HomeMy WebLinkAbout02 ZC 05-001 (MCAS Tustin SPA)
ITEM #2
Report to the
Planning Commission
DATE:
APRIL 25, 2005
ZONE CHANGE (MCAS TUSTIN SPECIFIC PLAN AMENDMENT)
05-001
SUBJECT:
APPLICANT:
CITY OF TUSTIN
LOCATION:
MCAS TUSTIN SPECIFIC PLAN AREA
ZONING:
MCAS TUSTIN SPECIFIC PLAN
GENERAL PLAN
DESIGNATION: MCAS TUSTIN SPECIFIC PLAN
ENVIRONMENTAL
STATUS: THE FINAL ENVIRONMENTAL IMPACT STATEMENTI
ENVIRONMENTAL IMPACT REPORT (FEIS/EIR) CERTIFIED ON
JANUARY 16, 2001, IN CONJUNCTION WITH THE MCAS TUSTIN
SPECIFIC PLAN/REUSE PLAN, ADEQUATELY ADDRESSES
ENVIRONMENTAL CONSIDERATIONS ASSOCIATED WITH THE
PROPOSED PROJECT. ADDITIONAL ENVIRONMENTAL
DOCUMENTATION WILL NOT BE PREPARED.
REQUEST:
ZONE CHANGE TO AMEND THE FOLLOWING SECTIONS OF
THE MCAS TUSTIN SPECIFIC PLAN:
a. SECTION 3.2.2, FOOTNOTES TO TABLES 3-1 AND 3-2
AND CHAPTER 6 (DEFINITIONS) RELATING TO
CALCULATION OF DENSITY;
b. SECTION 3.9.2.J AND CHAPTER 6 (DEFINITIONS) TO
ESTABLISH REVISED DEVELOPMENT UNIT CRITERIA
FOR PLANNING AREA 15; AND
c. SECTION 3.2.3 RELATING
RESIDENTIAL UNITS
TO
TRANSFER
OF
RECOMMENDATION
That the Planning Commission:
1. Adopt Resolution No. 3969 recommending that the City Council find that Zone
Change (MCAS Tustin Specific Plan Amendment) 05-001 is within the scope of the
adopted Final EIS/EIR for the MCAS Tustin Specific Plan/Reuse Plan.
Planning Commission Report
Zone Change 05-001
April 25, 2005
Page 2
2. Adopt Resolution No. 3970 recommending that the City Council approve Zone Change
(MCAS Tustin Specific Plan Amendment) 05-001 for MCAS Tustin.
BACKGROUND AND DISCUSSION
Marine Corps Air Station (MCAS) Tustin was closed on July 2, 1999. On January 16,
2001, the Tustin City Council approved General Plan Amendment (GPA) 00-001 which
adopted amendments to various Elements of the General Plan and established a new
"MCAS Tustin Specific Plan" General Plan designation for the former base property
within the City of Tustin. A joint program Environmental Impact StatemenV
Environmental Impact Report (EIS/EIR) was certified by the Tustin City Council at that
time. In February 2003, the MCAS Tustin Specific Plan (the "Plan") was adopted,
serving as the zoning for the site.
City-initiated Zone Change (MCAS Tustin Specific Plan Amendment) 05-001 is proposed
to facilitate the application and implementation of some of the requirements contained in
the Plan. The proposed amendments to the MCAS Tustin Specific Plan, attached hereto
as Exhibit A of Resolution No. 3970, include the following minor clarifications and
modifications:
1. Density Calculation. Specific Plan Section 3.2.2; footnotes to Tables 3-1 and 3-2;
and the Definitions section (Chapter 6) of the Specific Plan currently define the
calculation of dwelling units per acre (density) within the Specific Plan. The present
definition is based upon net acreage rather than an adjusted gross acreage. Using
net acreage and the densities allowed by the Specific Plan, it is not possible to
achieve the residential yields assumed in the Specific Plan. The proposed text
amendment to the definition of density would allow the density calculation to be
based on a gross acreage basis, allowing for inclusion of local roads while retaining
the dwelling unit thresholds envisioned in the plan and analyzed in the project
EIR/EIS.
2. Development Unit. Specific Plan Section 3.9.2 currently requires that
condominiums, multiple family developments and patio homes be mapped in
development units at a minimum ten (10) acre size. The Definitions section
(Chapter 6) defines the term "development unit" The 10-acre minimum results in
large neighborhoods of the same product type and inhibits the blending of product
types within a neighborhood. The proposed amendment would reduce the
minimum size of a development unit to five (5) acres and would further require
comprehensive site planning for development units with multiple products. In
addition, the Definitions section (Chapter 6) would be revised to state that a
development unit may contain multiple products, at an average density not to
exceed the maximum densities for each applicable land use designation (Le. low
density, medium density, and medium high density). The proposed amendment
responds to current industry standards and precedents set in other master planned
communities in the region such as Ladera Ranch and Irvine Ranch. The minimum
5-acre size allows for adequate maintenance by the Homeowners Association, and
Planning Commission Report
Zone Change 05-001
April 25, 2005
Page 3
allows for the flexibility of developing multiple residential products while reducing
the likelihood that a mass development of a single product type would occur.
3. Transfer of Residential Units. Specific Plan Section 3.2.3 currently defines the
provisions for the transfer of residential units between planning areas in cases
where a planning area is developed with less than the maximum units allowed,
limiting such transfers to a maximum of 10 percent of the maximum dwelling units
prescribed in the receiving planning area, without a Specific Plan Amendment.
Recent development within the MCAS Tustin Specific Plan area has resulted in
undeveloped units. Additional flexibility in the transfer of these units will allow the
City to realize the Land Use Plan envisioned in the Specific Plan. The proposed
amendment to Section 3.2.3 would allow the transfer of units to exceed 10 percent
without a Specific Plan Amendment, subject to a written finding by the Director of
Community Development, under certain criteria, including the following:
a. Such transfers shall not increase the total units allowable in the overall
Specific Plan;
b. Unit transfers must remain within the original school district boundaries;
c. Transfers shall be consistent with the uses and development standards of
the receiving area;
d. Units shall be transferred at the same density category as originally planned;
e. Transfers shall not exceed environmental thresholds established in the
project EIR/EIS.
The proposed criteria would ensure that any transfer of residential units be
compatible with the planning area to which they are transferred and would
minimize the potential for environmental impacts resulting from the development
of the transferred units.
ENVIRONMENTAL
On January 16, 2001, the City Council certified the Final Environmental Impact
StatemenVEnvironmentallmpact Report for the MCAS Tustin Reuse Plan and Specific
Plan (FEIS/EIR). The proposed amendments to the MCAS Tustin Specific Plan are
consistent with the development intensity previously considered in the certified
FEIS/EIR.
As the FEIS/EIR is a Program EIR under CEQA, if the City does an analysis of the
proposed Specific Plan Amendments under Title 14 Cal. Code of Regs. Section 15162
and finds that no new effects could occur or no new mitigation measures would be
required, the City can approve the Amendments as being within the scope of the project
covered by the program EIR, and no new environmental document would be required.
[Title 14 Cal. Code of Regs. Section 15168].
Staff has prepared an Environmental Analysis checklist that demonstrates all potential
impacts of the project were addressed by the certified FEIS/EIR and no additional
impacts have been identified (Attachment 1 to Exhibit A of Resolution No. 3969).
Planning Commission Report
Zone Change 05-001
April 25, 2005
Page 4
In addition, all applicable mitigation measures required in the FEIS/EIR will be
recommended as conditions of approval in the entitlements for future development
within the MCAS Tustin Specific Plan area.
A decision to approve Zone Change (MCAS Tustin Specific Plan Amendment) 05-001
may be supported by the findings contained in Resolution Nos. 3969 and 3970.
2~~1
Elizabeth A. Binsack
Community Development Director
J~~
Scott Reekstin
Senior Planner
Attachments:
A. Resolution No. 3969 - (Environmental Findings)
B. Resolution No. 3970 - (Zone Change-Specific Plan Amendment)
S:\Cdd\PCREPORT\ZC OS-OO1 (Global MCAS Amendments 2005).doc
ATTACHMENT A
RESOLUTION NO. 3969
(ENVIRONMENTAL FINDINGS)
RESOLUTION NO. 3969
A RESOLUTION OF THE CITY OF TUSTIN PLANNING COMMISSION
RECOMMENDING THAT THE CITY COUNCIL ADOPT FINDINGS THAT
THE FINAL ENVIRONMENTAL IMPACT STATEMENTI
ENVIRONMENTAL IMPACT REPORT FOR THE DISPOSAL AND
REUSE OF MCAS, TUSTIN ("FEIS/EIR") IS ADEQUATE TO SERVE AS
THE PROJECT EIS/EIR FOR ZONE CHANGE (MCAS TUSTIN
SPECIFIC PLAN AMENDMENT) 05-001.
I.
The Planning Commission of the City of Tustin does hereby resolve as follows:
A. That Zone Change (MCAS Tustin Specific Plan Amendment) 05-001 is
considered a "project" pursuant to the terms of the California
Environmental Quality Act.
B. That the FEIS/EIR was certified by the City Council on January 16, 2001.
The FEIS/EIR is a Program EIR under the California Environmental
Quality Act ("CEQA"). The FEIS/EIR considered the potential
environmental impacts associated with the development on the former
Marine Corps Air Station, Tustin.
C. That an Environmental Analysis Checklist, attached as Exhibit A hereto,
was prepared to evaluate the potential environmental impacts associated
with the Project. The Environmental Analysis Checklist demonstrates that
all potential impacts of the Project were addressed by the certified
FEIS/EIR, no additional impacts have been identified, no new mitigation
measures would be required, and that the City can approve the Specific
Plan Amendments as being within the scope of the FEIS/EIR.
II.
The Planning Commission hereby recommends that the City Council find that this
Project is within the scope of the previously approved Program FEIS/EIR and
that pursuant to Title 14 California Code of Regulations Sections 15162 and
15168(c), no new effects could occur, and no new mitigation measures would be
required. Accordingly, no new environmental document is required by CEQA.
Resolution No. 3969
Page 2
PASSED AND ADOPTED by the Planning Commission of the City of Tustin, at a
regular meeting on the 25th day of April, 2005.
JOHN NIELSEN
Chairperson
ELIZABETH A. BINSACK
Planning Commission Secretary
STATE OF CALIFORNIA)
COUNTY OF ORANGE)
CITY OF TUSTIN )
I, ELIZABETH A. BINSACK, the undersigned, hereby certify that I am the Planning
Commission Secretary of the Planning Commission of the City of Tustin, California; that
Resolution No. 3969 duly passed and adopted at a regular meeting of the Tustin
Planning Commission, held on the 25th day of April, 2005.
ELIZABETH A. BINSACK
Planning Commission Secretary
EXHIBIT A OF RESOLUTION NO. 3969
COMMUNITY DEVELOPMENT DEPARTMENT
300 Centennial Way, Tustin, CA 92780
(714) 573-3100
ENVIRONMENTAL ANALYSIS CHECKLIST
For Projects With Previously Certified/Approved Environmental Documents:
Environmental Impact Statement/Environmental Impact Report (EIS/EIR)
for the Disposal and Reuse of Marine Corps Air Station (MCAS) Tustin
This checklist and the following evaluation of environmental impacts (Attachment 1) takes into consideration
the preparation of an environmental document prepared at an earlier stage of the proposed project. The
checklist and evaluation evaluate the adequacy of the earlier document pursuant to Section 15162 and 15168 of
the California Environmental Quality Act (CEQA) Guidelines.
A.
BACKGROUND
Project Title(s):
Zone Change (MCAS Tustin Specific Plan Amendment) 05-001
Lead Agency:
City of Tustin, 300 Centennial Way, Tustin, California 92780
Lead Agency Contact Person:
Scott Reekstin
Phone: (714) 573-3016
Project Location:
MCAS Tustin Specific Plan, generally bounded by Edinger Avenue to the north,
Harvard Avenue to the east, Red Hill Avenue to the west, and Barranca Parkway
to the south.
Project Sponsor's Name and Address:
City of Tustin
300 Centennial Way
Tustin, California 92780
General Plan Designation:
MCAS Tustin Specific Plan
Zoning Designation:
MCAS Tustin Specific Plan District
Project Description: Approval of Zone Change (MCAS Tustin Specific Plan Amendment) 05-001 to
make minor administrative amendments that would modify the definition of density, revise the minimum
size of a development unit, and allow more flexibility in transferring residential units between planning
areas.
