HomeMy WebLinkAboutCUP 05-012
DATE:
TO:
FROM:
SUBJECT:
Inter-Com
AUGUST 29, 2005
ZONING ADMINISTRATOR
COMMUNITY DEVELOPMENT DEPARTMENT
CONDITIONAL USE PERMIT 05-012
APPLICANT:
PROPERTY
OWNER:
LOCATION:
ZONING:
DELTA ENVIRONMENTAL CONSULTANTS, INC.
ATTN: AARON BAIRD
27141 All SO CREEK ROAD, SUITE 270
ALiSO VIEJO, CA 92656
BP WEST COAST PRODUCTS, LLC
ATTN: DARRELL FAH
6 CENTERPOINT DRIVE
LA PALMA, CA 90623
14244 NEWPORT AVENUE
GENERAL COMMERCIAL (CG)
ENVIRONMENTAL
STATUS: THIS PROJECT HAS BEEN DETERMINED TO BE
CATEGORICALLY EXEMPT PURSUANT TO SECTION 15330
(CLASS 30) OF THE CALIFORNIA ENVIRONMENTAL QUALITY
ACT (CEQA).
AUTHORIZATION TO RE-ESTABLISH AN EXISTING
TEMPORARY SOIL REMEDIATION SYSTEM AT AN EXISTING
SERVICE STATION FOR TWO (2) YEARS.
REQUEST:
RECOMMENDATION
That the Zoning Administrator adopt Zoning Administrator Action No. 05-016 approving
Conditional Use Permit 05-012.
BACKGROUND
The project site is located at a gas station at 14244 Red Hill Avenue on the southeast
corner of Newport Avenue and Mitchell Avenue as identified on the Location Map
(Attachment A). The property is zoned as General Commercial (CG) and is currently used
as a gas station. Adjacent uses include commercial business immediately adjacent to the
Zoning Administrator Report
CUP 05-012
Page 2
south and east, single-family residences to the northeast and a fast-food restaurant to the
north across Mitchell Avenue, respectively, and a gas station, offices, and commercial
businesses to the west across Newport Avenue.
DISCUSSION
The applicant is requesting authorization to utilize an existing soil vapor extraction unit
previously approved per Conditional Use Permit (CUP) 92-012. CUP 92-012 authorized
construction of a temporary system to be installed within a fourteen (14) foot wide by
twenty-seven (27) foot long by six (6) foot high chain-link fence enclosure with wood slat
inserts (Attachment 8 - Submitted Plans). The equipment operation was approved to be
placed between the building and the south property line for twenty-four (24) months until
May 11, 1994. The equipment was not removed from the site and the property owner
requested an extension per CUP 01-023 until January 17, 2003, however, no remediation
occurred and the CUP expired. Planning Commission approval of CUP 05-012 would
extend the use of the system to twenty-four (24) months to complete the remediation. The
equipment would be removed upon completion of the remediation process at this site per
Condition 1.9.
The soil remediation equipment would be used twenty-four (24) hours a day, and the
service station would remain open while the equipment is in use. The equipment would be
located in the existing enclosure along the south property line per Condition 1 .11 and
would not encroach into any existing parking spaces or drive aisles. New wood slats
would be installed in the existing equipment per Condition 1.10. The equipment enclosure
is visible from Newport Avenue, however, since it is existing and would be removed within
two (2) years, it would not create an aesthetic impact. The applicant is requesting to
operate the soil remediation systems for up to two (2) years, pending final clearance from
the Orange County Health Care Agency (OCHCA).
Permit Requirements
In accordance with Tustin City Code Section 9270b(d), the removal of earth, other than
in connection with construction of buildings, roadways, or public or home improvements,
is allowed with the approval of a conditional use permit. Pursuant to Tustin City Code
(TCC) Section 9299(b)(4), the Zoning Administrator can approve conditional use permits
for groundwater and soil remediation operations for any length of time.
