HomeMy WebLinkAboutTPFA 02 ENA PARTNERS 06-06-05
8
AGENDA REPORT
Agenda Item TPFA 2
Rewewed: I ~~~
City Manager ~
Finance Director N/A
MEETING DATE: JUNE 6, 2005
FROM:
WILLIAM A. HUSTON, CITY MANAGER
CHRISTINE SHINGLETON, ASSISTANT CITY MANAGER
TO:
SUBJECT:
SECOND AMENDMENT TO EXCLUSIVE AGREEMENT TO
NEGOTIATE WITH TUSTIN COMMUNITY PARTNERS, LLC FOR THE
TUSTIN LEGACY MASTER DEVELOPER SITE
SUMMARY
Approval is requested for a Second Amendment to the Exclusive Agreement to
Negotiate with Tustin Legacy Community Partners, LLC.
RECOMMENDATION
It is recommended that the Tustin Public Financing Authority authorize the City Manager
to execute the Second Amendment to the Exclusive Agreement to Negotiate (ENA)
between the City, the Tustin Public Financing Authority and Tustin Legacy Community
Partners (TLCP), LLC.
FISCAL IMPACT
TLCP has been depositing funds to cover City costs of planning and negotiations to
date. The intent of the continuing negotiation period is to complete Phases II through V
in order that the City may then complete a final Disposition and Development
Agreement (DDA) for City Council consideration. There will likely be direct financial
impacts from the eventual development of the Tustin Legacy Master Developer site.
Fiscal impacts will be evaluated as part of the negotiation process and summarized for
the City Council when the DDA is brought forward for consideration.
BACKGROUND
The Tustin City Council previously selected TLCP for negotiations on the development
of an approximate 700 acre Master Developer site at Tustin Legacy. A Exclusive
Negotiation Agreement (ENA) was executed for the project on November 1, 2003. The
ENA identified the following phases in the planning and negotiation process:
Phase I -- Preliminary Master Development Plan (PMDP)
Page 2
Phase 11-- Refinement of Master Development Plan (MDP) & Infrastructure
Plans & completion of Preliminary Business Plan
Phase III--Preparation of Master Development Package
Phase IV-- Negotiation of Term Sheet and completion of a DDA
Based on revisions to the Master Development Plan requested by the City Council In
June 2004, the Developer subsequently requested the First Amendment to the ENA in
October 2004 to reflect completion of Phase II by December 15, 2004 and Phase IV by
August 1, 2005. Provisions of the First Amendment permitted the City upon a request
from the TLCP and demonstration of signficant progress by TLCP, to provide certain
extensions for completion of Phases II through IV, all of which have now been
exhausted. The last extension granted for submittal of the Preliminary Business Plan
under Phase II was April 18, 2005 (this automatically pushed out completion of Phase
IV, the DDA until December 15).
The Refined Master Development Plan was reviewed by the City Council on November
1, 2004 with specific direction provided to City staff. TLCP subsequently has been
working diligently on completion of the Preliminary Business Plan. The complete
Preliminary Business Plan was submitted to the City on May 23, 2005, with all required
information. This now necessitates a Second Amendment to the ENA to reflect
modifications to the schedule for completion of remaining Phases of the planning and
negotiations process.
The Developer has made reasonable and sufficient progress towards fulfillment of the
requirements of the ENA. Accordingly, we would recommend an extension of time of
the negotiation period identified in the First Amendment to the ENA to permit completion
by the Developer of Phases III through IV by January 20, 2004, unless additional time
is necessary subject to written agreement of the City and the Tustin Public Financing
Authority. All other terms of the original ENA and First Amendment to the ENA, unless
altered by the Second Amendment to the ENA would continue to remain in effect.
/c'
Christine Shingleton
Assistant City Manager
SECOND AMENDMENT TO EXCLUSIVE NEGOTIATION AGREEMENT
THIS SECOND AMENDMENT TO EXCLUSIVE NEGOTIATION AGREEMENT
(this "Second ENA Amendment") dated as of June 6, 2005 ("Amendment Effective Date") is
entered into by and among THE CITY OF TUSTIN (the "City"), the Tustin Public Financing
Authority (the "Authority"; the Authority and the City collectively, the "Agencies"), and
TUSTIN LEGACY COMMUNITY PARTNERS, LLC, a Delaware limited liability company
(the "Developer"). The City, the Authority and the Developer (collectively, the "Parties")
hereby agree as follows:
RECITALS
A. Reference is made to that certain Exclusive Negotiation Agreement (Master
Development Site) dated as of November 1,2003 (the "Effective Date"), by and among the
Agencies and Developer (the "Original ENA") and the First Amendment to the Exclusive
Negotiation Agreement (the "First Amendment"; with the Original ENA, the "Prior ENA").
