ZONING ADMINISTRATOR ACTION 99-010
CONDITIONAL USE PERMIT 99-025
The Zoning Administrator of the City of Tustin does hereby resolve as follows:
\. The Zoning Administratorfinds and determines as follows:
A. That a proper application for Conditional Use Permit 99-025 was filed by
Dale Dillon, County of Orange Public Facilities & Resources Department,
requesting authorization to temporarily store quarry rock at the southwest
corner of Harvard and the OCTAl SCRRA Railway for use in repairing the
Orange County Flood Control Channel for a maximum of six months.
B. Pursuant to City Code Section 9299b(3), the Zoning Administrator has the
authority to approve a temporary use not to exceed six months through a
conditional use permit.
C. That a public hearing was duly called, noticed and held on said application
on November 8, 1999 by the Zoning Administrator.
D. That the establishment, maintenance and operation off the use applied for
will not, under the circumstances of this case, be detrimental to the health,
safety, morals, comfort, or general welfare of the persons residing or
working in the neighborhood of such proposed use, nor be injurious or
detrimental to the property and improvements in the neighborhood of the
subject property, or to the general welfare of the City of Tustin, as
evidenced by the following findings:
1) The proposed temporary use, as conditioned, will not be
detrimental to the surrounding properties in that storage of the
quarry rocks will not result in erosion or excessive dust.
2) As conditioned, the use will not have a negative effect on the
surrounding property owners, in that there will not be
excessive truck traffic on Harvard.
3) As conditioned, the use will terminate within six months.
E. That this project is Categorically Exempt from the requirements of the
California Environmental Quality Act, pursuant to Section 15301 (Class 1).
F. That the project has been reviewed for consistency with the Air Quality Sub-
element of the City of Tustin General Plan and has been determined to be
consistent with the Air Quality Sub-element.
Zoning Administrator Act. _.,99-010
Conditional use Permit 99-025
November 15, 1999
Page 2
2 II.
The Zoning Administrator hereby approves Conditional Use Permit No. 99-025
authorizing the temporary storage of quarry rocks at the southwest corner of
Harvard and the OCTAl SCRRA Railway for a period of six months, subject to the
conditions contained within Exhibit A, attached hereto.
3
4
5
PASSED AND ADOPTED by the Zoning Administrator of the City of Tustin at a regular
meeting held on the 15th day of November, 1999.
6
7
10
a~xL ~~~
ELIZABETH A. B1NSACK
Zoning Administrator
8
9
11
12
13
STATE OF CALIFORNIA)
COUNTY OF ORANGE )
CITY OF TUSTIN )
14
15
I, KATHY MARTIN, the undersigned, hereby certify that I am the Recording Secretary of
the Zoning Administrator of the City of Tustin, California; that Zoning Administrator Action
No. 99-010 passed and adopted at a regular meeting of the Tustin Zoning Administrator,
held on the 15th day of November, 1999.
16
17
18~
19 KA~A~)
20 Recording Secretary
21
22
23
24
25
26
27
28
29
EXHIBIT A
ZONING ADMINISTRA TORACTION 99-010
CONDITIONS OF APPROVAL
CONDITIONAL USE PERMIT 99-025
GENERAL
(1) 1.1 The proposed use shall substantially conform with the submitted plans for
the project date stamped November 8, 1999, on file with the Community
Development Department, except as herein modified, or as modified by the
Director of Community Development in accordance with this Exhibit. The
Director of Community Development may also approve minor modifications
to plans during plan check if such modifications are to be consistent with the
provisions of the Tustin City Code and other applicable codes.
(1) 1.2 Approval of Conditional Use Permit 99-025 is contingent upon the applicant
signing and returning an "Agreement to Conditions Imposed" form as
established by the Director of Community Development.
(1) 1.3 The applicant shall hold harmless and defend the City of Tustin from all
claims and liabilities arising out of a challenge of the City's approval of this
project.
USE RESTRICTIONS
(1) 2.1 The Temporary Use approved under this Conditional Use Permit shall
expire six (6) months from November 8, 1999. The applicant shall remove
all quarry rock and equipment by May 9, 1999.
(1) 2.2 All operations, including engine warm-up, and deliveries and pick-up of
materials and equipment, shall be subject to the provisions of the Tustin
Noise Ordinance and shall take place only between the hours of 7:00 a.m.
and 6:00 p.m., Monday through Friday, and between 9:00 a.m. and 5:00
p.m. on Saturday, unless otherwise determined by the Building Official.
(1) 2.3 No more than 5,000 tons of quarry rock and one (1) loader may be stored
on the site at one time.
(1) 2.4 The applicant shall install a band of gravel material at the exit of the site
and shall clean Harvard Avenue daily. The applicant shall prevent all dirt,
erosion, and sediment from leaving the site and entering the storm drain
system by performing best management practices in accordance with the
Caltrans Storm Water Quality Handbook.
(1) 2.5 The applicant shall coordinate with the Cities of Tustin and Irvine to obtain
an overload transportation permit for the use of Harvard Avenue if loads
exceed restricted weight limits.