emergency evacuation plan?
h) Expose people or structures to a significant risk of loss, injury or death involving
wildland fires, including where wildlands are adjacent to urbanized areas or
. where residences are intermixed with wildlands?
The project will not create a significant hazard to the public through the transport, use, or
disposal of hazardous materials, nor are there reasonably foreseeable upset and accident
conditions at the property. In addition, construction and residential uses would not emit
hazardous emissions within a quarter mile of an existing or proposed school.
In addition, the project site is located within the boundaries of the Airport Environs Land
Use Plan; however, it is at least four (4) miles from John Wayne Airport, and does not lie
within a flight approach or departure colTidor and thus does not pose an aircraft-related
safety hazard for future residents or workers. The project site is not located in a wildland
fire danger area. Compliance with all federal, state and local regulations concerning
handling and use of these hazardous substances will reduce potential impacts to below a
level of significance. No substantial change is expected from the analysis previously
completed in the FEISIEIR for MCAS Tustin.
Mitigation/Monitoring Required: As identified in the FEISIEIR, compliance with existing
rules and regulations would avoid the creation of potential impacts. No mitigation is
required.
Sources:
Field Observation
FEISIEIR for Disposal and Reuse of MCAS Tustin pages (3-106 through 3-
117,4-130 through 4-138 and 7-30 through 7-31)
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, TT 16582, DR 04-004, Density Bonus
Page 9
MCAS Tustin Specific Plan (pages3-145 to 3-154)
Tustin General Plan.
HYDROLOGY AND WATER QUALITY: - Would the project:
a) Violate any water quality standards or waste discharge requirements?
b) Substantially deplete groundwater supplies or interfere substantially with
groundwater recharge, such that there would be a net deficit in aquifer volume
or a lowering of the local groundwater table level (e.g., the production rate of
pre-existing nearby wells would drop to a level which would not support existing
land uses or planned uses for which permits have been granted)?
c) Substantially alter the existing drainage pattern of the site or area, including
through the alteration of the course of a stream or river, in a manner which
would result in flooding on- or off-site?
d) Substantially alter the existing drainage pattern of the site or area, including
through the alteration of the course of a stream or river, or substantially
increase the rate or amount of surface runoff in a manner, which would result in
flooding on- or off-site?
e) Create or contribute runoff water which would exceed the capacity of existing or
planned storm water drainage systems or provide substantial additional sources
of polluted runoff?
f) Otherwise substantially degrade water quality?
g) Place housing within a tOO-year flood hazard area as mapped on a federal Flood
hazard Boundary of Flood Insurance Rate Map or other flood hazard
delineation map?
h) Place within a tOO-year flood hazard area structures, which would impede or
redirect flood flows?
i) Expose people or structures to a significant risk of loss, injury or death involving
flooding, including flooding as a result of the failure of a levee or dam?
j) Inundation by seiche, tsunami, or mudflow?
The proposed project includes construction of 465 residential units that would increase
runoff. However, the project will not result in additional impacts beyond what was analyzed
in the adopted FEISÆIR. The project design and construction of facilities to fully contain
drainage of the site woulq be required as conditions of approval of the project. No long-term
impacts to hydrology and water quality are anticipated for the proposed project. The
proposed project will not impact groundwater in the deep regional aquifer or shallow
aquifer. The proposed project would not include groundwater removal or alteration of
historic drainage patterns at the site. The project is not located within a 1DO-year flood area
and will not expose people or structures to a significant risk of loss, injury and death
involving flooding as a result of the failure of a levee or dam, nor is the proposed project
susceptible to inundation by seiche, tsunami, or mudflow.
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, 'IT 16582, DR 04-004, Density Bonus
Page 10
Construction operations would be required to comply with the Total Maximum Daily Load
(TMDL) for the Newport Bay watershed that requires compliance with the Drainage Area
Master Plan (DAMP) and National Pollution Discharge Elimination System (NPDES) and
the implementation of specific best management practices (BMP). Compliance with state
and local regulations and standards, along with established engineering procedures and
techniques, would avoid unacceptable risk or the creation of significant impacts related to
such hazards. Consequently, no substantial change is expected from the analysis
previously completed in the FEISIEIR for MCAS Tustin.
Mitigation/Monitoring Required: As identified in the FEISIEIR, compliance with existing
rules and regulations would avoid the creation of potential impacts. No mitigation is
required.
Sources:
Field Observation
FEISIEIR for Disposal and Reuse of MCAS Tustin (pages 3-98 through 3-
105,4-124 through 4-129 and 7-29 through 7-30)
MCAS Tustin Specific Plan (pages 3-145 to 3-154)
FEMA Map (August 9, 2002)
Tustin General Plan
IX.
LAND USE AND PLANNING: Would the project:
a) Physically divide an established community?
b) Conflict with any applicable land use plan, policy, or regulation of an agency
with jurisdiction over the project (including, but not limited, to the general plan,
specific plan, local coastal program, or zoning ordinance) adopted for the
purpose of avoiding or mitigating an environmental effect?
c) Conflict with any applicable habitat conservation plan or natural community
conservation plan?
The City of Tustin is the controlling authority over implementation of the Reuse Plan for the
fonner base, such as land use designations, zoning categories, recreation and open space
areas, major arterial roadways, urban design, public facilities, and infrastructure systems.
On February 3,2003, the Tustin City Council approved the Specific Plan for MCAS Tustin
that established land use and development standards for development of the site. The
proposed project meets the density requirements of Table 3-2 of the MCAS Tustin Specific
Plan and development standards of Planning Areas 21 to Single Family Residential Units
and Multiple Family residential Units. New development standards are proposed for
development of the Carriage Way units and development of condominium units on parcels
less than 10 acres that will be considered as part of Specific Plan Amendment/Zone Change
04-002. The carriage way units are similar to the single family detached product with the
exception of the rear yard setback since access to the garage is proposed from a rear
alleyway. The new standard would create an appealing streetscape with elimination of
driveway approached on the main roads. Compliance with state and local regulations and
standards would avoid the creation of significant land use and planning impacts. Also, the
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, TT 16582, DR 04-004, Density Bonus
Page 11
proposed project will not conflict with any habitat conservation plan or natural community
conservation plan. Consequently, no change is expected from the analysis previously
completed in the FEISÆIR for MCAS Tustin.
MitigationIMonitoring Required: The proposed project is consistent with the development
standards of the MCAS Tustin Specific Plan as identified by the adopted FEISÆIR. No
mitigation is required.
Sources:
Field Observation
FEISIEIR for Disposal and Reuse of MCAS Tustin (pages 3-3 to 3-17, 4-3
to 4-13 and 7-16 to 7-18)
MCAS Tustin Specific Plan (pages 3-145 to 3-154).
Tustin General Plan
x.
MINERAL RESOURCES: Would the project:
a) Result in the loss of availability of a known mineral resource that would be a
value to the region and the residents of the state?
b) Result in the loss of availability of a locally important mineral resource recovery
site delineated on a local general plan, specific plan or other land use plan?
Chapter 3.9 of the FEISIEIR indicates that no mineral resources. are known to occur
anywhere within the Reuse Plan area. The proposed project will not result in the loss of
mineral resources known to be on the site or identified as being present on the site by any
mineral resource plans. Consequently, no substantial change is expected from the analysis
previously completed in the FEISIEIR for MCAS Tustin.
MitigationIMonitoring Required: No mitigation is required.
Sources:
Field Observation
FEISÆIR for Disposal and Reuse of MCAS Tustin (Page 3-91)
MCAS Tustin Specific Plan (pages 3-145 through 3-154).