Surrounding Uses:
North: Residential, Light Industrial, and Commercial
East: Residential
South: Light Industrial and Commercial
West: Light Industrial and Commercial
Previous Environmental Documentation: Program Final Environmental Impact
Statement/Environmental Impact Report (Program FEIS/EIR) for the Disposal and Reuse of Marine
Corps Air Station (MCAS) Tustin (State Clearinghouse #94071005) certified by the Tustin City Council
on January 16,2001.
B.
ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED
The environmental factors checked below would be potentially affected by this project, involving at least one
impact that is a "Potentially Significant Impact" as indicated by the checklist in Section D below.
OLand Use and Planning
OPopulation and Housing
OGeology and Soils
OHydrology and Water Quality
OAir Quality
DTransportation & Circulation
DBiological Resources
OMineral Resources
DAgricultural Resources
DHazards and Hazardous Materials
DNoise
OPublic Services
DUtilities and Service Systems
OAesthetics
DCultural Resources
DRecreation
OMandatory Findings of
Significance
C. DETERMINATION:
On the basis of this initial evaluation:
D I find that the proposed project COULD NOT have a significant effect on the environment, and a
NEGATIVE DECLARATION will be prepared.
0 I find that although the proposed project could have a significant effect on the environment, there will
not be a significant effect in this case because the mitigation measures described on an attached sheet
have been added to the project. A NEGATIVE DECLARATION will be prepared.
D I find that the proposed project MAY have a significant effect on the environment, and an
ENVIRONMENTAL IMPACT REPORT is required.
0 I find that the proposed project MAY have a significant effect(s) on the environment, but at least one
effect 1) has been adequately analyzed in an earlier document pursuant to applicable legal standards, and
2) has been addressed by mitigation measures based on the earlier analysis as described on attached
sheets, ifthe effect is a "Potentially Significant Impact" or "Potentially Significant Unless Mitigated."
An ENVIRONMENTAL IMPACT REPORT is required, but it must analyze only the effects that
remain to be addressed.
~ I find that although the proposed project could have a significant effect on the environment, there WILL
NOT be a significant effect in this case because all potentially significant effects 1) have been analyzed
adequately in an earlier EIR pursuant to applicable standards, and 2) have been avoided or mitigated
pursuant to that earlier EIR, including revisions or mitigation measures that are imposed upon the
proposed project.
0 I find that although the proposed project could have a significant effect on the environment, there WILL
NOT be a significant effect in this case because all potentially significant effects 1) have been analyzed
0 I find that although the proposed project could have a significant effect on the environment, there WILL
NOT be a significant effect in this case because all potentially significant effects I) have been analyzed
adequately in an earlier NEGATIVE DECLARATION pursuant to applicable standards, and 2) have
been avoided or mitigated pursuant to that earlier NEGATIVE DECLARATION, including revisions or
mitigation measures that are imposed upon the proposed project.
Preparer: J t¿J;C ~
Scott Reekstin, Senior Planner
ÇJ:~d.J{~"¡
Elizabeth A. Binsack, Community Development Director
Date: if-itf-tlS
Date ~- /'1'- ¿j S-
D. EVALUATION OF ENVIRONMENTAL IMPACTS
See Attached
EV ALVA TION OF ENVIRONMENTAL IMPACTS
No Substantial
New More Change From
Significant Severe Previous
I. AESTHETICS - Would the project: Impact Impacts Analysis
a) Have a substantial adverse effect on a scenic vista? D D ~
b) Substantially damage scenic resources, including, but not
limited to, trees, rock outcroppings, and historic buildings
within a state scenic highway? D D ~
c) Substantially degrade the existing visual character or
quality of the site and its surroundings? D D ~
d) Create a new source of substantial light or glare which
would adversely affect day or nighttime views in the area? D D ~
II. AGRICULTURE RESOURCES: In determining
whether impacts to agricultural resources are significant
environmental effects, lead agencies may refer to the
California Agricultural Land Evaluation and Site Assessment
Model (1997) prepared by the California Dept. of
Conservation as an optional model to use in assessing impacts
on agriculture and farmland. Would the project:
a) Convert Prime Farmland, Unique Farmland, or Farmland
of Statewide Importance (Farmland), as shown on the maps
prepared pursuant to the Farmland Mapping and Monitoring
Program of the California Resources Agency, to non-
agricultural use? D D ~
b) Conflict with existing zoning for agricultural use, or a
Williamson Act contract? D D ~
c) Involve other changes in the existing environment which,
due to their location or nature, could result in conversion of
Farmland, to non-agricultural use? D D ~
III. AIR OUALITY: Where available, the significance
criteria established by the applicable air quality management
or air pollution control district may be relied upon to make the
following determinations. Would the project:
a) Conflict with or obstruct implementation of the applicable
air quality plan? D D ~
b) Violate any air quality standard or contribute substantially
to an existing or projected air quality violation? D D ~
c) Result in a cumulatively considerable net increase of any
criteria pollutant for which the project region is non-
attainment under an applicable federal or state ambient air
quality standard (including releasing emissions which exceed
quantitative thresholds for ozone precursors)? D D ~
d) Expose sensitive receptors to substantial pollutant
concentrations? D D ~
e) Create objectionable odors affecting a substantial number
of people? D D ~
IV. BIOLOGICAL RESOURCES: - Would the project:
a) Have a substantial adverse effect, either directly or
through habitat modifications, on any species identified as a
candidate, sensitive, or special status species in local or
regional plans, policies, or regulations, or by the California
Department ofFish and Game or U.S. Fish and Wildlife
Service?
b) Have a substantial adverse effect on any riparian habitat
or other sensitive natural community identified in local or
regional plans, policies, regulations or by the California
Department ofFish and Game or U.S. Fish and Wildlife
Service?
c) Have a substantial adverse effect on federally protected
wetlands as defined by Section 404 of the Clean Water Act
(including, but not limited to, marsh, vernal pool, coastal, etc.)
through direct removal, filling, hydrological interruption, or
other means?
d) Interfere substantially with the movement of any native
resident or migratory fish or wildlife species or with
established native resident or migratory wildlife corridors, or
impede the use of native wildlife nursery sites?
e) Conflict with any local policies or ordinances protecting
biological resources, such as a tree preservation policy or
ordinance?
f) Conflict with the provisions of an adopted Habitat
Conservation Plan, Natural Community Conservation Plan, or
other approved local, regional, or state habitat conservation
plan?
V. CULTURAL RESOURCES: - Would the project:
a) Cause a substantial adverse change in the significance of
a historical resource as defined in § 15064.5?
b) Cause a substantial adverse change in the significance of
an archaeological resource pursuant to § 15064.5?
c) Directly or indirectly destroy a unique paleontological
resource or site or unique geologic feature?
d) Disturb any human remains, including those interred
outside of formal cemeteries?
VI. GEOLOGY AND SOILS: - Would the project:
a) Expose people or structures to potential substantial
adverse effects, including the risk ofloss, injury, or death
involving:
New
Significant
Impact
More
Severe
Impacts
No Substantial
Change From
Previous
Analysis
0
0
~
0
0
~
D
D
~
D
D
~
D
D
~
0
0
~
D D ~
D D ~
D D ~
D 0 ~
No Substantial
New More Change From
Significant Severe Previous
Impact Impacts Analysis
i) Rupture of a known earthquake fault, as delineated on the
most recent Alquist-Priolo Earthquake Fault Zoning Map
issued by the State Geologist for the area or based on other
substantial evidence of a known fault? Refer to Division of
Mines and Geology Special Publication 42. 0 0 C8J
ii) Strong seismic ground shaking? D D ~
iii) Seismic-related ground failure, including liquefaction? D D ~
iv) Landslides? D D ~
b) Result in substantial soil erosion or the loss of topsoil? D D ~
c) Be located on a geologic unit or soil that is unstable, or
that would become unstable as a result of the project, and
potentially result in on- or off-site landslide, lateral spreading,
subsidence, liquefaction or collapse? D D ~
d) Be located on expansive soil, as defined in Table 18-1-B
of the Uniform Building Code (1994), creating substantial
risks to life or property? D D ~
e) Have soils incapable of adequately supporting the use of
septic tanks or alternative wastewater disposal systems where
sewers are not available for the disposal of waste water? D D ~
VII. HAZARDS AND HAZARDOUS MATERIALS:
Would the project:
a) Create a significant hazard to the public or the
environment through the routine transport, use, or disposal of
hazardous materials? D D ~
b) Create a significant hazard to the public or the
environment through reasonably foreseeable upset and
accident conditions involving the release of hazardous
materials into the environment? D D ~
c) Emit hazardous emissions or handle hazardous or acutely
hazardous materials, substances, or waste within one-quarter
mile of an existing or proposed school? D D ~
d) Be located on a site which is included on a list of
hazardous materials sites compiled pursuant to Government
Code Section 65962.5 and, as a result, would it create a
significant hazard to the public or the environment? D D ~
e) For a project located within an airport land use plan or,
where such a plan has not been adopted, within two miles of a
public airport or public use airport, would the project result in
a safety hazard for people residing or working in the project
area? D D ~
f) For a project within the vicinity of a private airstrip,
would the project result in a safety hazard for people residing
or working in the project area? D D ~
No Substantial
New More Change From
Significant Severe Previous
g) Impair implementation of or physically interfere with an Impact Impacts Analysis
adopted emergency response plan or emergency evacuation
plan? D D [g
h) Expose people or structures to a significant risk of loss,
injury or death involving wildland fires, including where
wildlands are adjacent to urbanized areas or where residences
are intermixed with wildlands? D D [g
VIII. HYDROLOGY AND WATER OUALITY: - Would
the project:
a) Violate any water quality standards or waste discharge
requirements? D D [g
b) Substantially deplete groundwater supplies or interfere
substantially with groundwater recharge such that there would
be a net deficit in aquifer volume or a lowering of the local
groundwater table level (e.g., the production rate of pre-
existing nearby wells would drop to a level which would not
support existing land uses or planned uses for which permits
have been granted)? D 0 ~
c) Substantially alter the existing drainage pattern of the site
or area, including through the alteration of the course of a
stream or river, in a manner which would result in substantial
erosion or siltation on- or off-site? D 0 ~
d) Substantially alter the existing drainage pattern of the site
or area, including through the alteration of the course of a
stream or river, or substantially increase the rate or amount of
surface runoff in a manner which would result in flooding on-
or off-site? 0 0 ~
e) Create or contribute runoff water which would exceed the
capacity of existing or planned stormwater drainage systems
or provide substantial additional sources of polluted runoff? D 0 [g
f) Otherwise substantially degrade water quality? D D [g
g) Place housing within a lOa-year flood hazard area as
mapped on a federal Flood Hazard Boundary or Flood
Insurance Rate Map or other flood hazard delineation map? 0 0 ~
h) Place within a lOa-year flood hazard area structures
which would impede or redirect flood flows? 0 0 ~
i) Expose people or structures to a significant risk of loss,
injury or death involving flooding as a result of the failure of a
levee or dam? 0 0 ~
j) Inundation by seiche, tsunami, or mudflow? 0 0 ~
IX. LAND USE AND PLANNING - Would the project:
a) Physically divide an established community? 0 0 ~
No Substantial
New More Change From
Significant Severe Previous
b) Conflict with any applicable land use plan, policy, or Impact Impacts Analysis
regulation of an agency with jurisdiction over the project
(including, but not limited to the general plan, specific plan,
local coastal program, or zoning ordinance) adopted for the
purpose of avoiding or mitigating an environmental effect? 0 0 ~
c) Conflict with any applicable habitat conservation plan or
natural community conservation plan? 0 0 ~
X. MINERAL RESOURCES - Would the project:
a) Result in the loss of availability of a known mineral
resource that would be of value to the region and the residents
of the state? 0 0 ~
b) Result in the loss of availability of a locally-important
mineral resource recovery site delineated on a local general
plan, specific plan or other land use plan? 0 0 ~
XI. NOISE -
Would the project result in:
a) Exposure of persons to or generation of noise levels in
excess of standards established in the local general plan or
noise ordinance, or applicable standards of other agencies? 0 0 ~
b) Exposure of persons to or generation of excessive
groundbome vibration or groundbome noise levels? 0 0 ~
c) A substantial permanent increase in ambient noise levels
in the project vicinity above levels existing without the
project? 0 0 ~
d) A substantial temporary or periodic increase in ambient
noise levels in the project vicinity above levels existing
without the project? 0 0 ~
e) For a project located within an airport land use plan or,
where such a plan has not been adopted, within two miles of a
public airport or public use airport, would the project expose
people residing or working in the project area to excessive
noise levels? 0 0 ~
f) For a project within the vicinity of a private airstrip,
would the project expose people residing or working in the
project area to excess noise levels? 0 0 ~
XII. POPULATION AND HOUSING - Would the project:
a) Induce substantial population growth in an area, either
directly (for example, by proposing new homes and
businesses) or indirectly (for example, through extension of
roads or other infrastructure)? 0 D ~
b) Displace substantial numbers of existing housing,
necessitating the construction of replacement housing
elsewhere? D D ~
No Substantial
New More Change From
Significant Severe Previous
Impact Impacts Analysis
c) Displace substantial numbers of people, necessitating the
construction of replacement housing elsewhere? 0 0 [gJ
XIII. PUBLIC SERVICES
a) Would the project result in substantial adverse physical
impacts associated with the provision of new or physically
altered governmental facilities, need for new or physically
altered governmental facilities, the construction of which
could cause significant environmental impacts, in order to
maintain acceptable service ratios, response times or other
perfonnance objectives for any of the public services:
Fire protection? 0 0 [gJ
Police protection? 0 0 [gJ
Schools? 0 0 [gJ
Parks? 0 0 [gJ
Other public facilities? 0 D [gJ
XIV. RECREATION -
a) Would the project increase the use of existing
neighborhood and regional parks or other recreational
facilities such that substantial physical deterioration of the
facility would occur or be accelerated? D D [gJ
b) Does the project include recreational facilities or require
the construction or expansion of recreational facilities which
might have an adverse physical effect on the environment? 0 0 [gJ
XV. TRANSPORTATION/TRAFFIC - Would the project:
a) Cause an increase in traffic which is substantial in relation
to the existing traffic load and capacity of the street system
(i.e. result in a substantial increase in either the number of
vehicle trips, the volume to capacity ratio on roads, or
congestion at intersections)? 0 0 [gJ
b) Exceed, either individually or cumulatively, a level of
service standard established by the county congestion
management agency for designated roads or highways? D D ~
c) Result in a change in air traffic patterns, including either
an increase in traffic levels or a change in location that results
in substantial safety risks? 0 0 [gJ
d) Substantially increase hazards due to a design feature (e.g.
