HomeMy WebLinkAbout07 APPROVE PLANS AND SPECS FOR BENETA WELL NO. 2 - PHASE 1 DRILLING PROJECT DocuSign Envelope ID: D7F3131 B8-F671-4BAF-B089-C5AD160135C913 • Agenda Item 7 os AGENDA REPORT Reviewed. City Manager Finance Director MEETING DATE: SEPTEMBER 21, 2021 TO: MATTHEW S. WEST, CITY MANAGER FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER SUBJECT: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE ADVERTISEMENT FOR BIDS FOR THE BENETA WELL NO. 2 — PHASE I DRILLING PROJECT, CIP NO. 60151 SUMMARY The plans and specifications for the Beneta Well No. 2 — Phase I Drilling Project, CIP No. 60151, have been prepared and the project is now ready for bid. RECOMMENDATION It is recommended that the City Council: 1. Adopt Resolution No. 21-79 approving the plans and specifications for the Beneta Well No. 2 — Phase I Drilling Project, CIP No. 60151; and 2. Authorize the City Clerk to advertise to receive bids. FISCAL IMPACT Sufficient funds in the amount of $4,575,140 have been budgeted in the Capital Improvement Program for Fiscal Year 2021-22 for construction of both the drilling and equipping phases of the project. The preliminary estimate for the Phase I — Drilling Project is approximately $1.5 million, including Professional Hydrogeological Support Services during construction. The preliminary estimate for the Phase II — Equipping Phase is $3 million. The SARCCUP / OCWD grant of $1,575,140 will be applied to the overall construction costs, reducing the City's estimated project costs to approximately $2.9 million. This will be further refined as the drilling phase is completed and aquifer yield and ground water quality are assessed. CORRELATION TO THE STRATEGIC PLAN The project contributes to the fulfillment of the City's Strategic Plan Goal B: Public Safety and Protection of Assets. Specifically, the project implements Strategy 1, which among other items, is to ensure continuous maintenance and improvement of public facilities. In addition, Goal D: Foster strong relationships within the community, specifically, Strategy 2, enhance collaborative efforts with agencies within and outside Tustin on issues of mutual interest and concern. DISCUSSION AND BACKGROUND The Orange County Water District (OCWD), in partnership with Santa Ana Watershed Project Authority (SAWPA), was awarded $7,875,000 in Proposition 84 grant funds from the Department of Water Resources (DWR) for the Santa Ana River Conservation and Conjunctive Use Program (SARCCU P). These grant funds have been dedicated to construct five additional groundwater wells within the OCWD service boundaries. Tustin was selected to receive $1,575,140 in matching funds to assist in the construction of a new groundwater well. On February 2, 2021, the City Council DocuSign Envelope ID: D7F3131 B8-F671-4BAF-B089-C5AD160135C913 Beneta Well No. 2— Phase I Drilling Project September 21, 2021 Page 2 approved a contract entitled "Contract Between Orange County Water District and the City of Tustin Regarding Construction of Wells for Santa Ana River Conservation and Conjunctive Use Program (SARCCUP) Water Bank". The scope of work of the drilling phase includes site preparation, borehole drilling, geophysical logging, isolated aquifer zone testing, borehole reaming, casing installation, gravel envelope installation, annular seal installation, well development, and completion of the well head. The proposed well will be drilled in two passes (i.e. pilot borehole and reamed borehole) using the fluid reverse circulation rotary drilling method with installation of a gravel envelope to stabilize the formation materials. A 17.5-inch diameter pilot borehole will be drilled to an estimated total depth of 1,030 feet. Once the pilot borehole has been drilled, a suite of geophysical logs will be obtained. Isolated aquifer zone testing will then be performed, the results of which will be used to quantify aquifer yield and groundwater quality. This data will be instrumental for preparation of the final well design such that the best possible groundwater quality can be achieved. Production rates for the proposed well are expected to range from approximately 1,500 gallons per minute (gpm) to 2,000 gpm. Drilling, construction, development, and testing of the well will require approximately 120 calendar days to complete. During that period of time, several phases of the work will require 24-hour continuous operations on the part of the drilling contractor. The number of work days required for each major phase of well installation, and the nature of that work (i.e., 24-hour or daylight only) is summarized below. Residents adjacent to the site and the Tustin Unified School District are being notified of the project and potential impacts. Road closures are not expected, but the north sidewalk on Beneta Way may be closed intermittently. Major Task Duration Daily Schedule Drilling Permit 10 N/A Install Sound Walls 7 Daylight Only Conductor Casing Installation 2 Daylight Only