Tustin General Plan
XI.
NOISE: Would the project:
a) Exposure of persons to or generation of noise levels in excess of standards
established in the local general plan or noise ordinance, or applicable standards
of other agencies?
b) Exposure of persons to or generation of excessive ground borne vibration or
ground borne noise levels?
c) A substantial permanent increase in ambient noise levels in the project vicinity
above levels existing without the project?
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
Page 12
d) A substantial temporary or periodic increase in ambient noise levels in the
project vicinity above levels existing without the project?
e) For a project located within an airport land use plan or, where such a plan has
not been adopted, within two miles of a public airport or public use airport,
would the project expose people residing or working in the project area to
excessive noise levels?
f) For a project within the vicinity of a private airstrip, would the project expose
people residing or working in the project area to excessive noise levels?
The proposed project could result in implementation activities that generate noise. The
FEISÆJR indicates that full build-out of the base will create noise impacts that would be
considered significant if noise levels experienced by sensitive receptors would exceed those
considered "normally acceptable" for the applicable land use categories in the Noise
Elements of the Tustin General Plan. A noise analysis was prepared for the project site that
includes sensitive receptors along Moffett A venue, Harvard A venue and Peters Canyon
Channel/Jamboree Road. The noise analysis concludes that special building construction
will be required to achieve a 45 dB interior noise level for units along these areas. No
substantial change is expected from the analysis previously completed in the approved
FEISÆJR for MCAS Tustin. However, the City of Tustin will ensure that construction
activities comply with the City's Noise Ordinance and the housing units are designed with
adequate noise attenuation (i.e., window design, sound walls) to meet the allowable noise
levels as required by Tustin City Code for residential use. The project would be sound
attenuated against present and projected noise so as not to exceed an exterior noise standard
of 65 dB CNEL in outdoor living areas and an interior standard of 45 dB CNEL in all
habitable rooms to reduce noise-related impacts to a level of insignificance. Compliance
with adopted mitigation measures and state and local regulations and standards, along with
established engineering procedures and techniques, will avoid unacceptable risk or the
creation of significant impacts related to such hazards.
Mitigation/Monitoring Required: Mitigation measures have been adopted by the Tustin
City Council in the FEISÆJR; these measures would be included as conditions of approval
for the project.
Sources:
Field Observation
FEISÆJR for Disposal and Reuse of MCAS Tustin (pages 3-154 to 3-162,
4-231 to 4-243 and 7-42 to 7-43)
MCAS Tustin Specific Plan (pages 3-145 through 3-154).
Tustin General Plan
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
< Page 13
XII.
POPULATION & HOUSING: Would the project:
a) Induce substantial population growth in an area, either directly (for example, by
proposing new homes and businesses) or indirectly (for example, through
extension of roads or other infrastructure)?
b) Displace substantial numbers of existing housing, necessitating the construction
of replacement housing elsewhere?
c) Displace substantial numbers of people, necessitating the construction of
replacement housing elsewhere?
The proposed project would construct 465 new residential units on a site that previously
contained military housing units that were vacant since 1997 and have been demolished.
The proposed project will not displace people or necessitate construction of replacement
housing elsewhere. The proposed number of residential units is consistent with the density
than was previously considered in the FEISÆIR for MCAS Tustin. The total number of
units for Planning Area 21 upon completion of the entire planning area would be consistent
with the number of units considered in the FEISÆIR for MCAS Tustin. No substantial
change is expected from the analysis previously completed in the FEISÆIR for MCAS
Tustin.
Mitigation/Monitoring Required: No mitigation is required.
Sources:
Field Observations
FEISÆIR for Disposal and Reuse of MCAS Tustin (pages 3-18 to 3-34, 4-
14 to 4-29 and 7-18 to 7-19)
MCAS Tustin Specific Plan (pages 3-145 through 3-154).
Tustin General Plan
XIII. PUBLIC SERVICES
a) Would the project result in substantial adverse physical impacts associated with
the provision of new or physically altered governmental facilities, need for new
or physically altered governmental facilities, the construction of which could
cause significant environmental impacts, in order to maintain acceptable service
ratios, response times, or other performance objectives for any of the public
services:
The site contains military housing which has been vacant since mid-1997. Development of
the site would require public services such as fire and police protection services, schools,
libraries, recreation facilities, and bikinglhiking trails.
Fire Protection. The proposed project will be required to meet existing Orange County
Fire Authority (OCFA) regulations regarding demolition, construction materials and
methods, emergency access, water mains, fire flow, fire hydrants, sprinkler systems,
building setbacks, and other relevant regulations. Adherence to these regulations would
reduce the risk of uncontrollable fire and increase the ability to efficiently provide fire
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
Page 14
protection services to the site. The number of fire stations in the areas surrounding the
site will meet the demands created by the proposed project.
Police Protection. The need for police protection services is assessed on the basis of
resident population estimates, square footage of non-residential uses, etc. Development of
the site would increase the need for police protection services. The developer as a condition
of approval for the project would be required to work with the Tustin Police Department to
ensure that adequate security precautions such as visibility, lighting, emergency access,
address signage are implemented in the project at plan check.
Schools. The proposed project is located within Irvine Unified School District (IUSD).
The implementation of the Reuse Plan provides for a 20-acre school site to IUSD to serve
the growing student population within its district. As a condition of approval for the
project, the developer would be required to pay applicable school fees to IUSD prior to
issuance of the building permit.
Other Public Facilities (Libraries). Implementation of the entire Reuse Plan would only
result in a library demand of up to approximately 2,500 square feet of library space. This
relatively small amount of space is well below the library system's general minimum size of
10,000 square feet for a branch library and would not trigger the need for a new facility.
General Implementation Requirements: To support development in the reuse plan area, the
Reuse Plan/Specific Plan requires public services and facilities to be provided concurrent
with demand. The proposed project will be required to comply with FEISÆIR
implementation measures adopted by the Tustin City Council.
No substantial change is expected from the analysis previously completed in the approved
FEISÆIR for MCAS Tustin for fire protection, police protection, and other public
facilities.
MitigationIMonitoring Required: Mitigation measures have been adopted by the Tustin
City Council in the FEISÆIR; these measures would be included as conditions of approval
for the project.
Sources:
Field Observation
FEISÆIR for Disposal and Reuse of MCAS Tustin (pages 3-47 to 3-57, 4-
56 to 4-80 and 7-21 to 7-22)
MCAS Tustin Specific Plan (Pages 3-145 through 3-154).
Tustin General Plan
XIV. RECREATION
a) Would the project increase the use of existing neighborhood and regional parks
or other recreational facilities, such that substantial physical deterioration of the
facility would occur or be accelerated?
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
Page 15
b) Does the project include recreational facilities or require the construction or
expansion of recreational facilities, which might have an adverse physical effect
on the environment?
The Reuse Plan provides for a new 84.S-acre Regional Park, a 24-acre Community Park and
two (2) Neighborhood Parks of at least five-acres each, and bike and hiking paths traversing
the property connecting to the bikeway/trail system, play areas associated with schools, and
child care facilities.
Since the Reuse Plan process included accommodation of public conveyance of
approximately 35 acres of city parks and 85 acres of Urban Regional Park, individual
developers were relieved of the requirement to dedicate land for park purposes. However,
pursuant to the MCAS Tustin Specific Plan, the developers are required to provide in-lieu
fees or public accessible park space (where approved by the City). This requirement will be
included in the conditions of approval for the project.
The proposed project would not generate an increase in the use of existing neighborhood
parks since a park site would be included in the site. Consequently, no substantial change is
expected from the analysis previously completed in the FEISÆIR for MCAS Tustin.