sharp curves or dangerous intersections) or incompatible uses
(e.g., farm equipment)? D D [gJ
e) Result in inadequate emergency access? D D [gJ
t) Result in inadequate parking capacity? D D [gJ
No Substantial
New More Change From
Significant Severe Previous
Impact Impacts Analysis
g) Conflict with adopted policies, plans, or programs
supporting alternative transportation (e.g., bus turnouts,
bicycle racks)? 0 0 ~
XVI. UTILITIES AND SERVICE SYSTEMS -
Would the project:
a) Exceed wastewater treatment requirements of the
applicable Regional Water Quality Control Board? 0 0 ~
b) Require or result in the construction of new water or
wastewater treatment facilities or expansion of existing
facilities, the construction of which could cause significant
environmental effects? D D [8J
c) Require or result in the construction of new storm water
drainage facilities or expansion of existing facilities, the
construction of which could cause significant environmental
effects? D D [8J
d) Have sufficient water supplies available to serve the
project trom existing entitlements and resources, or are new or
expanded entitlements needed? D D [8J
e) Result in a determination by the wastewater treatment
provider which serves or may serve the project that it has
adequate capacity to serve the project's projected demand in
addition to the provider's existing commitments? D D [8J
t) Be served by a landfill with sufficient permitted capacity
to accommodate the project's solid waste disposal needs? D 0 [8J
g) Comply with federal, state, and local statutes and
regulations related to solid waste? D D [8J
XVII. MANDATORY FINDINGS OF SIGNIFICANCE
a) Does the project have the potential to degrade the quality
of the environment, substantially reduce the habitat of a fish or
wildlife species, cause a fish or wildlife population to drop
below self-sustaining levels, threaten to eliminate a plant or
animal community, reduce the number or restrict the range of
a rare or endangered plant or animal or eliminate important
examples of the major periods of California history or
prehistory? 0 D ~
b) Does the project have impacts that are individually
limited, but cumulatively considerable? ("Cumulatively
considerable" means that the incremental effects of a project
are considerable when viewed in connection with the effects
of past projects, the effects of other current projects, and the
effects of probable future projects)? D D [8J
c) Does the project have environmental effects which will
cause substantial adverse effects on human beings, either
directly or indirectly? D D [8J
ATTACHMENT 1
EVALUATION OF ENVIRONMENTAL IMPACTS AS COMPARED TO FEIS/EIR
ZONE CHANGE (MCAS TUSTIN SPECIFIC PLAN AMENDMENT) 05-001
BACKGROUND
The former Marine Corps Air Station (MCAS) Tustin was officially closed on July 2, 1999,
as a result of recommendations of the Federal Base Closure and Realignment
Commission. The City was designated as the Local Redevelopment Authority (LRA) for
the reuse of MCAS Tustin and, acting as such, approved a Reuse Plan that provided for
future land uses at the former MCAS Tustin. The Reuse Plan was approved in October
1996 and was subsequently amended in September 1998 ("the Reuse Plan").
In accordance with the provisions of the National Environmental Policy Act ("NEPA") of
1969, as amended, and the California Environmental Quality Act ("CEQA"), the federal
government and City prepared a Joint Final Program Environmental Impact
Statement/Environmental Impact Report for the Reuse and Disposal of MCAS Tustin.
This was a Program EIR under CEQA. On January 16, 2001, the City of Tustin certified
the Final Joint Program Environmental Impact Statement/Environmental Impact Report
for the disposal and reuse of MCAS-Tustin (referenced as FEIS/EIR herein).
In February 2003, based on the FEIS/EIR, the MCAS Tustin Specific Plan (the "Plan")
for Alternative 1, the LRA Reuse Plan, was adopted for the MCAS Tustin property,
serving as the zoning.
The City is proposing changes to the text of the Plan, and desires to evaluate whether
those changes will trigger the preparation of a new environmental document or whether
the changes are within the scope of the FEIS/EIR.
City-initiated Zone Change (MCAS Tustin Specific Plan Amendment) 05-001 is
proposed to facilitate the application and implementation of some of the requirements
contained in the Plan. The proposed amendments to the MCAS Tustin Specific Plan,
include the following minor clarifications and modifications:
1. Density Calculation. Specific Plan Section 3.2.2; footnotes to Tables 3-1 and 3-
2; and the Definitions section (Chapter 6) of the Specific Plan currently define the
calculation of dwelling units per acre (density) within the Specific Plan. The
present definition is based upon net acreage rather than an adjusted gross
acreage. Using net acreage and the densities allowed by the Specific Plan, it is
not possible to achieve the residential yields assumed in the Specific Plan. The
proposed text amendment to the definition of density would allow the density
calculation to be based on a gross acreage basis, allowing for inclusion of local
roads while retaining the dwelling unit thresholds envisioned in the plan and
analyzed in the project EIR/EIS.
2. Development Unit. Specific Plan Section 3.9.2 currently requires that
condominiums, multiple family developments and patio homes be mapped in
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 2
development units at a minimum ten (10) acre size. The Definitions section
(Chapter 6) defines the term "development unit". The 1 O-acre minimum results in
large neighborhoods of the same product type and inhibits the blending of
product types within a neighborhood. The proposed amendment would reduce
the minimum size of a development unit to five (5) acres, and would further
require comprehensive site planning for development units with multiple
products. In addition, the Definitions section (Chapter 6) would be revised to
state that a development unit may contain multiple products, at an average
density not to exceed the maximum densities for each applicable land use
designation (i.e. low density, medium density and medium high density). The
proposed amendment responds to current industry standards and precedents set
in other master planned communities in the region such as Ladera Ranch and
Irvine Ranch. The minimum 5-acre size allows for adequate maintenance by the
Homeowners Association, and allows for the flexibility of developing multiple
residential products while reducing the likelihood that a mass development of a
single product type would occur.
3. Transfer of Residential Units. Specific Plan Section 3.2.3 currently defines the
provisions for the transfer of residential units between planning areas in cases
where a planning area is developed with less than the maximum units allowed,
limiting such transfers to a maximum of 10 percent of the maximum dwelling
units prescribed in the receiving planning area, without a Specific Plan
Amendment. Recent development within the MCAS Tustin Specific Plan area
has resulted in undeveloped units. Additional flexibility in the transfer of these
units will allow the City to more readily realize the maximum potential of the Land
Use Plan. The proposed amendment to Section 3.2.3 would allow the transfer of
units to exceed 10 percent without a Specific Plan Amendment, subject to a
written finding by the Director of Community Development, under certain criteria,
including the following:
a. Such transfers shall not increase the total units allowable in the overall
Specific Plan;
b. Unit transfers must remain within the original school district boundaries;
c. Transfers shall be consistent with the uses and development standards of
the receiving area;
d. Units shall be transferred at the same density category as originally
planned;
e. Transfers shall not exceed environmental thresholds established in the
project EIR/EIS.
The proposed criteria would ensure that any transfer of residential units be
compatible with the planning area to which they are transferred and would
minimize the potential for environmental impacts resulting from the development
of the transferred units.
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 3
COMPARISON WITH FEIS/EIR AND CONCLUSIONS
As the FEIS/EIR is a Program EIR under CEQA, if the City does an analysis of the
proposed Specific Plan Amendments under Title 14 Cal. Code of Regs. Section 15162
and finds that no new effects could occur or no new mitigation measures would be
required, the City can approve the Amendments as being within the scope of the project
covered by the program EIR, and no new environmental document would be required.
[Title 14 Cal. Code of Regs. Section 15168].
The key issues under Section 15162 are whether:
(a)
Substantial changes are proposed in the project which will require major
revisions of the previous EIR due to the involvement of new significant
environmental effects or a substantial increase in the severity of previously
identified significant effect; or
(b)
Substantial changes occur with respect to the circumstances under which the
project is undertaken which will require major revisions of the previous EIR due
to the involvement of new significant environmental effects or a substantial
increase in the severity of identified significant effect; or
(c)
New information of substantial importance, which was not known and could not
have been known with the exercise of reasonable diligence at the time of the
previous EIR was certified as complete shows any of the following:
(i)
the project will have one or more significant effects not discussed in
the previous EIR; or
(ii)
significant effects previously examined will be substantially more
severe than shown in the previous EIR; or
(iii)
mitigation measures or alternatives previously found not to be feasible
would in fact be feasible and would substantially reduce one or more
significant effects of the project; or
(iv)
mitigation measures or alternatives which are considerably different
from those analyzed in the previous EIR would substantially reduce
one or more significant effects on the environment.
In this case, after analyzing the environmental effects of the proposed project
under Section 15162, the City has concluded that no new effects could occur and
no new mitigation measures would be required and that the City can approve the
Specific Plan Amendments as being within the scope of the FEIS/EIR.
The following information provides background support for the conclusions identified
above and in the Environmental Analysis Checklist, as compared to the analysis in the
FEIS/EIR.
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 4
I.
AESTHETICS - Would the project:
a) Have a substantial adverse effect on a scenic vista?
b) Substantially damage scenic resources, including, but not limited to,
trees, rock outcroppings, and historic buildings within a state scenic
highway?
c) Substantially degrade the existing visual character or quality of the site
and its surroundings?
d) Create a new source of substantial light or glare, which would adversely
affect day or nighttime views in the area?
The proposed Specific Plan Amendments will not directly cause aesthetic impacts
because they are changes to a zoning text, not a development proposal. Similarly,
the project will not have direct effects on a scenic vista, scenic resources, or the
visual character or quality of the Specific Plan area, or create any new sources or
substantial light or glare. The project would not indirectly cause substantial
adverse effects in addition to those identified in the FEIS/EIR because the project
does not permit an increase in the number of residential units or residential floor
area assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR. While the
project allows more flexibility in the location of residential units and the mix of
product types, the urban design features of the Specific Plan (which are not
proposed to change) will ensure that residential development under the Specific
Plan Amendments will not adversely affect aesthetics.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the mitigation measure recommended in the FEIS/EIR (see page 4-87)
has been adopted by incorporation into the Specific Plan.
Substantial ChangeslNew Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 4-81 to 4-
87)
MCAS Tustin Specific Plan (Pages 2-152 to 2-175)
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 5
II.
AGRICULTURE RESOURCES: In determining whether impacts to
agricultural resources are significant environmental effects, lead agencies
may refer to the California Agricultural Land Evaluation and Site
Assessment Model (1997) prepared by the California Dept. of Conservation
as an optional model to use in assessing impacts on agriculture and
farmland. Would the project:
a) Convert Prime Farmland, Unique Farmland, or Farmland of Statewide
Importance (Farmland), as shown on the maps prepared pursuant to the
Farmland Mapping and Monitoring Program of the California Resources
Agency, to non-agricultural use?
b) Conflict with existing zoning for agricultural use or a Williamson Act
contract?
c) Involve other changes in the existing environment which, due to their
location or nature, could result in conversion of Farmland to non-
agricultural use?