Soil Remediation Process
The soil remediation system consists of vapor extraction wells, extraction piping, a skid-
type PEGO blower, two (2) 500 pound granular activated carbon (GAC) vessels and three
(3) 400 pound GAC vessels. The soil remediation vacuums vapors from the on-site dry
wells and the hydrocarbon vapors contained in the air are blown through a series of tank
containing granular activated carbon. After the vapors are "cleaned" through the tanks, the
Zoning Administrator Report
CUP 05-012
Page 3
effluent vapor is released to the atmosphere in association with a Southern California Air
Quality Management District (SCAQMD) permit which requires filtering and threshold
monitoring. No soil is not unearthed for the soil remediation process, and pursuant to the
applicant's SCAQMD permit, all wells must be capped once the process is complete to
prevent any remaining hydrocarbons from escaping into the air.
Noise
The City's noise ordinance limits sound produced by the equipment to 60 decibels.
Condition 2.1 requires staff to obtain a decibel reading of the equipment to verify that it
produces no more than 60 decibels of noise. If the reading exceeds the threshold, the
Community Development Director may require the applicant to provide mitigation
measures and install sound insulation materials.
FINDINGS
A decision to approve this request may be supported by the following findings:
1)
The proposed soil vapor extraction equipment is necessary to facilitate soil
remediation required by the Orange County Health Care Agency.
2)
The installation and operation of extraction and treatment equipment would be
temporary for a period up to twenty-four (24) months and will be removed at that
time or earlier upon completion of the process.
3)
Removing contaminates from the soil would benefit the environment and protect
the health, safety, morals, comfort, and general welfare of persons residing or
working in the neighborhood and improve the condition of the property..
4)
The temporary equipment would be adequately housed within an existing
enclosure on the property to buffer the use with the adjacent commercial center,
that is located on the south side of the building opposite of the single-family
residential properties located northeast of the building across Mitchell Avenue.
The equipment would be required to comply with the Tustin Noise Ordinance; as
conditioned, the noise levels may be verified prior to final inspection and the
applicant required to install sound insulation materials or as deemed necessary by
the Community Development Director.
The location of the equipment would allow the service station to remain in
business during the remediation process. On-site parking or circulation,
including trash services, would not be affected since the equipment is located at
the rear of the lot and not within a drive aisle.
5)
Zoning Administrator Report
CUP 05-012
Page 4
6)
As conditioned, the use would be approved and monitored by the City of Tustin,
Orange County Health Care Agency, and the South Coast Air Quality
Management District.
It1 #Æ W ¿¡j:
Matt West
Associate Planner
Attachments:
A - Location Map
8 - Submitted Plans
C - Zoning Administrator Action No. 05-016
S:\Cdd\PCREPORT\2005\CUP 05-012 (Newport Ave. ARCO Remediation).doc
ATTACHMENT A
Location Map
LOCATION MAP
~.
-;
'~
00
Co
%
o,?-
-<7
-<7""
~.>:
~<S;
'1->--
PROJECT NO.
ADDRESS
CUP 05-012
LOCATION:
14244 Newport Avenue
REQUEST:
A request by Aaron Baird, on behalf of BP
West Coast Products, LLC, to establish a
temporary soil remediation system at an
existing service station for up to two (2) years.
The project is also known as the southeasterly
156 feet of "the northwesterly 185 feet of the
southwesterly 150 feet of the northeasterly 183
feet of Lot 48 . n block 11 of Irvine's
Subdivision, in the County of Orange, State of
California; as per map recorded in book 1,
Page 88 of Miscellaneous Record Maps, in the
office of county recorder of said county, and
further known as Assessor's Parcel Number
432-081-01. . The Zoning Administrator may
modify the request as a result of the public
hearing.
(Applicant: Aaron Baird
Owner: BP West Coast Products, LLC)
,
,
~
<~
ATTACHMENT B
Submitted Plans
B-22.
~~
~
~
~O
~
~
-<1~
1'"8-21
8-16
CHAINLINK
<I:) FENCE
SVE SYSTEM
ENCLOSURE
(E)
8-17.
8-20.
B-1~
LEGEND
8-21. GROUNDWATER MONITORING WELL LOCATlON
8-18" SOIL VAPOR EXTRACTlON WELL LOCAl TON
~
- N -
0 ~ 40'
I I
SCALE
~
HANDICAPPED PARKING AREA
FIGURE 2
SITE MAP
ARCO FACILl1Y NO. 1865
14244 NEWPORT AVENUE
TUSTIN, CA.