Mitigation/Monitoring Required: Mitigation measures have been adopted by the Tustin
City Council in the FEISÆIR; these measures would be included as conditions of approval
for the project.
Sources:
Field Observation
FEISÆIR for Disposal and Reuse of MCAS Tustin pages 3-47 to 3-57, 4-56
to 4-80 and 7-21 to 7-22
Reuse Plan and MCAS Tustin Specific Plan (pages 3-145 through 3-154)
Tustin Parks and Recreation Services Department
Tustin General Plan
xv.
TRANSPORTATIONffRAFFIC: Would the project:
a) Cause an increase in traffic, which is substantial in relation to the existing traffic
load and capacity of the street system (i.e., result in a substantial increase in
either the number of vehicle trips, the volume to capacity ratio on roads, or
congestion at intersections)?
b) Exceed, either individually or cumulatively, a level of service standard
established by the county congestion management agency for designated roads
or highways?
c) Result in a change in air traffic patterns, including either an increase in traffic
levels or a change in location that results in substantial safety risks?
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, TT 16582, DR 04-004, Density Bonus
Page 16
d) Substantially increase hazards due to a design feature (e.g., sharp curves or
dangerous intersections) or incompatible uses (e.g., farm equipment)?
e) Result in inadequate emergency access?
f) Result in inadequate parking capacity?
g) Conflict with adopted policies, plans, or programs supporting alternative
transportation (e.g., bus turnouts, bicycle racks)?
The FEISÆIR indicates that transportation and circulation impacts would be created
through the phased development of the approved Reuse Plan and MCAS Tustin Specific
Plan. A projected 216,445 Average Daily Trips (ADT) would be generated by full
redevelopment of the base by year 2020 that, if left unmitigated, would overburden
existing roadways and intersections surrounding the base property. The FEISIEIR
indicates that traffic circulation activities at MCAS Tustin generated a baseline of 12,400
ADT when the base was fully operational (1993). As a military facility, the FEISIEIR
considered the traffic impact and developed a mitigation program to reduce potential
impacts to a level of insfgnificance. This project will be conditioned to participate in its fair
share responsibility for both on-site and off-site circulation mitigation and implementation
measures. In addition, construction activities are required to be meet all Transportation
related FEISÆIR Implementation and Mitigation Measures (e.g., lane closures, street/utility
construction, construction vehicle traffic, etc.). The FEISÆIR implementation and
mitigation measures will reduce potential impacts to the traffic and circulation system to a
level of insignificance. Consequently, no substantial change is expected from the analysis
previously completed in the approved FEISÆIR for MCAS Tustin.
Based upon the Traffic Study for Columbus Grove project (planning Area 21, the traffic
generation identified for the 465 residential units is less than the Trip Budget identified in
the Specific Plan. When compared with the Trip Budget contained in Chapter 3 of the
Specific Plan, the proposed project ADT is decreased by 1,427. The development is also
required to pay its fair share contribution to the Tustin legacy Backbone Infrastructure
Program which includes major arterial and secondary roadway systems. Therefore, there
would not be additional impacts associated with the proposed project's traffic.
Mitigation/Monitoring Required: Mitigation measures have been adopted by the Tustin City
Council in the FEISÆIR; these measures would be included as conditions of approval for
the project.
Sources:
Field Observation
FEISÆIR for Disposal and Reuse of MCAS Tustin (Pages 3-118 through 3-
142,4-139 through 4-206 and 7-32 through 7-41)
Reuse Plan and MCAS Tustin Specific Plan (pages 3-145 through 3-154).
Tustin General Plan
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, 'IT 16582, DR 04-004, Density Bonus
Page 17
XVI. UTILITIES AND SERVICE SYSTEMS: Would the project:
a) Exceed wastewater treatment requirements of the applicable Regional Water
Quality Control Board?
b) Require or result in the construction of new water or wastewater treatment
facilities or expansion of existing facilities, the construction of which could cause
significant environmental effects?
c) Require or result in the construction of new storm water drainage facilities or
expansion of existing facilities, the construction of which could cause significant
environmental effects?
d) Have sufficient water supplies available to serve the project from existing
entitlements and resources, or are new or expanded entitlements needed?
e) Result in.a determination by the wastewater treatment provider, which serves or
may serve the project that it has adequate capacity to serve the project's
projected demand in addition to the provider's existing commitments?
f) Be served by a landfill with sufficient permitted capacity to accommodate the
project's solid waste disposal needs?
g) Comply with federal, state, and local statutes and regulations related to solid
waste?
The FEIRÆIR analyzed low-density residential development on the proposed site, which
is consistent with the proposed project. Development of the site would require on-site
improvements and off-site infrastructure improvements to utilities and roadway systems,
including funding for 50 percent of the design and construction of Moffett A venue from
Harvard Avenue to Peters Canyon Wash Bridge. Improvements to Moffett Avenue
would include design and installation of a Class II bike trail, a new domestic water line if
required by the Irvine Ranch Water District, a new brine line, a new reclaimed water line
if required by the Irvine Ranch Water District, a new sanitary sewer line if required by
the Irvine Ranch Water District, a storm drain with adequate capacity to accommodate
runoff from the proposed development. The developer will be responsible for its fair
share contribution to Tustin Legacy Backbone Infrastructure Improvement Program
which includes but is not limited to roadways, water, sewer, and backbone underground
dry utilities (electric, gas, cable TV, telephone, etc). In addition, development of the site
is required to meet federal, state, and local standards for design of wastewater treatment.
The number of proposed units can be supported by the Irvine Ranch Water District for
domestic water and sewer services. Improvements to Peters Canyon Channel will be
installed at a later date adjacent to Parcel 35 through an implementation agreement
between the City of Tustin and the Orange County Flood Control District (OCFCD) as
previously required by the adopted FEISIEIR. Improvements adjacent to Parcel 36 will
be the responsibility of the developer including all jurisdictional wetland mitigation
subject to provisions of a Cooperative Agreement between the developer and the City of
Tustin. No substantial change is expected from the analysis previously completed in the
FEISIEIR for MCAS Tustin.
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, TI 16582, DR 04-004, Density Bonus
Page 18
Mitigation/Monitoring Required: Mitigation measures have been adopted by the Tustin
City Council in the FEISÆIR; these measures would be included as conditions of approval
for the project.
Sources:
Field Observations
FEISÆIR for Disposal and Reuse of MCAS Tustin (pages 3-35 through 3-
46,4-32 through 4-55 and 7-20 through 7-21)
Reuse Plan and MCAS Tustin Specific Plan (pages 3-145 through 3-154).
Tustin General Plan
XVII. MANDA TORY FINDINGS OF SIGNIFICANCE
a) Does the project have the potential to degrade the quality of the environment,
substantially reduce the habitat of a fish or wildlife species, cause a fish or
wildlife population to drop below self-sustaining levels, threaten to eliminate a
plant or animal community, reduce the number or restrict the range of a rare or
endangered plant or animal or eliminate important examples of the major
periods of California history or prehistory?
b) Does the project have impacts that are individually limited but cumulatively
considerable? ("Cumulatively considerable" means that the incremental effects
of a project are considerable when viewed in connection with the effects of past
projects, the èffects of other current projects, and the effects of probable future
projects.)
c) Does the project have environmental effects, which will cause substantial
adverse effects on human beings, either directly or indirectly?