Mobilization 5 Daylight Only Pilot Borehole Drilling 5 24-Hour Continuous Isolated Aquifer Zone Testing 10 24-Hour Continuous Final Well Design 10 N/A Borehole Reaming 5 24-Hour Continuous Well Construction 4 24-Hour Continuous DocuSign Envelope ID: D7F3131 B8-F671-4BAF-B089-C5AD160135C913 Beneta Well No. 2— Phase I Drilling Project September 21, 2021 Page 3 Initial Well Development 5 24-Hour Continuous Demobilization of Drilling Rig/ 8 Daylight Only Mobilization of Test Pump & Motor Final Development 6 Daylight Only Step Drawdown Aquifer Test 1 Daylight Only 24-Hour Constant Rate Aquifer Test 2 24-Hour Continuous Demobilize Test Pump and Motor 3 Daylight Only Plumbness and Alignment Surveys 2 Daylight Only Gyroscopic&Video Surveys 1 Daylight Only Well Disinfection 1 Daylight Only Site Cleanup and Restoration 5 Daylight Only The tentative schedule for construction of this project is as follows: • Authorization to Advertise for Bids.................................................................... 09/21/2021 • First Legal Advertisement.................................................................................. 09/23/2021 • Second Legal Advertisement............................................................................ 09/30/2021 • Bid Opening....................................................................................................... 10/26/2021 • Award of Contract.............................................................................................. 11/16/2021 • Start Construction...........................................................................................January 2022 • Complete Construction........................................................................................April 2022 A thorough environmental review and consultation with the City Attorney's Office determined the project is Categorically Exempt under California Environmental Quality Act(CEQA) requirements. A Notice of Exemption, prepared in accordance with Section 15303, has been recorded with the County of Orange. ,i V s . Stack, P.E. of Public Works/City Engineer Attachment(s): 1. Resolution No.21-79 2. Location Map DocuSign Envelope ID: D7F3131 B8-F671-4BAF-B089-C5AD160135C913 ATTACHMENT 1 Resolution No. 21-79 DocuSign Envelope ID: D7F3131 B8-F671-4BAF-B089-C5AD160135C913 RESOLUTION NO. 21-79 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA APPROVING PLANS AND SPECIFICATIONS FOR THE BENETA WELL NO. 2—PHASE I DRILLING PROJECT, CIP NO. 60151, AND AUTHORIZING ADVERTISEMENT FOR BIDS WHEREAS, it is the intention of the City Council of the City of Tustin, California to contract for the construction of the Beneta Well No. 2 — Phase I Drilling Project, CIP No. 60151; and WHEREAS, the City Engineer has presented plans and specifications for the construction of said work; and WHEREAS, the CIP No. 60151 project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA); Class 1, Section 15303: New Construction or Conversion of Small Structures; NOW, THEREFORE, BE IT RESOLVED that the plans and specifications presented by the City Engineer are hereby approved as the plans and specifications for: Beneta Well No. 2 — Phase I Drilling Project CIP No. 60151 BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to advertise as required by law for the receipt of sealed bids or proposals for the performance of the work specified in the aforesaid plans and specifications; PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin held on the 21 st day of September, 2021. LETITIA CLARK Mayor ATTEST: ERICA N. YASUDA City Clerk DocuSign Envelope ID: D7F3131 B8-F671-4BAF-B089-C5AD160135C913 STATE OF CALIFORNIA ) COUNTY OF ORANGE ) SS CITY OF TUSTIN ) I, Erica N. Yasuda, City Clerk and ex-officio Clerk of the City Council of the City of Tustin, California, do hereby certify that the whole number of the members of the City Council is five; that the above and foregoing Resolution No. 21-79 was duly and regularly passed and adopted at a regular meeting of the City Council held on the 21 st day of September, 2021 by the following vote: COUNCILMEMBER AYES: COUNCILMEMBER NOES: COUNCILMEMBER ABSTAINED: COUNCILMEMBER ABSENT: ERICA N. YASUDA City Clerk DocuSign Envelope ID: D7F3131 B8-F671-4BAF-B089-C5AD160135C913 ATTACHMENT 2 Location Map DocuSign Envelope ID:D71`3131 38-1`671-413AF-13089-05AD1 60135C913 CITY OF TUSTIN PARK I I "I H I I I I I I H I ` ■ NORWOOD PARK ■ z� ■ MAR-MA ANNE DR. ■ No scut 3 PROJECT a I WARREN Y LOCATION 0 DR. i444 LINNGSrON ■ T=rw r WELL ■ N •4N I 5 W FIT I TT-1 I U - I Z> LUCERO y�Y, FmTFFZ ED WY. ■ Q ■ AMAGANSET WY. NI O.C.F.C.D. R NORTH TUSTIN C1.HANNEL I I Z BENETA ILI: ■COLUMBUS i 7US77N WFLLWESTBURY LN. ZLEON WY. o w a d PLAZA WY 0 COLUMBUS TUSTIN 5 w z z ■ a MILLER DR. a = 21 A ■ ga / COLUMBUS I C 7Z/STIN uLUAN PARK ■ IRVINE BOULEVARD z w D z w NGEWOOD LN. 3 Q I O �� a WOOD P RK PL < 11111111 4 \% RE:RE: II PROJECT NAME: BENETA WELL NO. 2 - PHASE I DRILLING PROJECT(CIP NO. 60151)