The proposed Specific Plan Amendments will not directly cause agricultural
resources impacts because they are changes to a zoning text, not a development
proposal. Similarly, the project will not directly convert prime farmland, unique
farmland, or farmland of statewide importance as shown on maps prepared
pursuant to the Farmland Managing and Monitoring Program of the California
Resources Agency to non-agricultural use. Also, the property in the MCAS Tustin
Specific Plan area is not zoned for agricultural use or a Williamson Act Contract,
nor does the proposed project involve other changes in the existing environment
that could result in the conversion of farmland to non-agricultural use beyond what
was previously analyzed. The project would not indirectly cause substantial
adverse effects in addition to those identified in the FEIS/EIR because the project
does not permit an increase in the number of residential units or residential floor
area assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project. The
mitigation measures for agricultural resources impacts resulting from the
implementation of FEIS/EIR Alternative 1 (the Specific Plan) were found to be
infeasible and a Statement of Overriding Considerations was adopted.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 6
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-83 to 3-
87 and 4-109 to 4-113)
MCAS Tustin Specific Plan
Tustin General Plan Figure COSR-2
III.
AIR QUALITY: Where available, the significance criteria established by the
applicable air quality management or air pollution control district may be
relied upon to make the following determinations. Would the project:
a) Conflict with or obstruct implementation of the applicable air quality
plan?
b) Violate any air quality standard or contribute substantially to an existing
or projected air quality violation?
c) Result in a cumulatively considerable net increase of any criteria
pollutant for which the project region is non-attainment under an
applicable federal or state ambient air quality standard (including
releasing emissions that exceed quantitative thresholds for ozone
precursors)?
d) Expose sensitive receptors to substantial pollutant concentrations?
e) Create objectionable odors affecting a substantial number of people?
The proposed Specific Plan Amendments will not directly cause air quality
impacts because they are changes to a zoning text, not a development proposal.
Similarly, the project would not conflict with an air quality plan, violate an air
quality standard, result in an increase of any pollutant, expose sensitive
receptors, or create odors. As documented in the FEIS/EIR, the implementation of
the MCAS Tustin Specific Plan was projected to result in unavoidable significant air
quality impacts. The proposed project would not indirectly increase air quality
impacts related to the development of the MCAS Tustin Specific Plan beyond those
previously considered in the adopted FEIS/EIR because the proposed project
would not alter the development potential assumed by Alternative 1 (the Specific
Plan) in the FEIS/EIR.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the mitigation measures recommended in the FEIS/EIR (see pages 4-221-
to 4-224) have been adopted by incorporation into the Specific Plan.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 7
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEISIEIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-143
through153, 4-207 through 4-224 and pages 7-41 through 7-42)
MCAS Tustin Specific Plan
IV.
BIOLOGICAL RESOURCES: - Would the project:
a) Have a substantial adverse effect, either directly or through habitat
modifications, on any species identified as a candidate, sensitive, or
special status species in local or regional plans, policies, or regulations,
or by the California Department of Fish and Game or U.S. Fish and
Wildlife Service?
b) Have a substantial adverse effect on any riparian habitat or other
sensitive natural community identified in local or regional plans,
policies, regulations, or by the California Department of Fish and Game
or U.S. Fish and Wildlife Service?
c) Have a substantial adverse effect on federally protected wetlands as
defined by Section 404 of the Clean Water Act (including, but not limited
to, marsh, vernal pool, coastal, etc.) through direct removal, filling,
hydrological interruption, or other means?
d) Inteñere substantially with the movement of any native resident or
migratory fish or wildlife species or with established native resident or
migratory wildlife corridors, or impede the use of native wildlife nursery
sites?
e) Conflict with any local policies or ordinances protecting biological
resources, such as a tree preservation policy or ordinance?
f) Conflict with the provisions of an adopted Habitat Conservation Plan,
Natural Community Conservation Plan, or other approved local, regional
or state habitat conservation plan?
The proposed Specific Plan Amendments will not directly cause biological
resources impacts because they are changes to a zoning text, not a development
proposal. Similarly, the project will not have a substantial adverse effect on any
species, habitat, wetlands, or wildlife, nor will it conflict with any plans or ordinances
related to biological resources. The FEIS/EIR found that implementation of the
Reuse Plan and MCAS Tustin Specific Plan would not result in impacts to federally
listed threatened or endangered plant or animal species. The FEIS/EIR determined
that implementation of the Reuse Plan and MCAS Tustin Specific Plan could
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 8
impact jurisdictional waters/wetlands and the southwestern pond turtle or have an
impact on jurisdictional waters/wetlands. The proposed project would not
indirectly increase biological resources impacts related to the development of the
MCAS Tustin Specific Plan beyond those previously considered in the adopted
FEIS/EIR because the proposed project would not alter the development potential
assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the mitigation measures recommended in the FEIS/EIR (see pages 4-106-
to 4-107) have been adopted by incorporation into the Specific Plan.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-75
through 3-82, 4-103 through 4-107, and 7-26 through 7-27)
MCAS Tustin Specific Plan
v.
CULTURAL RESOURCES: - Would the project:
a) Cause a substantial adverse change in the significance of a historical
resource as defined in §15064.5?
b) Cause a substantial adverse change in the significance of an
archaeological resource pursuant to § 15064.5?
c) Directly or indirectly destroy a unique paleontological resource or site
or unique geologic feature?
d) Disturb any human remains, including those interred outside formal
cemeteries?
The proposed Specific Plan Amendments. will not directly cause cultural
resources impacts because they are changes to a zoning text, not a development
proposal. Similarly, the project will not adversely change the significance of a
historical or archaeological resource, destroy any paleontological or geologic
resource, or disturb any human remains.
The FEIS/EIR found that implementation of the Reuse Plan and MCAS Tustin
Specific Plan may result in the loss of one or both of the blimp hangars if it would
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 9
not be financially feasible to retain either of the hangars. If this were the case, there
would be irreversible significant impacts. Also, it is possible that previously
unidentified buried archaeological or paleontological resources within the project
site could be significantly impacted by grading and construction activities
associated with future development of the MCAS Tustin site. . The project would
not indirectly cause substantial adverse effects in addition to those identified in the
FEIS/EIR because the project does not change the scope of development
assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the mitigation measures recommended in the FEIS/EIR (see pages 4-97-
to 4-99) have been adopted by incorporation into the Specific Plan.
Substantial Changes/New Infonnation: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-68
through 3-74, 4-93 through 4-99 and 7-24 through 7-26)
MCAS Tustin Specific Plan
Tustin General Plan Figure COSR-3
VI.
GEOLOGY AND SOILS: - Would the project:
a) Expose people or structures to potential substantial adverse effects,
including the risk of loss, injury, or death involving:
. Rupture of a known earthquake fault, as delineated on the most
recent Alquist-Priolo Earthquake Fault Zoning map, issued by the
State Geologist for the area or based on other substantial evidence
of a known fault? Refer to Division of Mines and Geology Special
Publication 42.
. Strong seismic ground shaking?
. Seismic-related ground failure, including liquefaction?
. landslides?
b) Result in substantial soil erosion or the loss of topsoil?
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 10
c) Be located on a geologic unit or soil that is unstable, or that would
become unstable as a result of the project, and potentially result in on-
or off-site landslide, lateral spreading, subsidence, liquefaction or
collapse?
d) Be located on expansive soil, as defined in Table 18-1-B of the Uniform
Building Code (1994), creating substantial risks to life or property?
e) Have soils incapable of adequately supporting the use of septic tanks or
alternative wastewater disposal systems where sewers are not available
for the disposal of wastewater?
The proposed Specific Plan Amendments will not directly cause geology and
soils impacts because they are changes to a zoning text, not a development
proposal.
The FEIS/EIR indicates that impacts to soils and geology resulting from
implementation of the Reuse Plan and MCAS Tustin Specific Plan would "include
non-seismic hazards (such as local settlement, regional subsidence, expansive
soils, slope instability, erosion, and mudflows) and seismic hazards (such as
surface fault displacement, high-intensity ground shaking, ground failure and
lurching, seismically induced settlement, and flooding associated with dam failure."
However, the FEIS/EIR for MCAS Tustin concluded that compliance with state and
local regulations and standards, along with established engineering procedures and
techniques, would avoid unacceptable risk or the creation of significant impacts
related to such hazards. The project would not indirectly cause substantial
adverse effects in addition to those identified in the FEIS/EIR because the project
does not change the scope of development assumed by Alternative 1 (the Specific
Plan) in the FEIS/EIR for MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project. As
identified in the FEIS/EIR, compliance with existing rules and regulations would
avoid the creation of potential impacts. No mitigation is required.
Substantial ChangeslNew Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-88
through 3-97, 4-115 through 4-122 and 7-28 through 7-29)
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 11
MCAS Tustin Specific Plan
Tustin General Plan
VII.
HAZARDS AND HAZARDOUS MATERIALS: - Would the project:
a) Create a significant hazard to the public or the environment through the
routine transport, use or disposal of hazardous materials?
b) Create a significant hazard to the public or the environment through
reasonable foreseeable upset and accident conditions involving the
release of hazardous materials into the environment?
c) Emit hazardous emissions or handle hazardous or acutely hazardous
materials, substances, or waste within one-quarter mile of an existing or
proposed school?
d) Be located on a site which is included on a list of hazardous materials
sites compiled pursuant to Government code Section 65962.5 and, as a
result, would it create a significant hazard to the public or the
environment?
e) For a project located within an airport land use plan or, where such a
plan has not been adopted, within two miles or a public airport or public
use airport, would the project result in a safety hazard for people
residing or working in the project area?
f) For a project within the vicinity of a private airstrip, would the project
result in a safety hazard for people residing or working in the project.
area?
g) Impair implementation of or physically interfere with an adopted
emergency response plan or emergency evacuation plan?
h) Expose people or structures to a significant risk of loss, injury or death
involving wildland fires, including where wildlands are adjacent to
urbanized areas or where residences are intermixed with wildlands?
The proposed Specific Plan Amendments will not directly cause hazards and
hazardous materials impacts because they are changes to a zoning text, not a
development proposal. Similarly, the project will not create a significant hazard to
the public through the transport, use, or disposal of hazardous materials, nor are
there reasonably foreseeable upset and accident conditions. In addition, future
construction and residential uses associated with the MCAS Tustin Specific Plan
would not emit hazardous emissions within a quarter mile of an existing or
proposed school. The Navy has approved a Finding of Suitability to Transfer
(FOST) determining that the Quitclaim portions of the MCAS Tustin site are suitable
for reuse as planned within the Reuse Plan for MCAS Tustin and as shown in the
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 12
MCAS Tustin Specific Plan. In addition, MCAS Tustin Specific Plan is located
within the boundaries of the Airport Environs Land Use Plan; however, it is at least
four (4) miles from John Wayne Airport and does not lie within a flight approach or
departure corridor and thus does not pose an aircraft-related safety hazard for
future residents or workers. The MCAS Tustin Specific Plan is not located in a
wildland fire danger area. Compliance with all federal, state, and local regulations
concerning handling and use of these hazardous substances will reduce potential
impacts to below a level of significance. The project would not indirectly cause
substantial adverse effects in addition to those identified in the FEIS/EIR because
the project does not chahge the scope of development assumed by Alternative 1
(the Specific Plan) in the FEIS/EIR for MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project. As
identified in the FEIS/EIR, compliance with existing rules and regulations would
avoid the creation of potential impacts. No mitigation is required.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin pages (3-106
through 3-117, 4-130 through 4-135 and 7-30 through 7-31)
MCAS Tustin Specific Plan
Finding of Suitability to Transfer (FOST), MCAS Tustin
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 13
HYDROLOGY AND WATER QUALITY: - Would the project:
a) Violate any water quality standards or waste discharge requirements?
b) Substantially deplete groundwater supplies or inteñere substantially
with groundwater recharge, such that there would be a net deficit in
aquifer volume or a lowering of the local groundwater table level (e.g.,
the production rate of pre-existing nearby wells would drop to a level
which would not support existing land uses or planned uses for which
permits have been granted)?
c) Substantially alter the existing drainage pattern of the site or area,
including through the alteration of the course of a stream or river, in a
manner which would result in flooding on- or off-site?
d) Substantially alter the existing drainage pattern of the site or area,
including through the alteration of the course of a stream or river, or
substantially increase the rate or amount of suñace runoff in a manner,
which would result in flooding on- or off-site?
e) Create or contribute runoff water which would exceed the capacity of
existing or planned storm water drainage systems or provide
substantial additional sources of polluted runoff?
f) Otherwise substantially degrade water quality?
g) Place housing within a 100-year flood hazard area as mapped on a
federal Flood hazard Boundary of Flood Insurance Rate Map or other
flood hazard delineation map?
h) Place within a 100-year flood hazard area structures, which would
impede or redirect flood flows?