8-8 -9-
8-20 .
DESTROYED WELL LOCA TlON
EXPLORATORY SOIL BORING LOCA TlON
NOTES:
1.) UST = UNDERGROUND STORAGE TANK.
2.) WELLS RESURVEYED JANUARY 30. 2003.
3.) (E) = EXISTING
PROJECT NO. DRAWN BY
GOB79 K. MARTIN
FILE NO. PREPARED BY
AO- 71 8-05 C. BOERU
DATE REV. REVIEWED BY
20 JUN 05 D&B
SM
 De Ita
Environmental
~Â. Consultants, Inc.
\-
4[:
27'-0.
(E)
BOLLARDS
EXPLANATION:
(E) = EXISTING
-
-
0 B-6
0 B-7/B-2IB-4
0 B-5
0 B-18
(E)
PIPING
MANIFOLD
13'-9"
(E) 8' HIGH CHAIN
LINK FENCE W/WOOD
SLATS
PEGO SY$TEM BLOWER
PHASE I 60 Hz
230 VOLTS
SER# 3620
(MODEL 789031)
NOTES:
1.) EQUIPMENT LOCATIONS ARE APPROXIMATE.
2.) UPON COMPLETION OF SITE REMEDIATION
ENCLOSURE COMPOUND, BOLLARDS, AND EQUIPMENT
WILL BE REMOVED AND THE ENCLOSURE AREA WILL BE
RESTORED TO ITS ORIGINAL CONDITION.
-
-
(VAPOR)
EFFLUENT
VAPOR TO
ATMOSPHERE
3' HIGH BLOCK WALL
./
/'
SCALE: 1/4" = 1'-0"
FIGURE 3
EQUIPMENT LAYOUT PLAN VIEW
ARca FACILITY NO. 1865
14244 NEWPORT AVENUE
TUSTIN, CA.
PROJECT NO. DRAWN BY
GOB79 K. MARTIN
FILE NO. PREPARED BY
AO-718-04 C. BOERU
DATE REV. REVIEWED BY
16 JUN 05 D&B
 Delta
Environmental
~Â Consultants, Inc.
STD:~¿~OO-8Xl1AI INTL REF: I I
I
~.~
~x
no
10:::
lÜ~
I~
. «
1') '...../
PLAN
VIEW
4"
FNPT
D ¡VENT SCRUB I [ß] D
us; ¡fft~ff
ELEVATION
!
2'-6
3/8"
DIA
NOTES:
II'-JLET
4"
FNPT OUTLET
COMPANY CONFIDENTIAL
THIS DOCUMENT AND ALL INFORMATION CONTAINED
HEREIN ARE THE PROPERTY OF THE usmTER AND/OR
ITS AFFILIATES ("USF'). THE DESIGN CONCEPTS AND
INFORMATION CONTAINED HEREIN ARE PROPRIETARY
TO USF AND ARE SUB"'TTED IN CONFIDENCE. THEY
ARE NOT TRANSFERABLE AND "UST BE USED ONLY
FOR THE PURPOSE FOR WHICH THE DOCU"ENT IS
EXPRESSLY LOANED THEY "UST NOT BE DISCLOSED,
REPRODUCED, LOANED OR USED IN ANY OTHER
MANNER WITHOUT THE EXPRESS WRITTEN CONSENT
OF USF. IN NO EVENT SHALL THEY BE USED IN ANY
"ANNER DETRI"ENTAL TO THE INTEREST OF USF. ALL
3Z"
8
OF USF. THIS DOCU"ENT, ALONG WITH ALL COPIES
AND EXTRACTS, AND ALL RELATED NOTES AND
ANALYSES, MUST BE RETURNED TO USF OR ~'LE:
DESTROYED. AS INSTRUCTED BY USF. ACCEPTANCE OF
THE DElIVERY OF THIS DOCUMENT CONSTITUTES SCALE.
AGREEMENT TO THESE TERMS AND CONDITIONS. .
1.
CARBON:
AS REQUIRED.