B. The Parties have made substantial progress towards completing the various tasks
established in Phase I and II of the Master Development Planning Process as specified in Section
2.2.1 of the Prior ENA.
C. At the request of the Developer, the City has previously granted two extensions of
the Master Development Planning Process, pursuant to Section 2.2.3 of the Prior ENA, in order
to extend the time for completion of Phase II, III and IV of the Master Development Planning
Process.
D. The Parties now desire to amend the Prior ENA to extend the dates for completion
of Phases II, III and IV of the Master Development Planning Process and to extend the ENA
TenTI set forth in the Prior ENA, in order to reflect the extensions granted with respect to Phases
I, II, III and IV of the Master Development Planning Process, and to provide for certain
additional amendments to the Original ENA as provided herein.
NOW, THEREFORE, in consideration of the mutual agreements contained
herein, and for other good and valuable consideration, the receipt and sufficiency of which are
hereby acknowledged, the Agencies and Developer hereby agree as follows:
AGREEMENT
1. Definitions. Capitalized tenTIS used and not otherwise defined in this ENA Amendment
shall have the same meanings given to them in the Original ENA. From and after the
Amendment Effective Date, all references in the Original ENA or in the First Amendment to
"this Agreement" shall be deemed to refer to the Prior ENA as amended by this Second ENA
Amendment.
(a) Section 2.2.1 ofthe First Amendment is hereby deleted in its entirety and replaced
with the following:
TUSTIN LEGACY MASTER DEV>ENA-v-l]
A-I
Exclusive Negotiation Agreement
(Master Development Site)
"2.2.1 Notwithstanding the period of exclusive negotiations established by this
Agreement and in addition to the tennination rights set forth in Section 2.2.4, if
either the City or the Authority detennines in its sole discretion and notifies
Developer in writing (a) at any time that the Developer is not negotiating
diligently or in good faith or (b) that the Parties have failed to make substantial
progress in accordance with the Schedule ofPerfonnance, including completing
Phase I of the Master Development Planning Process not later than March I,
2004, , Phase II ofthe Master Development Planning Process not later than May
23,2005, Phase III of the Master Development Planning Process not later than
July 25, 2005 and Phase IV of the Master Development Planning Process not later
than January 23, 2006 or (c) that on or before July 25,2005 that the Parties have
not completed Phases I through III of the Master Development Planning Process
sufficient to allow final negotiation and preparation of the Tenn Sheet, then either
City or Developer may tenninate this Agreement at any time thereafter upon five
(5) days written notice to the other Parties and such tennination shall be binding
upon each of the Parties."
(b) Section 2.2.3 of the First Amendment is hereby deleted in its entirety and replaced
with the following
"2.2.3. On or before the date set forth in the Schedule ofPerfonnance for
Completion of the work described in Phases I through IV of the Master
Development Planning Process, the Developer may request in writing from the
Agencies a thirty (30) day extension of the time period for completion of such
Phase of the Master Development Planning Process. Upon receipt of such
request, each of the Agencies shall detennine in its sole discretion whether
reasonable and sufficient progress has been obtained toward fulfillment of the
requirements of this Agreement, and if each so detennines, each shall grant the
requested extension to the Developer, with such extension in writing. The date
for completion through Phase IV of the Schedule ofPerfonnance may be
extended by mutual agreement by the Developer and the Agencies for no more
than a total of two additional thirty day (30) day periods (for a total of a 60 day
extension to the Schedule of Perfonnance), in accordance with the foregoing
procedure. Each such extension shall also extend the ENA Tenn and the tenn to
complete Phase IV of the Master Development Planning Process for the period of
extension granted. The Parties agree that all two possible extensions established
in this Section 2.2.3 may be issued in accordance with the provisions ofthis
Section 2.2.3, notwithstanding any previous extensions issued by the Agencies
prior to the effective date of this Second Amendment.