Based upon the foregoing, the proposed project does not have the potential to degrade the
quality of the environment, substantially reduce the habitats of wildlife populations or
decrease or threaten, eliminate, or reduce animal ranges, etc. With the enforcement of
FEISÆIR mitigation and implementation measures approved by the Tustin City Council,
the proposed project does not cause unmitigated environmental effects that will cause
substantial effects on human beings, either directly or indirectly. In addition, the proposed
project does have air quality impacts that are individually limited, but cumulatively
considerable when viewed in connection with the effects of the reuse and redevelopment of
the former MCAS Tustin. The FEISÆIR previously consídered all environmental impacts
associated with the implementation of the Reuse Plan and MCAS Tustin Specific Plan. The
project proposes no substantial changes to environmental issues previously considered with
adoption of the FEISÆIR. Mitigation measures were identified in the FEISÆIR to reduce
impact but not to a level of insignificance. A Statement of Overnding Consideration for the
FEISÆIR was adopted by the Tustin City Council on January 16, 2001.
Mitigation/Monitoring Required: The FEISÆIR previously considered all environmental
impacts associated with the implementation of the Reuse Plan and MCAS Tustin Specific
Attachment 1 to Exhibit A of Resolution No. 3943
Evaluation of Environmental Impacts
ZC 04-002, CP 03-004, IT 16582, DR 04-004, Density Bonus
Page 19
Plan. Mitigation measures have been adopted by the Tustin City Council in the FEIS/EIR
and would be included in the project as applicable.
Sources:
Field Observations
FEISÆIR for Disposal and Reuse of MCAS Tustin (pages 5-4 through 5-11)
Reuse Plan and MCAS Tustin Specific Plan (pages 3-145 through 3-154).
Tustin General Plan
CONCLUSION
The summary concludes that all of the proposed project's effects were previously examined in the
FEISÆIR for MCAS Tustin, that no new effects would occur, that no substantial increase in the
severity of previously identified significant effects would occur, that no new mitigation measures
would be required, that no applicable mitigation measures previously not found to be feasible
would in fact be feasible, and that there are no new mitigation measures or alternatives applicable
to the project that would substantially reduce effects of the project that have not been considered
and adopted. A Mitigation and Monitoring and Reporting Program and Findings of Oveniding
Considerations were adopted for the FEISÆIR on January 16,2001 and shall apply to the proposed
project, as applicable.
S:\Cdd\MINOO\MCAS Tustin\Planning Area 21- Tract 16507\JLH-PA 21-Initial Study-analysis.doc
ATTACHMENT 2 TO EXHIBIT A OF RESOLUTION NO. 3943
PLANNING AREA 21 OF MCAS TUSTIN SPECIFIC PLAN
MARBLE MOUNTAIN PARTNERS LLC TRACT 16582
Mitigation and Implementation Measures
The Final EIS/EIR for the Disposal and Reuse ofMCAS Tustin considered the redevelopment of the entire former base as proposed in the approved specific plan.
The following identities only those EIRIEIS mitigation and implementation measures that are required ofthe proposed project as identified in the "Environmental
Checklist." All other mitigation/implementation measures identified in the final EIS/EIR are not applicable to this project*. Implementation measures are to be
required where environmental impacts are less than significant, but to support proposed development within the reuse plan area. Both implementation and
mitigation measures are identified in the adopted Mitigation and Monitoring Report Program (Resolution No. 00-090) and are equally enforceable.
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
Implementation Measures for Utilities
(a) The City of Tustin or City of Irvine, as appropriate, shall
ensure that intTastructure is constructed in phases as Per Table 4.3-1 of the Mitigation City Public Works Department
triggered by identified threshold in Table 4.3-1. The Monitoring Program and Community
Phasing Plan provides an organizational tTamework to Redevelopment Agency
facilitate development of the reuse plan area in tandem The project complies with
with intTastructure necessary to support the planned phasing requirements; all
subdivision infrastructure
development. This tTamework reflects the fact that each will be provided by the
component of the intTastructure has its own threshold for
accommodating additional development toward built-out applicant as conditioned
by Resolution Nos. 3946
of the reuse plan area. The triggering mechanisms that and 3947
identify timing of key intTastructure provisions are
summarized in Table 4.3-1.
(b) Prior to a fmal map recordation (except for financing and Prior to fmal map recordation Project developer Community Development
reconveyance purposes), the development applicant shall (except for fmancing and Department (Tustin and/or
enter into an agreement with the City of Tustin and City reconveyance purposes). Conditions 3.3 of Irvine, as applicable)
of Irvine and any appropriate regional utility agencies, Resolution No. 3946
Attachment 2 of Exhibit A of Resolution No. 3943
1
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
districts, and providers, as applicable, to dedicate all
easement, rights-of-way, or other land determined
necessary to construct adequate utility intrastructure and
facilities to serve the project as determined by the city,
agency, district, or other providers.
(c) Prior to any fmal map recordation (except for fmancing Prior to fmal map recordation Project developer Community Development
and conveyance purposes), the development applicant (except for financing and Condition 4.1 of Department (Tustin and/or
shall enter into a secured agreement with the cities of reconveyance purposes). Resolution No. 3946 Irvine, as applicable)
Tustin and/or Irvine, as applicable, to participate on a
pro-rated basis in construction of capital improvements
necessary to provide adequate utility facilities.
(d) Prior to the issuance of permits for any public Prior to the issuance of permits Project developer Community Development
improvements or development project, a development for any public improvements or Department (Tustin and/or
applicant shall submit to the City of Tustin and City of development project. Provided with Irvine, as appropriate)
Irvine, as applicable, information trom IR WD which Development Application
outlines required facilities necessary to provide adequate of Tract 16582
potable water and reclaimed water service to the
development.
(e) Prior to the issuance of the certificates of use and Prior to the issuance of the Project developer Community Development
occupancy, the project developer shall ensure that fIre certificates of use and occupancy. Department (Tustin and/or
hydrants capable of flows in amounts approved by the Condition 11.1 Resolution Irvine, as appropriate);
OCF A are in place and operational to meet fire flow 3947 OCFA
requirements.
(f) Prior to the issuance of permits for any public Prior to the issuance of permits Project developer Community Development
improvements or development project, a development for any public improvements or Department (Tustin and/or
applicant shall submit to the City of Tustin and City of development project. Provided with Irvine, as applicable)
Irvine, as applicable, information trom IRWD, OCSD, or Development Application
the City of Tustin which outlines required facilities of Tract 16582
necessary to provide adequate sanitary sewage service to
the development.
(g) Prior to the issuance of grading permits or approval of any Prior to the issuance of grading Project developer Tustin Building Division or
subdivision maD (exceot for fmancing and reconveyance oennits or aooTOval of any the Irvine Public Works
Attachment 2 of Exhibit A of Resolution No. 3943
2
Mitigation Monitoring and Reporting Program
Measure. Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
purposes), whichever occurs fITst, for development within subdivision map (except for Department, as applicable
the 100-year flood plain, grading and drainage systems fmanêing and reconveyance Site Dot within the 100-
shall be designed by the project developer such that all purposes), whichever occurs first year flood pain (FEMA
building pads would be safe from inundation from runoff Map dated August 9,
from all storms up to and including the theoretical 2002)
100-year storm, to the satisfaction of the City of Tustin
Building Division or the Irvine Public Works Department,
as applicable. Grading permits or subdivision maps
generated for fmancing and reconveyance purposes are
exempt.
(h) Prior to construction of regional flood control facilities, Prior to construction of regional Project developer Public Works Department
appropriate state and federal approvals, including flood control facilities. (Tustin and/or Irvine, as
agreements and permits, shall be obtained. These include Condition 6.1 of applicable)
but are not limited to Regional Water Quality Control Resolution 3947
Board permits, including NPDES permits; Section 404
permits from the USACOE, and Section 1601 or 1603
agreements from the CDFG in a manner meeting the
approval of the City of Tustin and the Irvine Public
Works Department, as applicable.