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 14
i) Expose people or structures to a significant risk of loss, injury or death
involving flooding, including flooding as a result of the failure of a levee
or dam?
j) Inundation by seiche, tsunami, or mudflow?
k) Potentially impact stormwater runoff from construction activities?
I) Potentially impact stormwater runoff from post-construction activities?
m) Result in a potential for discharge of stormwater pollutants from areas
of material storage, vehicle or equipment fueling, vehicle or equipment
maintenance (including washing), waste handling, hazardous materials
handling or storage, delivery areas, loading docks or other outdoor
work areas?
n) Result in a potential for discharge of stormwater to affect the beneficial
uses of the receiving waters?
0) Create the potential for significant changes in the flow velocity or
volume of stormwater runoff to cause environmental harm?
p) Create significant increases in erosion of the project site or surrounding
areas?
The proposed Specific Plan Amendments will not directly cause hydrology and
water quality impacts because they are changes to a zoning text, not a
development proposal. Similarly, the project will not directly cause hydrology and
water resources impacts, nor result in additional impacts beyond what was
analyzed in the adopted FEIS/EIR.
The design and construction of facilities to fully contain drainage of the MCAS
Tustin site would be required as conditions of approval of the future development
projects. No long-term impacts to hydrology and water quality are anticipated for
the future development of the MCAS Tustin site. The proposed future development
will not impact groundwater in the deep regional aquifer or shallow aquifer. The
proposed future development would not include groundwater removal or alteration
of historic drainage patterns at the site. The MCAS Tustin site is not located within
a 1 OO-year flood area and will not expose people or structures to a significant risk of
loss, injury, and death involving flooding as a result of the failure of a levee or dam,
nor is the project site susceptible to inundation by seiche, tsunami, or mudflow.
Construction operations associated with future development of the MCAS Tustin
site would be required to comply with the Total Maximum Daily Load (TMDL) for the
Newport Bay watershed that requires compliance with the Drainage Area Master
Plan (DAMP) and National Pollution Discharge Elimination System (NPDES) and
the implementation of specific best management practices (BMP). Compliance
with state and local regulations and standards, along with established engineering
procedures and techniques, would avoid unacceptable risk or the creation of
significant impacts related to such hazards.
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 15
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project. As
identified in the FEIS/EIR, compliance with existing rules and regulations would
avoid the creation of potential impacts. No mitigation is required.
Substantial ChangeslNew Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
IX.
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-98
through 3-105, 4-124 through 4-128 and 7-29 through 7-30)
MCAS Tustin Specific Plan
FEMA Map (August 9,2002)
LAND USE AND PLANNING: Would the project:
a) Physically divide an established community?
b) Conflict with any applicable land use plan, policy, or regulation of an
agency with jurisdiction over the project (including, but not limited, to
the general plan, specific plan, local coastal program, or zoning
ordinance) adopted for the purpose of avoiding or mitigating an
environmental effect?
c) Conflict with any applicable habitat conservation plan or natural
community conservation plan?
Sources:
The proposed Specific Plan Amendments will not directly cause land use and
planning impacts because they are changes to a zoning text, not a development
proposal. Similarly, the project will not directly physically divide an established
community, nor conflict with any applicable land use plan, habitat conservation plan
or natural community conservation plan.
The City of Tustin is the controlling authority over implementation of the Reuse Plan
for the Tustin portion of the former base, such as land use designations, zoning
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 16
categories, recreation and open space areas, major arterial roadways, urban
design, public facilities, and infrastructure systems. On February 3, 2003, the
Tustin City Council approved the Specific Plan for MCAS Tustin that established
land use and development standards for development of the site. Compliance with
state and local regulations and standards would avoid the creation of significant
land use and planning impacts.
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project. As
identified in the FEIS/EIR, compliance with existing rules and regulations would
avoid the creation of potential impacts. No mitigation is required.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-3 to 3-
17,4-3 to 4-7 and 7-16 to 7-18)
MCAS Tustin Specific Plan
Tustin General Plan land Use Element
x.
MINERAL RESOURCES: Would the project:
a) Result in the loss of availability of a known mineral resource that would
be a value to the region and the residents of the state?
b) Result in the loss of availability of a locally important mineral resource
recovery site delineated on a local general plan, specific plan or other
land use plan?
The proposed Specific Plan Amendments will not directly cause mineral
resources impacts because they are changes to a zoning text, not a development
proposal.
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 17
Chapter 3.9 of the FEIS/EIR indicates that no mineral resources are known to occur
anywhere within the Reuse Plan area. The implementation of the MCAS Tustin
Specific Plan will not result in the loss of mineral resources known to be on the site
or identified as being present on the site by any mineral resource plans.
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project. As
identified in the FEIS/EIR, compliance with existing rules and regulations would
avoid the creation of potential impacts. No mitigation is required.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Page 3-91)
MCAS Tustin Specific Plan
Tustin General Plan
XI.
NOISE: Would the project:
a) Exposure of persons to or generation of noise levels in excess of
standards established in the local general plan or noise ordinance, or
applicable standards of other agencies?
b) Exposure of persons to or generation of excessive ground borne
vibration or ground borne noise levels?
c) A substantial permanent increase in ambient noise levels in the project
vicinity above levels existing without the project?
d) A substantial temporary or periodic increase in ambient noise levels in
the project vicinity above levels existing without the project?
e) For a project located within an airport land use plan or, where such a
plan has not been adopted, within two miles of a public airport or public
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 18
use airport, would the project expose people residing or working in the
project area to excessive noise levels?
f) For a project within the vicinity of a private airstrip, would the project
expose people residing or working in the project area to excessive
noise levels?
The proposed Specific Plan Amendments will not directly cause noise impacts
because they are changes to a zoning text, not a development proposal.
Similarly, the project will not directly expose people to excessive noise or vibration,
or permanently or temporarily increase ambient noise levels.
Future development allowed by the MCAS Tustin Specific Plan could result in
implementation activities that generate noise. The FEIS/EIR indicates that full
build-out of the base will create noise impacts that would be considered significant if
noise levels experienced by sensitive receptors would exceed those considered
"normally acceptable" for the applicable land use categories in the Noise Elements
of the Tustin General Plan.
The City of Tustin will ensure that construction activities associated with future
development of the Specific Plan area comply with the City's Noise Ordinance and
the housing units are designed with adequate noise attenuation (Le., window
design, sound walls) to meet the allowable noise levels as required by Tustin City
Code for residential use. Future development projects would be sound attenuated
against present and projected noise so as not to exceed an exterior noise standard
of 65 dB CNEL in outdoor living areas and an interior standard of 45 dB CNEL in all
habitable rooms to reduce noise-related impacts to a level of insignificance.
Compliance with adopted mitigation measures and state and local regulations and
standards, along with established engineering procedures and techniques, will
avoid unacceptable risk or the creation of significant impacts related to such
hazards.
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the mitigation measures recommended in the FEIS/EIR (see pages 4-236-
to 4-237) have been adopted by incorporation into the Specific Plan.
Substantial ChangeslNew Infonnation: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 19
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-154 to 3-
162,4-231 to 4-237 and 7-42 to 7-43)
MCAS Tustin Specific Plan
Tustin General Plan Noise Element
XII.
POPULATION & HOUSING: Would the project:
a) Induce substantial population growth in an area, either directly (for
example, by proposing new homes and businesses) or indirectly (for
example, through extension of roads or other infrastructure)?
b) Displace substantial numbers of existing housing, necessitating the
construction of replacement housing elsewhere?
c) Displace substantial numbers of people, necessitating the construction
of replacement housing elsewhere?
The proposed Specific Plan Amendments will not directly cause population and
housing impacts because they are changes to a zoning text, not a development
proposal. Similarly, the project will not directly induce substantial population
growth in the area, nor displace people nor necessitate the construction of
replacement housing elsewhere. It is anticipated that the total number of units
would be consistent with the number of units considered in the FEIS/EIR for MCAS
Tustin.
The proposed amendment to MCAS Tustin Specific Plan Section 3.2.3 would
allow the transfer of units to exceed 10 percent without a Specific Plan
Amendment, subject to a written finding by the Director of Community
Development, under certain criteria, including the following:
a. Such transfers shall not increase the total units allowable in the overall
Specific Plan;
b. Unit transfers must remain within the original school district boundaries;
c. Transfers shall be consistent with the uses and development standards of
the receiving area;
d. Units shall be transferred at the same density category as originally
planned;
e. Transfers shall not exceed environmental thresholds established in the
project EIR/EIS.
The proposed criteria would ensure that any transfer of residential units be
compatible with the planning area to which they are transferred and would
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 20
minimize the potential for environmental impacts resulting from the development
of the transferred units.
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project. As
identified in the FEIS/EIR, compliance with existing rules and regulations would
avoid the creation of potential impacts. No mitigation is required.
Substantial ChangeslNew Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-18 to 3-
34,4-14 to 4-21 and 7-18 to 7-19)
MCAS Tustin Specific Plan
XIII.
PUBLIC SERVICES
a) Would the project result in substantial adverse physical impacts
associated with the provision of new or physically altered governmental
facilities, need for new or physically altered governmental facilities, the
construction of which could cause significant environmental impacts, in
order to maintain acceptable service ratios, response times, or other
peñormance objectives for any of the public services:
The proposed Specific Plan Amendments will not directly cause public services
impacts because they are changes to a zoning text, not a development proposal.
The project will not directly change the amount of development of the site that
would require public services such as fire and police protection services, schools,
libraries, recreation facilities, and biking/hiking trails.
Fire Protection. The development of the MCAS Tustin site will be required to
meet existing Orange County Fire Authority (OCFA) regulations regarding
demolition, construction materials and methods, emergency access, water
mains, fire flow, fire hydrants, sprinkler systems, building setbacks, and other
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 21
relevant regulations. Adherence to these regulations would reduce the risk of
uncontrollable fire and increase the ability to efficiently provide fire protection
services to the site. The number of fire stations at and surrounding the site will
meet the demands created by the proposed build out of the Specific Plan.
Police Protection. The need for police protection services is assessed on the basis
of resident population estimates, square footage of non-residential uses, etc.
Development of the MCAS Tustin site would increase the need for police protection
services. As a condition of approval for the future development of the MCAS Tustin
site, developers would be required to work with the Tustin Police Department to
ensure that adequate security precautions such as visibility, lighting, emergency
access, and address signage are implemented in the project at plan check.
Schools. The residential development proposed within the Specific Plan area is
located within the Tustin Unified and Irvine Unified School Districts (TUSD) and
(IUSD). The implementation of the Reuse Plan provides for school sites to serve
the growing student population within the area. As a condition of approval for the
future development of the Reuse Plan area, residential developers would be
required to pay applicable school fees to TUSD or IUSD prior to issuance of
building permits. Under the proposed zone change (specific plan amendment)
transfers of residential units will be required to remain within the same school
district, thereby eliminating any possible additional impacts to school facilities.
Other Public Facilities (Libraries). Recent communication from the Orange County
Library System indicates that implementation of the entire Reuse Plan would result
in an increased library demand. The City is exploring financing opportunities
afforded by conveyance and development of the site to fund expansion of an
existing County-owned library within the City to meet this additional demand for
library services. In addition, three existing public libraries exist within a three-mile
radius of the base. With an additional funding source established for library
expansion, implementation of the proposed project will not result in an increase in
the demand for and utilization of public services and facilities beyond the existing
capacity nor create a demand that exceeds the available planned capacity of those
services.
General Implementation Requirements: To support development in the reuse plan
area, the Reuse Plan/Specific Plan requires public services and facilities to be
provided concurrent with demand. The proposed project will be required to comply
with FEIS/EIR implementation measures adopted by the Tustin City Council.
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 22
because the mitigation measures recommended in the FEIS/EIR (see pages 4-66-
to 4-67) have been adopted by incorporation into the Specific Plan.
Substantial ChangeslNew Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-47 to 3-
57,4-56 to 4-67 and 7-21 to 7-22)
MCAS Tustin Specific Plan
Tustin General Plan
XIV.