(c) Section 2.2.5 of the First Amendment is hereby deleted in its entirety and
replaced with the following:
"It is the intent of the Parties to conclude exclusive negotiations and to complete
Phases I through IV of the Master Development Plan Process during the period
commencing on the Effective Date and tenninating on or before January 23, 2006,
as such date may be extended (a) pursuant to the provisions of Section 2.2.3 or
TUSTIN LEGACY MASTER DEV>ENA-v-l]
A-2
Exclusive Negotiation Agreement
(Master Development Site)
(b) following completion of Phase III of the Master Development Plan Process,
upon request by any Party, provided that in no event shall the total exclusive
negotiation period established by this Agreement be extended beyond March 24,
2006 without the prior written consent ofthe City Council and the Developer (as
extended, the "ENA Term"). This Agreement shall automatically tenninate upon
the last day of the ENA Tenn unless the Developer and the Agencies' staff have
agreed upon a fonn ofDDA acceptable to each as of said date."
(d) Exhibit "D" (Schedule ofPerfonnance) included in the First Amendment to the
ENA is hereby deleted in its entirety and replaced with the Schedule of Performance attached as
Schedule I hereto.
(d) The address ofSteefel, Levitt & Weiss set forth in Section 8.9 of the Prior ENA is
hereby deleted in its entirety and replaced with the following:
"Steefel, Levitt & Weiss
550 South Hope Street, Suite 2350
Los Angeles, CA 90071
Attn: Amy E. Freilich, Esq."
2. Counterparts. This Second ENA Amendment may be executed in any number of
counterparts each of which shall be deemed an original and all of which shall constitute one and
the same agreement with the same effect as if all the parties had signed the same signature page.
Any signature page of this Second ENA Amendment may be detached from any counterpart of
this Second ENA Amendment and reattached to any other counterpart of this Second ENA
Amendment identical in fonn hereto but having attached to it one or more additional signature
pages.
3. ENA Remains in Effect. Except as specifically provided in this Second ENA
Amendment, all of the tenns and provisions of the Prior ENA remain unchanged and in full force
and effect.
4. Effectiveness. This Second ENA Amendment shall be effective when it shall have been
executed and delivered by the Agencies and Developer.
TUSTIN LEGACY MASTER DEV>ENA-v-l]
A-3
Exclusive Negotiation Agreement
(Master Development Site)
IN WITNESS WHEREOF, the authorized representatives of the Parties hereto have
executed this Agreement as of the date first set forth above.
"CITY"
City of Tustin
By:
William Huston
City Manager
"AUTHORITY"
Tustin Public Financing Authority
By:
Name:
Its:
APPROVED AS TO FORM
Special Counsel for the City
STEEFEL, LEVITT & WEISS
By:
Amy E. Freilich, Esq.
TUSTIN LEGACY MASTER DEV>ENA-v-J]
A-4
Exclusive Negotiation Agreement
(Master Development Site)
TUSTIN LEGACY COMMUNITY
PARTNERS, LLC, a Delaware limited liability
company
By:
Centex Homes, a Nevada general
partnership, a Member
By:
Centex Real Estate Corporation,
a Nevada corporation,
Managing Partner
By:
Richard P. Douglas
Division President
TUSTIN LEGACY MASTER DEV>ENA-v-J]
A-5
By:
By:
Shea Homes Limited Partnership, a
California limited partnership, a
Member
By:
J.F. Shea LLC, a Delaware
limited liability company
By:
Jack Godard
Assistant Secretary
Shea Properties, LLC, a Delaware
limited liability company, a Member
By:
Jack Godard
Vice President - Manager
Assistant Secretary
Exclusive Negotiation Agreement
(Master Development Site)
TUSTIN LEGACY MASTER DEV>ENA-v-l]
A-6
Exclusive Negotiation Agreement
(Master Development Site)
SCHEDULE "1" TO SECOND AMENDMENT TO EXCLUSIVE NEGOTIA TION
AGREEMENT
EXHIBIT "D" TO EXCLUSIVE NEGOTIATION AGREEMENT
SCHEDULE OF PERFORMANCE
18403:6450161.2
EXHIBIT D
Second Amendment to Exclusive Negotiation Agreement
Between the City of Tustin, Public Financing Authority
And
Tustin Legacy Community Partners
Task Name Start Finish
ENA Phase 1 (Preliminary Master
Development Plan) 11/01/03 3/1/04
ENA Phase 2 ( Refine Plan, Infrastructure
and Prepare Preliminary
Business Plan) 3/1/04 5123/05
ENA Phase 3 (Finalize Master
Development Plan) 5/23/05 7/25/05
ENA Phase 4 (Negotiate and 7/26/05 1/23/06
Prepare Draft DDA)
. Negotiate Tenn Sheet 7/26/05 9/12/06
. Prepare Draft DDA 9113/05 1/23/06