(i) Prior to issuance of any grading permit or approval of any Prior to issuance of any grading Project developer Tustin Building Division or
subdivision map (except for fmancing and conveyance permit or approval of any the Irvine Public Works
purposes), for any development that is either partially or subdivision map (except for Site not within the 100- Department, as applicable
completely located within the 100-year flood plain of the fmancing and conveyance year flood pain (FEMA
Flood Insurance Rate Map, the development applicant purposes).
shall submit all required documentation to the FEMA and Map dated August 9,
demonstrate that the application for a Conditional Letter 2002)
of Map Revision for changes to the 100-year flood plain
is satisfied in a manner meeting the approval of each
respective city, as applicable.
(k) Prior to any grading for any new development, the Project developer Tustin Building Division or
followmg drainage studies shall be submitted to and Public Works Department
approved by the City of Tustin, City of Irvine, and/or (Tustin and/or Irvine, as
OCFCD, as applicable: applicable)
3
Mitigation Monitoring and Reporting Program
Attachment 2 of Exhibit A of Resolution No. 3943
1
. !
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
(1) A drainage study including diversions (i.e., Prior to any grading for any new Condition 5.4 of
off-site areas that drain onto and/or through the development. Resolution 3946
project site), with justification and appropriate
mitigation for any proposed diversion.
(2) A drainage study evidencing that proposed Prior to any grading for any new Project developer Tustin Building Division or
drainage patterns would not result in increased development. Public Works Department
I OO-year peak discharges within and (Tustin and/or Irvine, as
downstream of the project limits, and would not applicable)
worsen existing drainage conditions at stonn
drains, culverts, and other street crossings Condition 3.8 of
including regional flood control facilities. The Resolution 3946
study shall also propose appropriate mitigation
for any increased runoff causing a worsening
condition of any existing facilities within or
downstream of project limits. Implementation
of appropriate interim or ultimate flood control
infTastructure construction must be included.
(2) Detailed drainage studies indicating how, in Prior to any grading for any new Project developer Tustin Building Division or
conjunction with the drainage conveyance systems development. Public Works Department
including applicable swales, channels, street flows, Conditions 3.8 & 5.4 of (Tustin and/or Irvine, as
catch basins, stonn drains, and flood water retarding, Resolution 3946 applicable) .
building pads are made safe fTom runoff inundation
which may be expected fTom all stonns up to and
including the theoretical IOO-year flood.
(I) Prior to approval of any subdivision map (except for Prior to approval of any
fmancing or conveyance purposes), an agreement will be City Tustin Public Works
executed with the OCFCD that provides for the subdivision map Department and Community
identification and contribution of a project-specific fair Redevelopment Agency
share contribution toward the construction of ultimate Conditions 4.1 & 4.2 of
flood control faculties needed to accommodate built-out Resolution 3946
of the affected project. Interim flood control facilities
may be considered for approval provided such facilities
meet OCFCD reQuirements. Nothing shall preclude the
Attachment 2 of Exhibit A of Resolution No. 3943
4
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
City of Tustin from transferring the obligation onto other
oroiect develooers within the oroiect area.
Implementation Measures for Public Services and Facilities
(m) General Project developer
The City of Tustin and the City ofIrvine, each within its
respective jurisdiction, shall ensure that adequate fIfe
protection, police protection, and parks and recreation
facilities (including bikeways/trails) needed to adequately
serve the reuse plan area shall be provided as necessary.
To eliminate any negative impact the project could have
on each community's general fund, fmancing mechanisms
including but not limited to developer fees, assessment
district fmancing, and/or tax increment fmancing (in the
event that a redevelopment project area is created for the
site), shall be developed and used as determined
appropriate by each City. Specifically;
(1) Applicants for private development projects shall Prior to final map recordation or Resolution 14.1 of Community Development
be required to enter into an agreement with City building permit issuance Resolution 3947 Department
of Tustin or the City of Irvine, as applicable, to
establish a fair-share mechanism to provide
needed fIfe and police protection services and
parks and recreation facilities (including -
bikeways) through the use of fee schedules,
assessment district fmancing, Community
Facility District fmancing, or other mechanisms
as determined appropriate by each respective
city.
(2) Recipients of property through public
conveyance process shall be required to mitigate
any impacts of their public uses of property on
public services and facilities.
(n) The cities of Tustin and Irvine shall jointly consult and Prior to fmal map recordation or Agreement executed Community Development
coordinate with the OCPFRD/Harbors, Beaches and building permit issuance between City and OCFCD Department (Tustin and/or
Attachment 2 of Exhibit A of Resolution No. 3943
5
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
parks, Program management and Coordination Division, Irvine, as applicable)
in preparation of trail designs for the Peters Canyon and
Barranca trails within the reuse plan area. Improvements
for each ofthese trails would be installed upon
completion of flood control channel improvements and
approval of their joint use by the OCPFRD.
(0) Fire ProtectionÆmergencv Medical Services Prior to the fITst fmal map Project developer Tustin Community
recordation or building pennit Redevelopment Agency and
Prior to the first final map recordation or building permit issuance for development (except Not Applicable the City of Irvine
issuance for development (except for fmancing and for fmancing and reconveyances
reconveyances purposes), the project developer could be purposes).
required to enter into an agreement with the City of Tustin
or City of Irvine/OCF A, as applicable, to address impacts
of the project on fire services. Such agreement could
include participation for fire protection, personnel and
equipment necessary to serve the project and eliminate
any negative impacts on fire protection services.
(p) Prior to issuance of building penn its, the project Prior to issuance of building Project developer Community Development
developer shall work closely with the OCF A to ensure pennits. Department (Tustin and/or
that adequate fire protection measures are implemented in Conditions 11.1 to 11.5 of Irvine, as applicable)
the project. Resolution 3947
(q) Prior to issuance of building penn its for phased projects, Prior to issuance of building Project developer Community Development
the project developer shall submit a construction phasing pennits for phased projects. Department (Tustin and/or
plan to the OCF A demonstrating that emergency vehicle Conditions 11.1 to 11.5 of Irvine, as applicable)
access is adequate. Resolution 3947
(r) Prior to the issuance of building pennits, the project Prior to issuance of building Project developer Community Development
developer shall submit a fITe hydrant location plan for the pennits. Department (Tustin and/or
review and approval of the Fire Chief and ensure that fITe Conditions 11.1 to 11.5 of Irvine, as applicable)
hydrants capable of flows in amounts approved by the Resolution 3947
OCF A are in place and operational to meet fITe flow
Attachment 2 of Exhibit A of Resolution No. 3943
6
Mitigation Monitoring and Reporting Program
Measure. Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
requirements.
(s) Police Protection Prior to issuance of building Project developer Community Development
permits. Department (Tustin Police)
Prior to issuance of building permits, the project Condition 13.1G of
developer shall work closely with the respective Police Resolution 3947
Department to ensure that adequate security precautions
are implemented in the project.
(t) Schools Prior to the issuance of Project developer Community Development
certificates of use and occupancy. Department (Irvine Unified
Prior to the issuance of certificates of use and occupancy, Condition 14.1 of School District)
the project developer shall submit to the respective City Resolution 3947
proof of payment of appropriate school fees adopted by
the applicable school district.