RECREATION
a) Would the project increase the use of existing neighborhood and
regional parks or other recreational facilities, such that substantial
physical deterioration of the facility would occur or be accelerated?
b) Does the project include recreational facilities or require the
construction or expansion of recreational facilities, which might have an
adverse physical effect on the environment?
The proposed Specific Plan Amendments will not directly cause recreation
impacts because they are changes to a zoning text, not a development proposal.
Similarly, the project will not directly increase the use of existing parks or require
the construction of recreational facilities.
The Reuse Plan provides for a new 84.5-acre Regional Park, a 24-acre Community
Park, two (2) Neighborhood Parks of at least five-acres each, and bicycle trails, and
riding and hiking paths traversing the property connecting to the regional
bikeway/trail system, play areas associated with schools, and child care facilities.
Since the Reuse Plan process included the accommodation of public conveyance
of approximately 35 acres of city parks and 85 acres of Urban Regional Park,
individual developers were relieved of the requirement to dedicate land for park
purposes. However, pursuant to the MCAS Tustin Specific Plan, developers are
required to provide in-lieu fees or publicly accessible park space (where approved
by the City).
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 23
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the implementation measures recommended in the FEIS/EIR (see pages
4-67-to 4-70) have been adopted by incorporation into the Specific Plan.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin pages 3-47 to 3-
57,4-67 to 4-70
MCAS Tustin Specific Plan
Tustin Parks and Recreation Services Department
Tustin General Plan
xv.
TRANSPORTATIONITRAFFIC: Would the project:
a) Cause an increase in traffic, which is substantial in relation to the existing
traffic load and capacity of the street system (i.e., result in a substantial
increase in either the number of vehicle trips, the volume to capacity ratio
on roads, or congestion at intersections)?
b) Exceed, either individually or cumulatively, a level of service standard
established by the county congestion management agency for
designated roads or highways?
c) Result in a change in air traffic patterns, including either an increase in
traffic levels or a change in location that results in substantial safety
risks?
d) Substantially increase hazards due to a design feature (e.g., sharp
curves or dangerous intersections) or incompatible uses (e.g., farm
equipment)?
e) Result in inadequate emergency access?
f) Result in inadequate parking capacity?
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 24
g) Conflict with adopted policies, plans, or programs supporting
alternative transportation (e.g., bus turnouts, bicycle racks)?
The proposed Specific Plan Amendments will not directly cause transportation
and traffic impacts because they are changes to a zoning text, not a development
proposal. Similarly, the project will not directly cause an increase in traffic, exceed
a level of service standard, change air traffic patters, increase hazards, result in
inadequate emergency access or parking capacity, or conflict with adopted
alternative transportation programs.
The FEIS/EIR indicates that transportation and circulation impacts would be
created through the phased development of the approved Reuse Plan and
MCAS Tustin Specific Plan. A projected 216,445 Average Daily Trips (ADT)
would be generated by full redevelopment of the base by year 2020 that, if left
unmitigated, would overburden existing roadways and intersections surrounding
the base property. The FEIS/EIR indicates that traffic circulation activities at MCAS
Tustin generated a baseline of 12,400 ADT when the base was fully operational
(1993). As a military facility, the FEIS/EIR considered the traffic impact and
developed a mitigation program to reduce potential impacts to a level of
insignificance. In addition, construction activities are required to be meet all
Transportation related FEIS/EIR Implementation and Mitigation Measures (e.g.,
lane closures, street/utility construction, construction vehicle traffic, etc.). The
FEIS/EIR implementation and mitigation measures will reduce potential impacts to
the traffic and circulation system to a level of insignificance.
The proposed zone change would not change the dwelling unit thresholds or
residential density analyzed in the FEIS/EIR, nor generate any additional traffic.
The proposed amendment to MCAS Tustin Specific Plan Section 3.2.3 would
allow the transfer of units to exceed 10 percent without a Specific Plan
Amendment, subject to a written finding by the Director of Community
Development, under certain criteria, including the following:
a. Such transfers shall not increase the total units allowable in the overall
Specific Plan;
b. Unit transfers must remain within the original school district boundaries;
c. Transfers shall be consistent with the uses and development standards of
the receiving area;
d. Units shall be transferred at the same density category as originally
planned;
e. Transfers shall not exceed environmental thresholds established in the
project EIR/EIS.
The proposed criteria would ensure that any transfer of residential units be
compatible with the planning area to which they are transferred and would
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 25
minimize the potential for environmental impacts resulting from the development
of the transferred units.
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the mitigation measures recommended in the FEIS/EIR (see pages 4-154-
to 4-163) have been adopted by incorporation into the Specific Plan.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (Pages 3-118
through 3-142, 4-139 through 4-163 and 7-32 through 7-41)
MCAS Tustin Specific Plan
Tustin General Plan Circulation Element
XVI.
UTILITIES AND SERVICE SYSTEMS: Would the project:
a) Exceed wastewater treatment requirements of the applicable Regional
Water Quality Control Board?
b) Require or result in the construction of new water or wastewater
treatment facilities or expansion of existing facilities, the construction
of which could cause significant environmental effects?
c) Require or result in the construction of new storm water drainage
facilities or expansion of existing facilities, the construction of which
could cause significant environmental effects?
d) Have sufficient water supplies available to serve the project from
existing entitlements and resources, or are new or expanded
entitlements needed?
e) Result in a determination by the wastewater treatment provider, which
serves or may serve the project that it has adequate capacity to serve
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 26
the project's projected demand in addition to the provider's existing
commitments?
f) Be served by a landfill with sufficient permitted capacity to
accommodate the project's solid waste disposal needs?
g) Comply with federal, state, and local statutes and regulations related to
solid waste?
h) Would the project include a new or retrofitted storm water treatment
control Best Management Practice (BMP), (e.g. water quality treatment
basin, constructed treatment wetlands), the operation of which could
result in significant environmental effects (e.g. increased vectors and
odors)?
The proposed Specific Plan Amendments will not directly cause utilities and
service systems impacts because they are changes to a zoning text, not a
development proposal. Similarly, the project will not directly affect waste water,
storm water drainage, water supplies, landfill capacity, solid waste, or Best
Management Practices.
Developers will be responsible for their fair share contribution to the Tustin
Legacy Backbone Infrastructure Improvement Program which includes, but is not
limited to, roadways, water and sewer systems, and backbone underground dry
utilities (electric, gas, cable TV, telephone, etc). In addition, development of the
MCAS Tustin site is required to meet federal, state, and local standards for
design of wastewater treatment. The number of allowable residential units can
be supported by the Irvine Ranch Water District for domestic water and sewer
services. The proposed project would also not result in a need for new landfill
service systems or facilities.
The project would not indirectly cause substantial adverse effects in addition to
those identified in the FEIS/EIR because the project does not change the scope of
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the implementation measures recommended in the FEIS/EIR (see pages
4-43-to 4-46) have been adopted by incorporation into the Specific Plan.
Substantial Changes/New Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 27
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and Reuse of MCAS Tustin (pages 3-35
through 3-46, 4-32 through 4-46 and 7-20 through 7-21)
MCAS Tustin Specific Plan
Tustin General Plan Public Safety Element
XVII. MANDATORY FINDINGS OF SIGNIFICANCE
a) Does the project have the potential to degrade the quality of the
environment, substantially reduce the habitat of a fish or wildlife
species, cause a fish or wildlife population to drop below self-sustaining
levels, threaten to eliminate a plant or animal community, reduce the
number or restrict the range of a rare or endangered plant or animal or
eliminate important examples of the major periods of California history
or prehistory?
b) Does the project have impacts that are individually limited but
cumulatively considerable? ("Cumulatively considerable" means that
the incremental effects of a project are considerable when viewed in
connection with the effects of past projects, the effects of other current
projects, and the effects of probable future projects.)
c) Does the project have environmental effects, which will cause
substantial adverse effects on human beings, either directly or
indirectly?
Based upon the foregoing, the proposed project does not have the potential to
degrade the quality of the environment, substantially reduce the habitats or
wildlife populations to decrease or threaten, eliminate, or reduce animal ranges,
etc. With the enforcement of FEIS/EIR mitigation and implementation measures
approved by the Tustin City Council, the proposed project does not cause
unmitigated environmental effects that will cause substantial effects on human
beings, either directly or indirectly. In addition, the proposed project does have
air quality impacts that are individually limited, but cumulatively considerable
when viewed in connection with the effects of the reuse and redevelopment of
the former MCAS Tustin. The FEIS/EIR previously considered all environmental
impacts associated with the implementation of the Reuse Plan and MCAS Tustin
Specific Plan. The project proposes no substantial changes to environmental
issues previously considered with adoption of the FEIS/EIR. Mitigation measures
were identified in the FEIS/EIR to reduce impact but not to a level of
insignificance. A Statement of Overriding Consideration for the FEIS/EIR was
adopted by the Tustin City Council on January 16, 2001. Consequently, the
project would not indirectly cause substantial adverse effects in addition to those
identified in the FEIS/EIR because the project does not change the scope of
Attachment 1
Evaluation of Environmental Impacts
ZC (SPA) 05-001
Page 28
development assumed by Alternative 1 (the Specific Plan) in the FEIS/EIR for
MCAS Tustin; and no substantial change is expected from the analysis previously
completed in the FEIS/EIR for MCAS Tustin.
Mitigation Measures: No new mitigation measures are warranted because there are
no new substantial adverse environmental effects resulting from the project and
because the mitigation and implementation measures recommended in the
FEIS/EIR have been adopted by incorporation into the Specific Plan.
Substantial ChangeslNew Information: The Specific Plan that was Alternative 1 in
the FEIS/FEIR is not proposed to be substantially changed. As discussed above
and elsewhere in this evaluation, the changes to the text of the Plan simply provide
flexibility in the location and mix of residential units and in the case of density, allow
an interpretation that is consistent with the maximum density assumptions for
Alternative 1 in the FEIS/EIR. There is no substantial change in circumstances
from when the FEIS/EIR was approved or new information of substantial
importance that involves new or more severe environmental effects or new
mitigation measures.
Sources:
Project Description
FEIS/EIR for Disposal and
through 5-11)
MCAS Tustin Specific Plan
Tustin General Plan
Reuse of MCAS Tustin (pages 5-4
CONCLUSION
The summary concludes that all of the proposed project's effects were previously
examined in the FEIS/EIR for MCAS Tustin, that no new effects would occur, that no
substantial increase in the severity of previously identified significant effects would occur,
that no new mitigation measures would be required, that no applicable mitigation
measures previously not found to be feasible would in fact be feasible, and that there are
no new mitigation measures or alternatives applicable to the project that would
substantially reduce effects of the project that have not been considered and adopted. A
Mitigation and Monitoring and Reporting Program and Findings of Overriding
Considerations were adopted for the FEIS/EIR on January 16, 2001 and shall apply to the
proposed project, as applicable.
S:\Cdd\SCOmTustin Legacy\Global Specific Plan Amendments Initial Study Evaluation.doc
ATTACHMENT B
RESOLUTION NO. 3970
(ZONE CHANGE-SPECIFIC PLAN AMENDMENT)
RESOLUTION NO. 3970
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
TUSTIN, CALIFORNIA, RECOMMENDING THAT THE TUSTIN CITY
COUNCIL APPROVE ZONE CHANGE (MCAS TUSTIN SPECIFIC
PLAN AMENDMENT) 05-001 TO AMEND SECTIONS 3.2; 3.2.2; 3.2.3;
3.9.2; FOOTNOTES TO TABLES 3-1 AND 3-2 AND THE DEFINITIONS
SECTION OF THE MCAS TUSTIN SPECIFIC PLAN RELATING TO
DENSITY CALCULATION, DEVELOPMENT UNIT DEFINITION, AND
TRANSFER OF UNITS
The Planning Commission of the City of Tustin does hereby resolve as follows:
I.
The Planning Commission finds and determines as follows:
A.
B.
That City staff has identified proposed amendments to the MCAS
Tustin Specific Plan as Zone Change (MCAS Tustin Specific Plan
Amendment) 05-001 to amend Sections 3.2; 3.2.2; 3.2.3, 3.9.2,
footnotes to Tables 3-1 and 3-2 and the Definitions section
(Chapter 6, Appendix D) of the MCAS Tustin Specific Plan as
identified in Exhibit A attached hereto.
The proposed amendments are consistent with the Tustin General
Plan. The Land Use Element includes the City's goals and policies
for the long-term growth, development, and revitalization of Tustin,
including the MCAS Tustin Specific Plan area. The Tustin Land
Use Element identifies ten goals, which include the following:
1.