MATERIALS OF CONSTRUCTION:
VESSEL: ..............
EXTERNAL COATING:
INTERNAL COATING:
INTERNAL DISTRIBUTION:
WESTATES BLUE
2
...CARBON STEEL
..HIGH GLOSS PAINT,
..CURED EPOXY
........PVC
3.
SPECIFICATIONS:
FLOW * - CFM (MAX):
PRESSURE - PSIG (MAX):
TEMPERATURE - DEG F (MAX):
CARBON FILL VOLUME - CU FT:
CROSS SECTION - SQ FT: ........
SHIPPING WEIGHT - LBS: (APPROX,)
OPERATING WEIGHT - LBS: (APPROX,) ..-.....
300
3
140
14.0
4.9
480
480
(SBV) AS REQUIRED FOR SPECIFIC CONTAMINANTS.
EXH / 6fT
A
DESIGNER
AJA
CHECKER
DATE I TITLE
11-2-01
DATE
~
DATE
~
8
VSC400
GENERAL ASSEMBLY
ENGINEER
MANAGER
DATE
II~----
,,~; if; ;-
USFIL TER/WE5TATES
RED BLUFF, CA
1-800-795-2664
-
0<
6'
V'
PROJECT
DRAWING
VSC400GENASSY.DWG
SHEET
1 OF 1
REV
u~----
=:--=.=.- --
- - ----- -
-------
= ====-=
Westates
11711 Reading Road
Red Bluff, CA 96080
Telephone (530) 527-2664
Facsimile (530) 527-8724
VSC400
Specification Summary
A~co IffGS
Exl+ibí¡ B
VSC400 Liquid Phase Adsorption Filter is designed to treat a wide range of contaminated
process streams, ease of handling and economical usage. This ad sorber is capable of
maximum flow rate of 300 CFM.
Data Summary:
Dimensions ................................................................................ 32" dia x 43" high
Carbon Capacity....................................................................................... 400 Ibs.
Carbon Bed Volume-Typical........................................................................ 14 Fe
Maximum Flow........................ ................. ........... .......... ............ .............300 CFM
Maximum Working Pressure.......................................................................... 3 psi
Maximum Operating Temperature..............................................................140 of
Material............................................................................................. Carbon Steel
Interior Surface Coating. ........................... ................................. .... ........ ...... Epoxy
Exterior Surface Coating.......................................................................... Enamel
Standard Color .... ................. .................... .......... ....................... .................... Blue
UNDERDRAIN:
Slotted pipe... ...........,............................................... .................................. 4" x 18" Pye
WEIGHT:
S hip pi ng....... .. . . . ... ... ..... .. ........... .. ... . .. .... .... ...... .... ....... .. .. .. .. .. .. .. ...... .. ...... . . . .. . 480 I b
0 perati ng . ...... .. ..,... ... ...... .... .. .. . . . . ........... . .. . ." .. .. ...... .. ........... .. .. .. . . . . .... ....... ...480 I b
2-2-04
Þrl(co
\~(Ôs
E:.AST \/\ evJ or ItEM~DiA-T10N COMPouND ~\-\QlA1iNG- E7Ù
c.\\h\~ \...\~K FéNCE.
ON Gr
.,..
A-R.CO I!G5
ViEW OF CoMPOUND FI<.OM Në().lPO/<..T /'rVENtlE
/t~co /165
View OF COMPOUt.Jð FROM MÍTcHE.LL AvE. (SOUTH
V iE-IV )
Åf.to \ ~GS
~oU\\\ E.AST \J\EW O~ ~6Me:~iA-nON COMPOU~b
ATTACHMENT C
Zoning Administrator Action No 05-016
ZONING ADMINISTRATOR ACTION 05-016
CONDITIONAL USE PERMIT 05-012
The Zoning Administrator of the City of Tustin does hereby resolve as follows:
I.
The Zoning Administrator finds and determines as follows:
A.
That a proper application for Conditional Use Permit 05-012 was filed
by Aaron Baird, on behalf of the Atlantic Richfield Company,
requesting authorization to temporarily operate a vapor extraction unit
to remove hydrocarbons from the soil under an existing gas station
located at 14244 Newport Avenue.