(u) Parks and Recreation Prior to the first final map Project developer Tustin Community
recordation (except for financing Development Department
Prior to the fIrst final map recordation (except for and reconveyance purposes) or Condition 12.1 & 12.2 of and Parks and Recreation
fmancing and reconveyance purposes) or building permit building permit issuance. Resolution 3946 Department
issuance for development within the City of Tustin
portion of the site, the project developer shall be required
to provide evidence of compliance with all requirements
and standards ofthe City of Tustin Park Code.
(v) Prior to the first fmal map recordation or building permit Prior to the first final map Project developer Irvine Community
issuance within the City ofIrvine portion of the site, the recordation (except for financing Not ~pplicable to tracts in Development Department
project developer shall be required to provide evidence of and reconveyance purposes) or Tustin
compliance with all requirements and standards of the building permit issuance.
City of Irvine Park Code.
(w) Prior to the first concept plan for tentative tract map in the Prior to the first concept plan for Condition 9.1 of resolution Tustin Public Works
City of Tustin, the project developer shall file a petition tentative tract map. No. 3946 Department; Tustin
for the creation of a landscape maintenance district for the Community Redevelopment
7
Mitigation Monitoring and Reporting Program
Attachment 2 of Exhibit A of Resolution No. 3943
(
J
l- --¡
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
project area with the City of Tustin. The district shall Agency
include public neighborhood parks, landscape
improvements, and specific trails (Barranca only), the
medians in arterials, or other eligible items mutually
agreed to by the petitioner and the City of Tustin. In the
event that a district is not established prior to issuance of
the first building permit, maintenance of items mentioned
above shall be the responsibility of a community
association.
(x) Prior to approval of any subdivision map (except for Prior to approval of any Project developer Community Development
fmancing or conveyance purposes), an agreement will be subdivision map (except for Department (Tustin and/or
executed with the following agencies for the associated fmancing or conveyance Condition 4.2 of Irvine, as applicable)
trail improvements: purposes). Resolution No. 3946
a. County of Orange Harbors, Beaches -
identification of a project-specific fair share
contribution toward the installation of necessary
regional bikeway trail improvements within
Peters Canyon Channel, to be installed in
conjunction with the County of Orange's other
channel improvements;
b. City of Tustin - the identification of a Prior to the first final map Project developer Tustin Community
project-specific fair share contribution toward recordation (except for financing Development Department
the installation of Class II bicycle trails through and reconveyance purposes) or Not applicable and/or SCRRNOCT A, as
the project site. For the area of the site northeast building permit issuance. appropriate
of Irvine Center Drive, a separate agreement
would be required to ensure the provision of a
bikeway right-of-way easement, and design and
construction of a bike trial along the
SCRRA/OCT A rail tracks from Harvard Avenue
westerly to the Peters Canyon Channel. In
addition, project developers of the areas of the
site southeast of the Peters Canyon Channel
would need to accommodate access to both the
Peters Canyon Trail and the trail adjacent to the
SCRRA/OCT A tracks in any project site design
Attachment 2 of Exhibit A of Resolution No. 3943
8
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
including dedication of any necessary
recreational trail easements;
c. City of Tustin - the identification of a Prior to the first fmal map Project developer Tustin Community
project-specific fair-share contribution toward recordation (except for financing Development Department
installation of Class I bikeway trail and reconveyance purposes) or Not applicable
improvements northerly of Barranca Parkway building permit issuance.
after completion of the Barranca Channel
improvements. For proposed developments
adjacent to Barranca Channel, separate
agreements would be required to ensure the
establishment of a bikeway right-of-way
easement between Jamboree Road and Red Hill
Avenue.
Mitigation Measures for Aesthetics
Vis-l In conjunction with any zoning ordinance amendments to Prior to the first fmal map City of Tustin and City of Community Development
implement the reuse plan in Tustin or Irvine, an urban recordation (except for financing Irvine Department (Tustin and/or
design plan shall be adopted to provide for distinct and and reconveyance purposes) or Irvine, as applicable)
cohesive architectural and landscape design, features and building permit issuance.
treatments, as well as harmony with adjacent landscaping. Conditions 7.1 to 7.9 and
The urban design plan shall have the following elements:
. landscaping concept and master signage plan; 8.1 to 8.8 of Resolution
3947
. design review and approval process;
. limits on development intensity for each specific land
use;
. limits on height of structures and lot coverage;
. minimum site building setbacks;
. minimum on-site landscaping requirements;
. buffering requirements, including berms, masonry
walls, and landscaping;
. lighting regulations, including regulations ensuring
that exterior lighting does not negatively impact
surrounding property;
. screening regulations for mechanical equipment and
outside storage; and
Attachment 2 of Exhibit A of Resolution No. 3943
9
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
site signage requirements, including sign pennit
approval
Mitigation Measures for Cultural and Paleontological Resources
Arch- I Prior to issuance of grading pennits, the four-acre parcel Prior to issuance of grading Project developer Tustin Community
currently outside the boundaries ofthe Air Station along pennits. Not applicable to this Development Department
Harvard Avenue shall be surveyed to detennine the project
presence/absence of archaeological resources prior to
grading.
Arch-2 Prior to issuance of grading pennits, the cities of Tustin Prior to issuance of grading Project developer Community Development
and Irvine shall each require applicants of individual pennits. Department (Tustin and/or
development projects to retain, as appropriate, a county- Condition 13.1 of Irvine, as applicable)
certified archaeologist. If buried resources are found Resolution 3947
during grading within the reuse plan area, a qualified
archaeologist would need to assess the site significance
and perfonn the appropriate mitigation. The Native
American view point shall be considered during this
process. This could include testing or data recovery.
Native American consultation shall also be initiated
during this process.
Paleo- I The cities of Tustin and Irvine shall each require Prior to issuance of grading Project developer Community Development
applicants of individual development projects to comply pennits. Department (Tustin and/or
with the requirements established in a PRMP prepared for Condition 13.1 of Irvine, as applicable)
the site, which details the methods to be used for Resolution 3947
surveillance of construction grading, assessing finds, and
actions to be taken in the event that unique
paleontological resources are discovered during
construction.
Paleo-2 Prior to the issuance of a grading pennit, project Prior to issuance of grading Project developer Community Development
applicants shall provide written evidence to each city, that pennits. Department (Tustin and/or
a county-certified paleontologist has been retained to Condition 13.1 of Irvine, as applicable)
conduct salvage excavation of unique paleontological Resolution 3947
resources if they are found.
Attachment 2 of Exhibit A of Resolution No. 3943
10
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
Mitigation Measures for Traffic/Circulation
T/C-l Construction Prior to site development permit. Project developer Public Works Department
(Tustin or Irvine, as
In conjunction with the approval of a site development Condition 13.1 of applicable)
permit, the City of Tustin and the City of Irvine, as Resolution 3947
applicable (for that portion of the reuse plan within
Irvine), shall require each developer to provide traffic
operations and control plans that would minimize the
traffic impacts of proposed construction activity. The
plans shall address roadway and lane closures, truck hours
and routes, and notification procedures for planned
short-term or interim changes in traffic patterns. The City
of Tustin and the City ofIrvine, as applicable, shall
ensure that the plan would minimize anticipated delays at
major intersections. Prior to approval, the City of Tustin
or the City oflrvine, as applicable shall review the
proposed traffic control and operations plans with any
affected jurisdiction.