2.
Achieve balanced development.
Ensure that compatible and complementary development
occurs.
Revitalize older commercial, industrial, and residential
development.
Improve city-wide urban design.
Promote economic expansion and diversification.
Coordinate development with provision of adequate public
facilities and services.
Ensure that the development character of East Tustin is
compatible with the surrounding man-made and natural
environment.
Strengthen the development character and mixture of uses
in the Old Town/First Street area.
Promote an integrated business park character for the
Pacific Center East area.
3.
4.
5.
6.
7.
8.
9.
Resolution No. 3970
Page 2
10.
Implement a reuse plan for MCAS Tustin which maximizes
the appeal of the site as a mixed-use, master-planned
development.
These goals establish the framework for policies related to
allocation of land use in the City, and the implementation policies
reflect the direction and image the City seeks for the future.
Proposed Zone Change 05-001 supports the General Plan goals
and the policies established for the MCAS Tustin Specific Plan
area, including the following:
1. Goal 1. Provide for a well balanced land use pattern that
accommodates existing and future needs for housing,
commercial and industrial land, open space and community
facilities and services while maintaining a healthy, diversified
economy adequate to provide future City services.
a. Policy 1.10 - Ensure that the distribution and intensity of
land uses are consistent with the land Use Plan and
classification system.
2. Goal 13. The project will implement policies under the goals and
policies for future development of MCAS Tustin Specific Plan
including:
a.
Policy 13.2 - Encourage a development pattern that
offers a connectedness between buildings and uses,
and has a strong sense of place through architectural
styles and creative landscape design.
Policy 13.5 - Promote high quality architecture,
landscaping, signage, open space design, circulation
patterns, and landscape patterns distinct from
surrounding areas.
b.
C.
That a public hearing was duly called, noticed, and held on said
application on April 25, 2005, by the Planning Commission.
II.
The Planning Commission hereby recommends that the City Council
approve Zone Change (MCAS Tustin Specific Plan Amendment) 05-001
to amend Sections 3.2; 3.2.2; 3.2.3; 3.9.2, footnotes to Tables 3-1 and 3-2
and the Definitions section (Chapter 6, Appendix D) of the MCAS Tustin
Specific Plan, as identified in Exhibit A, attached hereto.
Resolution No. 3970
Page 3
PASSED AND ADOPTED at a regular meeting of the Tustin Planning
Commission held on the 25th day of April, 2005.
JOHN NIELSEN
Chairperson
ELIZABETH A. BINSACK
Planning Commission Secretary
STATE OF CALIFORNIA)
COUNTY OF ORANGE)
CITY OF TUSTIN )
I, ELIZABETH A. BINSACK, the undersigned, hereby certify that I am the
Planning Commission Secretary of the Planning Commission of the City of
Tustin, California; that Resolution No. 3970 was duly passed and adopted at a
regular meeting of the Tustin Planning Commission, held on the 25th day April,
2005.
ELIZABETH A. BINSACK
Planning Commission Secretary
EXHIBIT A OF RESOLUTION NO. 3970
Chapter 3. land Use and Development/Reuse Regulations
Specific Plan by defining appropriate locations for certain land uses and
permitted development intens ities. The Land Use Plan includes thirteen
(13) separate land use designations as described in Section 2.2.1. Each
parcel within the Specific Plan has been assigned a specific land use
designation. Each designation has been assigned a Planning Area (PA)
number, as shown on Figure 3-1. The Planning Area is the smallest
regulatory unit for the application of development regulations. The
development standards are customized for each Planning Area and
grouped according to the neighborhood in which they belong.
The Land Use Plan Statistical Analysis is organized in two ways. Table 3-
1 is the Land Use Plan Statistical Analysis organized by land use
designation, and Table 3-2 is the Land Use Plan Statistical Analysis
organized by neighborhood. The neighborhoods of the Plan are shown
again for reference in Figure 3-2. Each statistical analysis contains the
approximate acreages, square footage allocations and dwelling units
permitted in each Planning Area shown on the Land Use Plan. Each
Planning Area is assigned an amount of land devoted to existing buildings
(where applicable), and includes an allocation of land available for new
uses based on the density/intensity standards established in the Specific
Plan. The maximum number of dwelling units and total square footage of
non-residential development provided for in the Specific Plan are
prescribed in the Statistical Analysis and further defined in the following
I regulations sections. Calculation of development potential is based on Ret
gross acreage figures for each Planning Area, which excludes land
devoted to arterial roadways as identified in the Circulation Plan (Figure
2-5) aM loeal roaå'.':ays (p!:1blie a:oå private) \yhieh are eK~eeteå to øee\:H"
within each PlarJliRg Area.
The shaded area on the Land Use Planning Areas map (Figure 3-1)
indicates where alternative conceptual roadway alignments for Tustin
Ranch Road and Warner Avenue could occur. The Land Use Plan
Statistical Analysis assumes the most easterly alignment for Tustin Ranch
Road and the most southerly alignment for Warner Avenue. If either final
alignment differs from these assumed conceptual locations, the provisions
of Section 3.2.5, below, shall apply.
MCAS Tustin Specific Plan/Reuse Plan
City of Tustin
Page 3-5
Chapter 3. land Use and Development/Reuse Regulations
TABLE 3-1
LAND USE PLAN STATISTICAL ANALYSIS ORGANIZED BY LAND USE DESIGNATION
ACREAGE NON-RESIDENTIAL USES RESIDENTIAL USES
Total Floor Existing Floor Potential Floor DU's Potential Existing Total
DesignationIPlanning Area Gross 1 Net 2 F.A.R. 3 Area (SQ. FtJ 4 Area (SQ. FtJ 5 Area (Sq. Ft) e Per Acre 7 DU'se DU's9 DU's1o
INSTlTUTIONAL/RECREATIONAL (CONTINUEDJ
Ri2;ht-of-Way
Arterial Roadways 23 158.4 158.4 0 0 0 0 0 0 0
Drainage (Flood Control, Storm 28.5 28.5 0 0 0 0 0 0 0
Drains)"
SUBTOTAL 423.5 403.6 N/A 2,028,174 1,359,155 669,019 0 0 0 0
TOTALS: 1,606.2 1,462.5 N/A 11,406,975 2,185,317 9,221,658 0 3,064 1,537 4,601
Notes:
I. Gross acreage for each Planning Area is an estimated allocation measured from the edge of the adjacent future arterial and secondaIy roadway, any public roadway shown on the Land Use Plan, and/or the
boundaIy of the Planning Area. The amount ofland devoted to roadways shown on the Plan is calculated under the Right-of-Way designation. Actual acreages will be refmed during the site plan and
subdivision process.
2. Net acreage is an estimated allocation based on gross acreage reduced for internal circulation (local roads) within a Planning Area. Net acreage is estimated approximately for each Planning Area, based on
permitted use, size of the Planning Area, and typical site planning considerations. Actual net acreages will be refmed during the site plan and subdivision process.
3. Floor Area Ratio (F AR.) is the gross floor area of all buildings within a Planning Area divided by the net acreage of the Planning Area for purposes of this Statistical Analysis. The FAR. column specifies
a floor area ratio derived from an assumed mix of uses within a Planning Area. The mix of commercial, industrial, office, or other uses that have been initially assigned to each Planning Area are shown on
Table 3-3. This floor area ratio has been used to calculate Total Floor Area (square footage) allocated to each Planning Area. The maximum floor area ratio at which a particular use can be developed is
specified in Chapter 3. Floor area ratio specifies development intensity for non-residential uses, whereas DU's per acre specify maximum density for residential uses.
4. Total Floor Area is the total square footage of non-residential development derived by multiplying the floor area ratio by the net acreage.
S. Existing Floor Area is the square footage of existing buildings by Planning Area.
6. Potential Floor Area is the potential square footage of new development within each Planning Area, assuming the square footage devoted to existing structure remains.
I 7. DU's per Acre reflects the maximum density per Bet-acre at which dwelling units may be calculated. The density ranges for each residential land use designation are specified in Section 2.2.1.
8. Potential DU's is the maximum number of new dwellings units, based on the density per Bet-acre for the Planning Area.
9. Existing DU's identifies the existing military family housing units within each Planning Area. The bachelor housing (or barracks quarters) is accounted for in the Existing Floor Area column.
10. Total DU's is the maximum number of dwelling units allocated to each Planning Area. Even though actual gross and net acreages may be refmed during the site plan and subdivision process, the maximum
number of dwelling units in each Planning Area shall not exceed the number designated on the Statistical Analysis, except as specified in Section 3.2.3.
II. The DU's per acre figure of7.0 reflects the maximum density of development should the existing housing be replaced by new housing.
12. A portion ofPA 21 (ISO units) and all ofPA 22 (402 units) are located within the City of Irvine. The permitted density range in PA 22 shall not exceed 12.5 dwelling units per acre at the high end.
13. PA 22 is within the Irvine jurisdictional limits. It includes a 20-acre allocation for a K-8 school. The precise acreage and location will be determined when the Navy's Record of Decision is issued. PA 22
also includes an 8-acre allocation for a Neighborhood Park site. The precise acreage and location will be detennined prior to property transfer to the City of Irvine, however, the total allowable dwelling
units in PA 22 will remain the same.
14. P A IS-A includes a S-acre allocation for a neighborhood park site. The precise acreage and location will be detennined prior to fmal subdivision map approval, however, the total allowable dwelling units
in PA IS-A will remain the same.
IS. PA IS-B includes a 10-acre allocation for an Elementary School. The precise acreage and location will be detennined when the Navy's Record of Decision is issued. If the actual acreage varies from 10
acres, then an acreage adjustment will be made to the Medium Density designation, however, the maximum units shown in the Statistical Analysis shall not be exceeded. PA IS-B also includes as-acre
allocation for a neighborhood park site. The precise acreage and location will be detennined prior to fmal subdivision map approval, however, the total allowable dwelling units in PA IS-B will remain the
same.
16. PA 8 includes a 4O-acre allocation for a High School. The precise acreage and location will be detennined when the Navy's Record of Decision is issued. If the actual acreage varies from 40 acres, then the
acreage adjustment will be made to the Community Core designation, however, the total allowable square feet of non-residential development and maximum dwelling units in P A 8 will remain the same.
17. PA I is composed of numerous public conveyance uses as specified in Section 2.3 and 2.4 of the Specific Plan.
18. P A I-A includes a 10-acre allocation for an Elementary School. The precise acreage and location will be detennined when the Navy's Record of Decision is issued. If the actua1 acreage varies from 10
acres, then an acreage adjustment will be made to the Learning Village use, however, the total allowable square feet of non-residential development in P A I-A will remain the same.
City of Tustin
Page 3-8
MCAS Tustin Specific Plan/Reuse Plan
Chapter 3. Land Use and Development/Reuse Regulations
TABLE 3-2
LAND USE PLAN STATISTICAL ANALYSIS ORGANIZED BY NEIGHBORHOOD
ACREAGE NON-RESIDENTIAL USES RESIDENTIAL USES
Existing Potential
Total Floor Floor Area Floor Area DU's Potential Existing Total
Desisrnation/Planninf! Area Gross 1 Net 2 F .A.R. 3 Area (Sq. Ft.) 4 (Sa. Ft.J 5 (Sa. Ft.) e Per Acre7 DU'se DU's9 DU's1o
NEIGHBORHOOD H
Planning Area 22 12 73.4 61.0 N/A N/A N/A 15 0 402 402
Medium Density (8-15 du/ac)
Elementary School K.8 13
Neighborhood Park 13
SUBTOTAL FOR NEIGHBORHOOD H 73.4 61.0 N/A N/A N/A N/A N/A 0 402 402
RIGHT-OF-WAY
Roadways 22 158.4 158.4 N/A N/A N/A 0 0 0 0
Drainage (Flood Control, Storm 28.5 28.5 N/A N/A N/A 0 0 0 0
Drains)
SUBTOTAL RIGHT OF WAY 186.9 186.9 N/A N/A N/A N/A 0 0 0 0
TOTALS: 1,606.2 1,462.5 N/A 11,406,975 2,185,31719 9,221,658 N/A 3,064 1,537 4,601
Notes:
I. Gross acreage for each Planning Area is an estimated allocation measured from the edge of the adjacent future arterial and secondary roadway, any public roadway shown on the Land Use Plan, and/or the
boundary of the Planning Area. The amount of land devoted to arterial roadways shown on the Plan is calculated under the Right-of-Way designation. Actual acreages will be rermed during the site plan
and subdivision process.
