HomeMy WebLinkAbout05 AWARD CONTRACT FOR SIMON RANCH RESERVOIR (CIP NO. 60114)1�Y OAGENDA REPORT
MEETING DATE: FEBRUARY 18, 2020
TO: MATTHEW S. WEST, CITY MANAGER
Agenda Item
5
Reviewed:
^
City Manager
Finance Director
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: AWARD CONTRACT FOR THE SIMON RANCH RESERVOIR, BOOSTER PUMP
STATION, AND PIPELINE REPLACEMENT PROJECT (CIP NO. 60114)
SUMMARY
Staff is recommending that the City Council award the construction contract for the Simon Ranch
Reservoir, Booster Pump Station, and Pipeline Replacement Project (CIP No. 60114) to the
lowest responsive/responsible bidder, Pacific Hydrotech Corporation.
RECOMMENDATION
It is recommended that the City Council:
1. Award the construction contract for the Simon Ranch Reservoir, Booster Pump Station,
and Pipeline Replacement Project (CIP No. 60114) to the lowest responsive/responsible
bidder, Pacific Hydrotech Corporation, in the amount of $12,599,070.00 and authorize the
Mayor and the City Clerk to execute the contract documents on behalf of the City, and
2. Appropriate $776,200 from Operating Reserves (Fund 300), $5,974,800 from Capital
Reserves (Fund 301), and $289,000 from 2011 Water Bond Fund balance (Fund 305).
FISCAL IMPACT
The City's Fiscal Year 2019-2020 beginning reserve balance for all water funds is approximately
$20.6M and the City also has $9.5M of bond proceeds remaining. Currently, the City maintains 4
designated reserve funds including Operating Reserve, Capital Reserve, Rate Stabilization
Reserve, and Emergency Reserve. Based on the City's reserve policies the running balance
should be at least $8.2M for Fiscal Year 2019-2020. Although the City's reserve balance exceeds
this threshold as of July 1, 2019, the capital needs in Fiscal Year 2019-2020 will require the
planned use of reserves to fully fund the Simon Ranch Reservoir project, resulting in a reduction
in reserves.
The remaining available budget for the Simon Ranch Road Main Line Replacement Project (CIP
No. 60171) is $850,000 and for the Simon Ranch Reservoir and Booster Pump Station Project
(CIP No. 60114) is $8,110,000, for a total of $8,960,000 (2013 Water Bond, Fund 306). An
additional appropriation of $7,040,000 will be needed to bring the total budget for this project to
$16,000,000. Staff has identified available funding from Funds 300 (Operating Reserve), 301
(Capital Reserve) and 305 (2011 Water Bond) in the amounts of $776,200, $5,974,800 and
$289,000, respectively. The total estimated expenditure for the construction of this project is
$14,501,520.
Award Contract for the Simon Ranch Reservoir Project
February 18, 2020
Page 2
Project expenditures include:
• Construction Contract.............................................................$12,599,070
• Construction Management and Inspection................................$1,230,700
• Construction Engineering/Support ...............................................$390,000
• Geotechnical Engineering and Materials Testing .........................$170,750
• Certification Line/Grade & Deputy Inspection ................................ $50,000
• Environmental Compliance and Monitoring ................................... $36,000
• Utility Coordination Allowance....................................................... $25,000
Estimated Expenditures.......................................................$14,501,520
The remaining budgetary appropriation will be set aside as project contingency for potential
unforeseen conditions that may arise necessary to complete the work within the approved project
scope and budget.
Additionally, the City purchased two residential properties adjacent to the reservoir to facilitate
construction. The combined value of the properties is approximately $4,000,000. All proceeds
from the sale of the properties will be applied to the appropriate water fund.
CORRELATION TO THE STRATEGIC PLAN
The proposed project furthers Goal B of the City of Tustin Strategic Plan pertaining to Public
Safety and the Protection of Assets, in that the project will improve vital public facilities which
enhance Tustin's readiness in responding to fire and drought conditions.
DISCUSSION AND BACKGROUND
The Simon Ranch Reservoir, constructed in 1960, is located at the intersection of Valhalla Drive
and Outlook Lane within the unincorporated territory of Orange County. The existing Simon
Ranch Booster Pump Station, located at 11921 Simon Ranch Road, pumps water from Zone 1
into Zone 3, working in conjunction with the John Lyttle Reservoir. The City completed technical
studies of the existing reservoir and booster pump station in 1990, 1996, and 2000, and
determined that, due to age and the existing deteriorated condition, the Simon Ranch Reservoir
should be rehabilitated or replaced and that the Simon Ranch Booster Pump Station has reached
the end of its service life and should be replaced. The project will replace the existing buried,
gunite lined, earthen reservoir with a new circular, pre -stressed concrete tank. A new pump
station has been designed and integrated within the reservoir site. A portion of existing 8 inch
pipeline serving the existing booster station and 10 inch pipeline leading to the Simon Ranch
Reservoir will be abandoned and a new 16 inch ductile iron transmission pipeline, approximately
1,600 feet in length, will be constructed to feed both the new pump station and reservoir.
The City Council adopted Resolution No. 19-38 approving the plans and specifications and
authorized and directed the City Clerk to advertise for Project bids on August 20, 2019. The
Project was advertised and the bids were opened on October 15, 2019, and evaluated.
Three (3) bids were received by the noticed deadline and are summarized as follows:
Pacific Hydrotech Corporation ..............................................$ 12,599,070.00
Lonerock, Inc.................................................................... $ 14,850,600.00
Kiewit Infrastructure West Co ................................................$ 15,238,000.00
Award Contract for the Simon Ranch Reservoir Project
February 18, 2020
Page 3
Staff has reviewed the references and verified the State Contractor's License for Pacific
Hydrotech Corporation and has determined they are in good standing and current. Pacific
Hydrotech constructed the Edinger Avenue Well and Rawlings Reservoir projects. The quality of
both projects met the City's expectations and both were completed in timely manner.
It is recommended that the City Council award the construction contract to the lowest
responsive/responsible bidder, Pacific Hydrotech Corporation, and authorize the Mayor and the
City Clerk to execute the contract documents on behalf of the City.
ZDIa S. Stack, P.E.f Public Works/City Engineer
Attachment: Location Map
ALF
S�MON RANCH
Rogo
w
z
Q
J
W
z
Q
J
FLE: OP -6114.
CITY OF TUSTIN
P RP�G�O LAS cticF
S
NO SCALE
p
PROJECT LOCATION
�P
dp
O�
TU STI N HILLS
RACQUET CLUB
PROJECT NAME- SIMON RANCH RESERVOIR, BOOSTER PUMP STATION & PIPELINE REPLACEMENT PROJECT (CIP NO. 60t14)