T/C-2 Development Prior to issuance of certificates of Project developer Public Works Department
occupancy. (Tustin or Irvine, as
The City of Tustin and the City of Irvine, as applicable Staff received final traffic applicable)
(for that portion of the reuse plan area within Irvine), shall study addressing
ensure that the arterial intersection improvements required cumulative ADT
in 2005 and 2020 and as indicated in Tables 4.12-7 and thresholds and fair share
4.12-9 of the Final EISÆIR (see Tables 2 and 4 and at the responsibility for
end of this Mitigation Monitoring and Reporting mitigation improvements;
Program) are implemented for their respective traffic study determined
jurisdictions according to the cumulative ADT thresholds need for traffic signal at
identified in each table and according to the fair share Harvard; required by
basis noted. The ADT threshold represents the traffic various Conditions of
volume which would result in an impact and the fair share Resolution No. 3946
percentage reflects the percent of the traffic impact
resulting from the reuse generated traffic. In some cases,
reuse traffic would generate 100 percent of the impact,
thereby assuming full financial responsibility for the
identified improvements. In other cases, reuse traffic
Attachment 2 of Exhibit A of Resolution No. 3943
11
Mitigation Monitoring and Reporting Program
'I
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
would generate only a fraction of the traffic impacting the
intersection and [mancial responsibility would
correspond.
T/C-3 The City of Tustin and the City ofIrvine, as applicable See Table 4.12-8 of the Final Project developer Public Works Department
(for that portion of the reuse plan area within Irvine), shall EISÆIR or Table 3 at the end of (Tustin or Irvine, as
contribute, on a fair share basis, to improvements to the Mitigation Monitoring and Addressed by backbone applicable)
fieeway ramp intersections as listed in Table 4.12-8 of the Reporting Program for each infrastructure fee
Final EISÆIR (see Table 3 at the end of the Mitigation specific triggering mechanism. requirement in Condition
Monitoring and Reporting Program). The method of 4.1 Resolution 3946
implementing improvements, e.g., restriping, ramp
widening, shall be based on special design studies, in
association with Caltrans.
T/C-4 The City of Tustin and the City ofIrvine, as applicable Ongoing (see Table 4.12-10 of Project developer Public Works Department
(for that portion of the reuse plan area within Irvine), shall the Final EISÆIR or Table 5 at (Tustin or Irvine, as
ensure that all on-site circulation system improvements the end of the Mitigation Addressed by backbone applicable)
for the reuse plan area assumed in the 2005 and 2020 Monitoring and Reporting infrastructure fee
traffic analysis and as shown in Table 4.12-10 of the Final Program for each specific requirement in Condition
EISÆIR (see Table 5 at the end of the Mitigation triggering mechanism. 4.1 of Resolution 3946
Monitoring and Reporting Program) are implemented
according to the cumulative ADT thresholds identi.fied in
the table. Under this Phasing Plan, the City of Tustin
shall monitor all new development within the site,
accounting for the cumulative ADT generated by
development projects. As each ADT threshold is reached,
the roadway improvements listed in Table 4.12-10 of the
Final EISÆIR (see Table 5 at the end of the Mitigation
Monitoring and Reporting Program) shall be constructed
before any additional projects within the reuse plan area
would be approved.
TIC-51 Prior to approval of a site development pennit or vesting Ongoing, prior to approval of a Project developer Public WorkslCommunity
tract, except for financing or conveyance purposes, for all site development pennit or Required by Condition 4.1 Development Departments
Table references in the mitigation measures have been changed from Final FEISÆIR to match the correct table numbers in the FEISÆIR.
Attachment 2 of Exhibit A of Resolution No. 3943
12
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
land use designation areas in Alternative I with the vesting tract, except for fmancing of Resolution 3946 (Tustin and/or Irvine, as
exception of the Learning Village, Community Park, and or conveyance purposes, based on applicable)
Regional Pàrk, a project developer shall enter into an the ADT generation thresholds
agreement with the City of Tustin and City of Irvine, as shown in Tables 4.12-7, 4.12-8,
applicable (for that portion of the reuse plan area within 4.12-9, and 4.12-10 of the Final
Irvine) which assigns improvements required in the EISÆIR (see Tables 2 through 5
EISÆIR to the development site and which requires at the end of the Mitigation
participation in a fair share mechanism to design and Monitoring and Reporting
construct required on-site and arterial improvements Program for each specific
consistent with the ADT generation thresholds shown in triggering mechanism).
Tables 4.12-7, 4.12-8, 4.12-9, and 4.12-10 (see Tables 2
through 5 at the end of the Mitigation Monitoring and
Reporting Program).
T/C-61 The City of Tustin and the City of Irvine, as applicable Ongoing, based on the ADT Project developer Public Works and
(for that portion of the reuse plan area in Irvine), will generation thresholds shown in Community Development
monitor new development within the reuse plan area, Table 4.12-10 of the Final Final traffic study Departments (Tustin and/or
accounting for the cumulative ADTs generated by EISÆIR (see Table 5 at the end identified cumulative Irvine, as applicable)
development projects within the reuse plan area. As each of the Mitigation Monitoring and ADTs; City monitoring
cumulative ADT threshold shown in Table 4.12-10 (see Reporting Program for each
Table 5 at the end of the Mitigation Monitoring and specific triggering mechanism). will determine timing of
Reporting Program) is reached, the roadway roadway improvements
identified in MMP Table
improvements listed shall be constructed before any 5; per project final traffic
additional projects within the reuse plan area are study, project does not
approved. exceed ADT threshold
level requiring roadway
improvements shown in
Table 5.
IA-l Table 4, 12-10 of the Final EISÆIR (see Table 5 at the See Table 4.12-10 of the Final City of Tustin Community Development
end of the Mitigation Monitoring and Reporting Program) EISÆIR or Table 5 at the end of and Public Works
presents the Phasing Plan for the on-site circulation the Mitigation Monitoring and Final traffic study Departments (Tustin and/or
system. The Phasing Plan for the on-site circulation Reporting Program for each identified cumulative Irvine, as applicable)
system. The Phasing Plan is based upon traffic circulation specific triggering mechanism. ADTs; City monitoring
impact and mitigation analyses contained in the Traffic
Report (Final Ap¡:iendix F of the Final EISÆIR). Under will determine timing of
this Phasing Plan, the City of Tustin shall monitor all new roadway improvements
development within the Soecific Plan, accounting for the identified in MMP Table
Attachment 2 of Exhibit A of Resolution No. 3943
13
Mitigation Monitoring and Reporting Program
)
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
cumulative ADT generated by development projects. As 5; per project final traffic
each ADT threshold is reached, the roadway study, project does not
improvements listed in Table 4.12-10 of the Final exceed ADT threshold
EIS/EIR (see Table 5 at the end of the Mitigation level requiring roadway
Monitoring and Reporting Program) shall be constructed improvements shown in
before any additional projects within the Specific Plan Table 5.
would be approved.
IA-2 Table 7-3 of the Final EIS/EIR (see Table 6 at the end of See Table 7-3 of the Final City of Tustin Tustin Community
the Mitigation Monitoring and Reporting Program) EIS/EIR or Table 6 at the end of Development and Public
presents the Trip Budget which summarizes the square the Mitigation Monitoring and Not applicable to this Works Departments
footage of non-residential uses allocated to each Reporting Program for each
neighborhood by Planning Area and the Associated ADT. specific triggering mechanism. project; staff is
(Residential uses are shown for infonnation only; they are monitoring ADT levels
associated with non-
not part of the budget). Pursuant to Section 3.2.4 of the residential development.
Specific Plan, the City of Tustin shall implement the trip
budget by neighborhood to control the amount and
intensity of non-residential uses. Trip Budget transfers
between neighborhoods shall also be implemented as
directed in subsection 3.2.4 of the Specific Plan.