2. Net acreage is an estimated allocation based on gross acreage reduced for internal circulation (local roads) within a Planning Area. Net acreage is estimated approximately for each Planning Area, based on
permitted use, size of the Planning Area, and typical site planning considerations. Actual net acreages will be rermed during the site plan and subdivision process.
3. Floor Area Ratio (FAR) is the gross floor area of all buildings within a Planning Area divided by the net acreage of the Planning Area for purposes of this Statistical Analysis. The FAR. column specifies
a floor area ratio derived from an assumed mix of uses within a Planning Area. The mix of commercial, industrial, office, or other uses that have been initially assigned to each Planning Area are shown on
Table 3-3. This floor area ratio has been used to calculate Total Floor Area (square footage) allocated to each Planning Area. The maximum floor area ratio at which a particular use can be developed is
specified in Chapter 3. Floor area ratio specifies development intensity for non-residential uses, whereas DU's per acre specifY maximum density for residential uses.
4. Total Floor Area is the total square footage of non-residential development derived by multiplying the floor area ratio by the net acreage.
5. Existing Floor Area is the square footage of existing buildings by Planning Area.
6. Potential Floor Area is the potential square footage of new development within each Planning Area, assuming the square footage devoted to existing structure remains.
7. DUs per Acre reflects the maximum density per Bet-acre at which dwelling units may be calculated. The density ranges for each residential land use designation are specified in Section 2.2.1.
8. Potential DU's is the maximum number of new dwellings units, based on the density per Bet-acre for the Planning Area.
9. Existing DU's identifies the existing military family housing units within each Planning Area. The bachelor housing (or barracks quarters) is accounted for in the Existing Floor Area column.
10. Total DUs is the !DIIXÌInum number of dwelling units allocated to each Planning Area. Even though actual gross and net acreages may be rermed during the site plan and subdivision process, the maximum
number of dwelling units in each Planning Area shall not exceed the number designated on the Statistical Analysis, except as specified in Section 3.2.3.
II. The DU's per acre figure of7.0 reflects the maximum density of development should the existing housing be replaced by new housing.
12. A portion ofPA 21 (150 units) and all ofPA 22 (402 units) are located within the City ofIrvine. The permitted density range in PA 22 shall not exceed 12.5 dwelling units at the high end.
13. PA 22 includes a 20-acre allocation for aK-8 school. The precise acreage and location will be detennined when the Navy's Record of Decision is issued. PA 22 also includes an 8-acre allocation for a
neighborhood park site. The precise acreage and location will be detennined prior to property transfer to the City of Irvine, however, the total allowable dwelling units in PA 22 will remain the same.
14. P A 15-A includes a 5-acre allocation for a neighborhood park site. The precise acreage and location will be detennined prior to rmal subdivision map approval, however, the total allowable dwelling units
in PA 15-A will remain the same.
MCAS Tustin Specific Plan/Reuse Plan
City of Tustin
Page 3-15
Chapter 3 . Land Use and Development/Reuse Regulations
3.2.1
land Use Boundaries
Land use designation boundaries are generally as depicted on the Land
Use Plan, Figure 2-1. The Planning Area boundaries are equivalent to the
land use designation boundaries, and are shown in Figure 3-1.
Adjustments in boundaries resulting from final road alignments or more
precise surveys, or technical refinements will not require a Specific Plan
Amendment. While precise boundaries and acreages will be determined
when more definitive plans are submitted, the maximum development
limits as shown in the Land Use Statistical Analysis (Table 1-1) shall
apply, subject to transfer conditions between neighborhoods provided
below in Sections 3.2.3 and 3.2.4.
3.2.2
Maximum Dwelling Units
The maximum number of dwelling units in each Planning Area may not
exceed the numbers as specified on the Land Use Statistical Analysis.
The calculation of residential density, as stated in dwelling units per acre,
shall be based on aet-gross acres for each project. Net-Gross acres is
defined as ~ acres less the arterial roadways as identified on the
Circulation Plan (Figure 2-5) and local roa(:h1¡'ays (beth fl1:lblie and prÍ'.'at@)
internal to the PlaRFliBg Area.
3.2.3
Transfer of Dwelling Unit Allocations
If a Planning Area is developed with less than the maximum number of
units allowed, then the "unused" residential development potential may be
transferred to another Planning Area which supports residential uses. In no
case shall transfers of units result in:
A.
The maximum number of dwelling units in a Planning Area
exceeding prescribed Planning Area maximums by more than 10
percent without a Specific Plan Amendment, as shown on the Land
Use Statistical Analysis (Table 3-1 ), unless the following criteria are
met, subject to a written finding by the Director of Community
Development:
I. Such transfers shall not increase the total units allowable in the
overall Specific Plan;
2. Unit transfers must remain within the original school district
boundaries;
3. Transfers shall be consistent with the uses and development
standards of the receiving area:
MCAS Tustin Specific Plan/Reuse Plan
City of Tustin
Page 3-17
Chapter 3 . land Use and Development/Reuse Regulations
4. Units shall be transferred at the same density category as
originally planned;
5. Transfers shall not exceed environmental thresholds established
in the project EIRÆIS.
B.
Significant alteration of the basic character of development in the
gaining or losing Planning Area.
3.2.4
Non-Residential Land UselTrip Budget
The non-residential land use/trip budget tracking system is a mechanism
for managing the forecasted vehicular trips generated by the land use mix
in the Specific Plan. The purpose of the tracking system is to ensure that
development can be accommodated within the planned roadway capacity
of the on-site and off-site roadway systems.
The basis for the trip budget is the specification of a mix of non-residential
uses for each neighborhood. The budget establishes a baseline capacity of
average daily trips (ADT) for each neighborhood. Using assumed traffic
generation rates, the number of trips that would be generated at buildout of
the Plan was estimated. This mix has been further allocated to Planning
Areas only for ease of administration. However, the trip budget by
neighborhood shall control the amount and intensity of non-residential
uses by neighborhood.
In order to manage the availability of lOadway capacity, a Trip Budget
Tracking System is established as part of this Specific Plan to monitor and
report on the traffic implications of each development project which
involves non-residential uses. The system entails establishment of a
maximum limit on the number of ADT's generated from non-residential
uses within the Specific Plan and for each neighborhood. That limit is
shown in Table 3-3, Trip Budget, which summarizes the square footage of
non-residential uses allocated to each neighborhood by Planning Area, and
the associated ADT. Residential uses are shown for information only, but
are not part of the Trip Budget. This information is derived from the
Environmental Impact StatementÆnvironmental Impact Report for the
Disposal and Reuse of MCAS Tustin.
TABLE 3-3
PLANNING AREA TRIP BUDGET 1
Planning
Area No.
Assumed Land Use
3,033
8,479
City of Tustin
Page 3-18
MCAS Tustin Specific Plan/Reuse Plan
Chapter 3 . land Use and Development/Reuse Regulations
.
5.
Tenure - Development in Planning Area 15 of apartments is a
discretionary action requiring approval of a conditional use
permit. No more than 25 percent of the total number of units
permitted within the Tustin portion of the Specific Plan area
may be approved for apartments.
Prior to approval of any subdivision map or site plan in
Planning Area 15, a precise boundary plan for the golf course
shall be submitted by the developer to the City of Tustin for
review and approval. This plan shall precisely define the edges
of the course and show frontages and visibility from Edinger
Avenue, Tustin Ranch Road, and North Loop Road. In
addition, the plan shall identify a program for public use of the
golf course, and conceptually identify/locate proposed
buildings and facilities such as clubhouse, driving range, golf
school, snack bar, and maintenance yards.
Prior to issuance of building permits for golf course facilities,
the ultimate owner or operator of the golf course shall enter
into a recordable agreement with the City of Tustin that will
specify that the course:
a) Will remain open to the public;
b) Will make available a certain percentage of high demand
tee times for public walk-on use; and
Will establish a formula to guarantee the affordability of
a round of golf to Tustin residents.
Condominiums, multiple family developments, and patio
homes may contain numerous lots, but shall be designated as a
de~¡eløf!meRt Development æHt-Unit on a tentative map. The
minimum size for a development unit shall be -W-2acres...A
development unit which is proposed to contain multiple
products shall have a single site plan and shall be designed as
one development with integrated architecture, design features,
circulation. and maintenance of common areas.
Hotel and commercial uses, not including the golf course, shall
be located only in the vicinity of Edinger Avenue and
Jamboree Road.
Refer to Section 3.11.24 for dedication requirements for the
Santa Ana - Santa Fe Channel.
If the final alignment for Tustin Ranch Road and Warner
Avenue differs from the assumed alignments as described in
Section 3.2, adjustments in acreage and development potential
for Planning Area 15 and Planning Area 8 (Community Core)
shall be calculated in accordance with the provisions of Section
3.2.5. While the respective Planning Area boundaries may shift
slightly, Tustin Ranch Road and Warner Avenue will remain
the common boundary between Planning Area 15 and Planning
Area 8.
6.
7.
c)
8.
9.
10.
11.
MCAS Tustin Specific Plan/Reuse Plan
City of Tustin
Page 3-135
Appendices
D.
DEFINITIONS
Words, phrases and tenus not specifically defined herein shall be as
defined in the Tustin City Code.
Acres, Gross. An estimated allocation of land area within a Planning Area,
measured from the edge of the adjacent arterial roadways and/or the
boundary ofthe Planning Area (as shown on the Land Use Planning Areas
map).
Acres, Net. An estimated allocation of land area within a Planning Area,
based on gross acreage reduced for internal circulation (local roads) within
a Planning Area.
Baseline Mix of Uses. An assumed mix of ron-residential uses for each
neighborhood, which establish a baseline capacity of average daily trips
for each neighborhood.
Building Setbacks. Building setback distances are measured from future
rights-of-way. Non-confonning building setbacks will be permitted to
remain to accommodate existing buildings not in future rights-of-way.
Children's Intennediate Care Shelter. A 60-bed emergency shelter for
abused, neglected children.
Concept Plan. A type of plan required concurrent with submission of a
new development proposal, reuse project, or subdivision used to document
and insure that the necessary linkages are provided between the
development project and the Planning Area/Neighborhood in which it is
located, the integrity of the Specific Plan and purpose and intent of each
Neighborhood is maintained, and applicable considerations of City
requirements are identified and satisfied.
Development Unit. Consists of all building sites, their private open space,
common recreation and open space areas, and public and/or private streets
serving 1he I'rejeeta proposed development project that is five acres or
more. A development unit may contain multiple products, at an average
density not to exceed maximum densities for each applicable land use
designation (i.e. low dens ity, medium density, and medium high density).
Dwelling Units, Existing. The existing military family housing units
within the MCAS Tustin boundary.
I Dwelling Units per Acre. The maximum density per grossBet acre at which
dwelling units may be calculated. This overall density may not be
exceeded even by a fraction.
City of Tustin
Page 6-36
MCAS Tustin Specific Plan/Reuse Plan
Appendices
Dwelling Units, Potential. The maximum number of new dwelling units,
I based on the density per~~acre for the Planning Area.
Dwelling Units, Total. The maximum number of existing and potent ial
dwelling units allocated to each Planning Area (where applicable).
Floor Area Ratio (F.A.R.). The gross floor area of all buildings within a
Planning Area divided by the net acreage of the Planning Area.
Existing Floor Area. The square footage of existing buildings within the
MCAS Tustin boundary.
Floor Area, Potential. The potential square footage of new development
within each Planning Area, assuming the square footage devoted to
existing structure remains.
Floor Area, Total. The total square footage of non-residential development
derived by multiplying the floor area ratio by the net acreage.
Household Income Level, Low. Fifty to eighty percent of the County
median income level.
Household Income Level, Moderate. Eighty to one-hundred twenty
percent of the County median income level.
Household Income Level, Very Low. Zero to fifty percent of the County
median income level.
Interim Use. The purpose for which a parcel of land or a structure is or
may be intended, designed, arranged, constructed, erected, occupied,
leased, maintained, altered, moved and/or enlarged for a limited period of
time in excess of six months and not to exceed 5 years from the date of the
interim lease, in lieu of a permanent use in accordance with this Specific
Plan.
Landscape Setbacks. Landscape setback distances are measured from the
back of the curb and are a combination of parkway, sidewalk, and planting
areas. Non-conforming landscape setbacks will be permitted to remain to
accommodate existing walls not in future right-of-way.
Law Enforcement Training Facility. An educational facility including
classroom training, office space, obstacle course, gym, locker and shower
facilities, canine training, indoor pistol range, laser village and weapons
storage to be located within the proposed Urban Regional Park site.
MCAS Tustin Specific Plan/Reuse Plan
City of Tustin
Page 6-37