B.
In accordance with Tustin City Code Section 9270b(d), the removal
of earth is allowed with an approved conditional use permit in the
General Commercial (CG) Zoning District and within the Community
Commercial land use designation of the City of Tustin General Plan
which maintains a goal of revitalizing older commercial properties
such as contaminated gas stations. In accordance with Tustin City
Code (TCC) Section 9299(b)(4), the Zoning Administrator can
approve conditional use permits for soil remediation operations for
any length of time. In addition, the project has been determined to
be consistent with the Air Quality Sub-element of the City of Tustin
General Plan in that Policy 3.1 of the Sub-element encourages the
minimization of particulate emissions, and the proposed
remediation process is a much cleaner method than non-filtered
evaporation of hydrocarbon particulate into the air.
C.
That the establishment, maintenance, and operation of the use
applied for will not, under the circumstances of this case, be
detrimental to the health, safety, morals, comfort, or general welfare
of the persons residing or working in the neighborhood of such
proposed use nor be a detriment to the property and improvements in
the neighborhood of the subject property, nor to the general welfare
of the City of Tustin as evidenced by the following findings:
1)
The proposed soil vapor extraction equipment is necessary to
facilitate soil remediation required by the Orange County
Health Care Agency.
2)
The installation and operation of extraction and treatment
equipment would be temporary for a period up to twenty-four
(24) months and will be removed at that time or earlier upon
completion of the process.
Zoning Administrator Action 05-016
Conditional Use Permit 05-012
Page 2
D.
E.
3)
Removing contaminates from the soil would benefit the
environment and protect the health, safety, morals, comfort,
and general welfare of persons residing or working in the
neighborhood and improve the condition of the property.
4)
The temporary equipment would be adequately housed within
an enclosure on the property to buffer the use with the
adjacent commercial center, and would be on the south side of
the building opposite of the single-family residential properties
located northeast of the building across Mitchell Avenue. The
equipment would be required to comply with the Tustin Noise
Ordinance; as conditioned, the noise levels may be verified
prior to final inspection and the applicant required to install
sound insulation materials or as deemed necessary by the
Community Development Director.
5)
The location of the equipment would allow the service station
to remain in business during the remediation process. On-site
parking or circulation, including trash services, would not be
affected since the equipment is located at the rear of the lot
and not within a drive aisle.
6)
As conditioned, the use would be approved and monitored by
the City of Tustin, Orange County Health Care Agency, and
the South Coast Air Quality Management District.
This project is categorically exempt pursuant to Section 15330,
Article 19, Class 30 of Title 14, Chapter 3 of the California Code of
Regulations (Guidelines for the California Environmental Quality
Act).
That a public hearing was duly called, noticed, and held on said
application on August 29,2005, by the Zoning Administrator.
The Zoning Administrator hereby approves Conditional Use Permit No. 05-
012 authorizing the operation of temporary soil remediation equipment, for
. up to twenty-four (24) months within a temporary enclosure at an existing
gas station at 14244 Newport Avenue, subject to the conditions contained
within Exhibit A attached hereto.
II.
Zoning Administrator Action 05-016
Conditional Use Permit 05-012
Page 3
PASSED AND ADOPTED by the Zoning Administrator of the City of Tustin at a
regular meeting held on the 29th day of August 29, 2005.
Scott Reekstin
ACTING ZONING ADMINISTRATOR
Flor Williams
RECORDING SECRETARY
STATE OF CALIFORNIA)
COUNTY OF ORANGE)
CITY OF TUSTIN )
I, ELOISE HARRIS, the undersigned, hereby certify that I am the Recording
Secretary of the Zoning Administrator of the City of Tustin, California; that Zoning
Administrator Action No. 05-016 passed and adopted at a regular meeting of the
Tustin Zoning Administrator, held on the 29th day of August, 2005.
Flor Williams
RECORDING SECRETARY
GENERAL
(1 )
(1 )
(1 )
(1 )
(1 )
1.1
1.2
1.3
1.4
1.5
EXHIBIT A
CONDITIONS OF APPROVAL
CONDITIONAL USE PERMIT 05-012
The proposed project shall substantially conform with the submitted
plans for the project date stamped on August 29, 2005, on file with
the Community Development Department, as herein modified, or as
modified by the Director of Community Development Department in
accordance with this Exhibit.