IA-3 Prior to the approval of (1) a Planning Area Concept Plan Prior to the approval of (1) a Project developer Tustin Community
pursuant to Section 4.2 of the Specific Plan, (2) a site Planning Area Concept Plan Development and Public
development pennit, or (3) a vesting tentative map for pursuant to Section 4.2 of the Works Departments
new square footage (not for fmancing or conveyance Specific Plan, (2) a site
purposes), a project developer shall provide traffic development pennit, or (3) a Not applicable to this
infonnation consistent with the provisions of the Specific vesting tentative map for new project; staff is
Plan, this EIS/EIR and the requirements of the City of square footage (not for fmancing monitoring ADT levels
Tustin Traffic Engineer. The traffic infonnation shall (a) or conveyance purposes). associated with non-
identify and assign traffic circulation mitigation measures residential development.
required in the EIS/EIR pursuant to the Phasing Plan
described in Table 4.12-10 of the Final EIS/EIR (see
Table 5 at the end of the Mitigation Monitoring and
Reporting Program); (b) evaluate the effects of either the
delay of any previously committed circulation
improvements or the construction of currently
unanticipated circulation improvements; and (c) utilize the
circulation system and capacity assumDtions within the
Attachment 2 of Exhibit A of Resolution No. 3943
14
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
EISÆIR and any additional circulation improvements
completed by affected jurisdictions for the applicable
timeframe of analysis.
IA-4 Prior to the issuance of building penn-its for new Prior to the issuance of building Project developer Tustin Community
development within planning areas requiring a concept pennits. Development and Public
plan, a project developer shall enter into an agreement Not applicable Works Departments
with the City of Tustin to (a) design and construct
roadway improvements consistent with the ADT
generation Phasing Plan described in Table 4.12-10 of the
Final EISÆIR (see Table 5 at the end of the Mitigation
Monitoring and Reporting Program) and (b) address the
impact of and specify the responsibility for any previously
committed circulation improvements assumed in the
EISÆIR which have not been constructed.
IA-5 Tustin Community
If a subsequent traffic Phasing Plan demonstrates that Prior to the issuance of building Project developer Development and Public
certain circulation improvements should be included in a pennits. Works Departments
different phase of Specific Plan development (accelerated Not applicable to this
or delayed) or that a circulation improvement can be
substituted, the mitigation Phasing Plan in Table 4.12-10 project.
of the Final EISÆIR (see Table 5 at the end of the
Mitigation Monitoring and Reporting Program) may be
amended, subject to approval ofthe City of Tustin and
any other affected jurisdictions, provided that the same
level of traffic mitigation and traffic capacity would be
provided.
IA-6 The City of Tustin will enter into agreements with Within one (1) year of approval City of Tustin Tustin Public Works and
Caltrans and the cities of Santa Ana and Irvine to ensure of reuse and disposal ofMCAS Community Development
that the off-site roadway improvements needed to mitigate Tustin Completed as part of Departments
the effects of the Specific Plan are constructed pursuant to
improvement programs established by the respective FEIS/EIR approval.
jurisdiction.
IA-7 Each Specific Plan project would contain, to the Prior to issuance of grading Project developer Community Development
satisfaction of the City of Tustin and/or City of Irvine, as pennits Department (Tustin and/or
applicable, a pedestrian circulation component showing Irvine, as applicable)
Attachment 2 of Exhibit A of Resolution No. 3943
15
Mitigation Monitoring and Reporting Program
I
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
pedestrian access to regional hiking trails, parks, schools, Condition 8.5 Resolution
shopping areas, bus stops, and/or other public facilities. 3947 and Condition 12.2
of Resolution No. 3946
Mitigation Measures for Air Quality
AQ-I If determined feasible and appropriate on a Prior to issuance of grading or Project developer Community Development
project-by-project basis, the City of Tustin and the City of building permits. Department (Tustin and/or
Irvine, as applicable, shall require individual development Condition 3.15 of Irvine, as applicable)
projects to implement one or more of the following Resolution 3947
control measures, if not already required by the
SCAQMD under Rule 403:
- Apply water twice daily, or chemical soil
stabilizers according to manufacturers'
specifications, to all unpaved parking or staging
areas or unpaved road surfaces at all actively
disturbed sites.
- Develop a construction traffic management plan
that includes, but is not limited to, rerouting
construction trucks off congested streets,
consolidating truck deliveries, and providing
dedicated turn lanes for movement of
construction trucks and equipment onsite and
offsite.
- Use electricity from power poles rather than
temporary diesel or gasoline powered
generators.
- Reduce traffic speeds on all unpaved roads to 15
mph or less.
- Pave construction roads that have a traffic
volume of more than 50 daily trips by
construction equipment or ISO total daily trips
for all vehicles.
Attachment 2 of Exhibit A of Resolution No. 3943
16
Mitigation Monitoring and Reporting Program
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
- Apply approved chemical soil stabilizers
according to manufacturers' specifications to all
inactive construction areas (previously graded
areas inactive for four days or more).
- Replace ground cover in disturbed areas as
quickly as possible.
- Enclose, cover, water twice daily, or apply
approved soil binders according to
manufacturers' specifications, to exposed piles of
gravel, sand, or dirt.
- Cover all trucks hauling dirt, sand, soil, or other
loose materials, and maintain at least two feet of
ueeboard (Le., minimum vertical distance
between top of the load and top of the trailer).
- Sweep streets at the end of the day if visible soil
material is carried over to adjacent roads (use
water sweepers with reclaimed water when
feasible).
- Install wheel washers where vehicles enter and
exit unpaved roads onto paved roads, or wash off
trucks and any equipment leaving the site each
trip.
-
AQ-2 Unless determined by the City of Tustin and the City of Prior to issuance of grading or Project developer Community Development
Irvine, as applicable, to be infeasible on a building permits. Department (Tustin and/or
project-by-project basis due to unique project Irvine, as applicable)
characteristics, each city shall require individual Condition 3.15 of
development projects to use low VOC architectural
coatings for all interior and exterior painting operations. Resolution 3947
Mitigation Measures for Noise
N-I Prior to reuse of any existing residential units within the Prior to reuse of any existing Project developer Community Development
17
Mitigation Monitoring and Reporting Program
Attachment 2 of Exhibit A of Resolution No. 3943
Measure* Timing and Implementation Mitigation Compliance Mitigation Monitoring and
Responsibility Enforcement Responsibility
reuse area for civilian use, the City of Tustin or the City residential units. Department (Tustin and/or
ofIrvine, as applicable, and where necessary and feasible, ! Irvine, as applicable)
Conditions 12.1-12.3
shall require the installation of noise attenuation barriers, of Resolution 3947
insulation, or similar devices to ensure that interior and
exterior noise levels at these residential units do not
exceed applicable noise standards.
N-3 For new development within the reuse area, the City of Prior to issuance of building Project developer Community Development
Tustin and City oflrvine, as applicable, shall ensure that permits. Department (Tustin and/or
interior and exterior noise levels do not exceed those Condition 12.1-12.3 of Irvine, as applicable)
prescribed by state requirements and local city ordinances Resolution 3947
and general plans. Plans demonstrating noise regulation
confonnity shall be submitted for review and approval
prior to building permits being issued to accommodate
reuse.
*Measures LV-I, LV-2 have been completed; Hist 1,2,3,4,5, Bio 1,2,3,4, and N-2, N-4 do not apply to the project site; AQ-3, AQ-4 do not apply to residential projects, TC-7, TC-8 have been
created through the adoption of the FEISÆIR and staff is monitoring, TC-9 has been completed.
Attachment 2 of Exhibit A of Resolution No. 3943
18
Mitigation Monitoring and Reporting Program