This approval shall become null and void unless the use is
established within twelve (12) months of the date of this Exhibit.
Time extensions may be granted if a written request is received by
the Community Development Department within thirty (30) days
prior to expiration.
All conditions in this Exhibit shall be complied with prior to issuance
of permits, or as specified, subject to review and approval by the
Community Development Department.
Approval of Conditional Use Permit 05-012 is contingent upon the
property owner signing and returning to the Community Development
Department a notarized "Agreement to Conditions Imposed" form and
the property owner signing and recording with the County Clerk-
Recorder a notarized "Notice of Discretionary Permit Approval and
Conditions of Approval" form. The forms shall be established by the
Director of Community Development, and evidence of recordation
shall be provided to the Community Development Department.
As a condition of approval of Conditional Use Permit 05-012, the
applicant shall agree, at its sole cost and expense, to defend,
indemnify, and hold harmless the City, its officers, employees,
agents, and consultants, from any claim, action, or proceeding
brought by a third party against the City, its officers, agents, and
employees, which seeks to attack, set aside, challenge, void, or annul
an approval of the City Council, the Planning Commission, or any
other decision-making body, including staff, concerning this project.
The City agrees to promptly notify the applicant of any such claim or
action filed against the City and to fully cooperate in the defense of
any such action. The City may, at its sole cost and expense, elect to
participate in defense of any such action under this condition.
(1)
(2)
(3)
(4)
***
SOURCE CODES
STANDARD CONDITION
CEQA MITIGATION
UNIFORM BUILDING CODE(S)
DESIGN REVIEW
EXCEPTIONS
(5)
(6)
(7)
RESPONSIBLE AGENCY
REQUIREMENTS
LANDSCAPING GUIDELINES
PC/CC POLICY
Zoning Administrator Action 05-016
Conditional Use Permit 05-012
Exhibit A
Page 2
(1 )
(1 )
(*)
(*)
(*)
(*)
1.6
1.7
1.8
1.9
Any violation of any of the conditions imposed is subject to the
payment of a civil penalty of $100.00 for each violation, or such other
amounts as the City Council may establish by ordinance or
resolution, and for each day the violation exists, subject to the
applicable notice, hearing, and appeal process as established by the
City Council ordinance.
The applicant shall be responsible for costs associated with any
necessary code enforcement action, including attorney fees, subject
to the applicable notice, hearing, and appeal process as established
by the City Council by ordinance.
Conditional Use Permit 05-012 may be reviewed annually or more
often, if deemed necessary by the Community Development
Department, to ensure compatibility with the area and compliance
with the conditions contained herein.
The enclosure and all equipment shall be removed no later than
August 29, 2007, or upon completion of the remediation process
pursuant to clearance from the Orange County Health Care Agency
(OCHCA), whichever comes first. The property owner shall provide
the Community Development Director with the most current soil
remediation status report prepared for OCHCA.
1.10 Prior to building permit issuance, the applicant shall install all new
wood slats in the existing equipment fencing enclosure to ensure the
entire enclosure maintains a uniform and new appearance.
1.11
The entire remediation system, including storage drums and
equipment, shall be located in the entirely within the enclosure with
the gates closed.
USE RESTRICTIONS
(5)
(5)
2.1
2.2
Prior to final inspection, the Community Development Department,
Building Division shall obtain a decibel reading of the soil
remediation equipment to evaluate that the equipment produces no
more than 60 decibels of noise in compliance with Tustin City Code
Section 4614. If the reading determines that noise thresholds are
exceeded, the Community Development Director may require the
applicant provide mitigation measures and install sound insulation
materials. The applicant shall bear all associated costs.
Contaminated material may not leave the site except as described in
Condition 5.4. All necessary precautions and preventive measures
shall be in place to prevent material from being washed away by
Zoning Administrator Action 05-016
Conditional Use Permit 05-012
Exhibit A
Page 3
(5)
2.3
surface waters or blown by wind. These controls shall be in
accordance with AQMD Rule 1166.
All necessary precautions and preventive measures such as Best
Management Practices shall be implemented to prevent the flow of
contaminated water off-site. Contaminated water includes any water
from leaking wells or soil laden water from on-site construction
activity.
BUILDING DIVISION
(1 )
3.1
(5)
3.2
At the time of building permit application, the plans shall comply with
the 2001 California Building Code (CBC), 2001 California Mechanical
Code (CMC), 2001 California Plumbing Codes (CPC), 2001
California Electrical Code (CEC), California Title 24 Accessibility
Regulations, Title 24 Energy Regulations, City Ordinances, and State
and Federal laws and regulations.
Building plan check submittal shall include the following:
.
Seven (7) sets of construction plans, including drawings for
mechanical, plumbing and electrical.
.
Note on plans that no field changes shall be made without
prior approval from the Building Official and architect or
engineer of record.
Prior to issuance of a demolition and/or Building permit having
valuation of $50,000 or greater, the applicant shall submit for
approval by the City of Tustin, Construction & Demolition (C&D)
debris collection, disposal, and diversion information on the city
prescribed form.
At least 50% of the construction debris shall be diverted from
landfill to a recycling plant(s). A security deposit in amount of $50
per ton (not to exceed $5,000 per project) for a C&D security
deposit will be collected prior to issuance the permit. Prior to a final
inspection, the project proponent must submit documents to the
City of Tustin (i.e. receipt from vendor) showing the actual weight or
volume of each material of C&D diverted to the recycling center.
PUBLIC WORKS DEPARTMENT
(5)
4.1
During the life of the project, the applicant and/or property owner will
be required to repair any damage that the project causes to existing
street improvements and/or utilities.
Zoning Administrator Action 05-016
Conditional Use Permit 05-012
Exhibit A
Page 4
(5)
4.2
Prior to any work in the public right-of-way, an Encroachment Permit
needs to be obtained and applicable fees paid to the Public Works
Department.
OUTSIDE AGENCIES
(*)
5.1
(*)
5.2
(*)
5.3
(*)
5.4
The applicant shall obtain all necessary permits from the South Coast
Air Quality Management District (SCAQMD), related to the operation,
installation, and monitoring of the subject site and equipment.
The applicant shall obtain all necessary permits and approvals, if
applicable, from the Orange County Fire Authority and the Orange
County Health Care Agency related to the operation, installation, and
monitoring of the subject site and equipment.
The applicant shall obtain all necessary clearances from the State
Department of Occupational Safety and Health Administration.
All contaminated material being transported must be manifested and
may only be carried by a waste hauler licensed to transport the
material being hauled. A copy of the appropriate waste hauler permit
shall be provided to the City prior to transportation of hazardous
material off-site. Transportation of contaminated material and
hazardous materials shall be in accordance with the regulations of
the following agencies:
. United States Department of Transportation;
. United States Environmental Protection Agency;
. California Environmental Protection Agency; and,
. California Division of Occupational Safety and Health
Administration.
ORAN§.E COUlITY FIRE AUTHORJIYjOCFAl
(*)
6.1
FEES
(1 )
7.1
Prior to the issuance of a building permit, the applicant shall submit to
the Orange County Fire Authority for review and approval a plan
specific to the soil remediation. The service code for this review is a
2.41.
Prior to issuance of any building permits, payment shall be made of
all applicable fees, including but not limited to, the following.
Payment shall be required based upon those rates in effect at the
time of payment and are subject to change.
Zoning Administrator Action 05-016
Conditional Use Permit 05-012
Exhibit A
Page 5
a. Building plan check and permit fees to the Community
Development Department based on the most current schedule.
b. Within forty-eight (48) hours of approval of the subject project,
the applicant shall deliver to the Community Development
Department, a cashier's check payable to the COUNTY CLERK
in the amount of forty-three dollars ($43.00) to enable the City to
file the appropriate environmental documentation for the project.
If within such forty-eight (48) hour period that applicant has not
delivered to the Community Development Department the
above-noted check, the statute of limitations for any interested
party to challenge the environmental determination under the
provisions of the California Environmental Quality Act could be
significantly lengthened.