HomeMy WebLinkAbout09 APPROVE PLANS AND SPECS FOR THE ANNUAL ROADWAY REHABILITATIONDocuSign Envelope ID: 1E4DOB21-EOA5-43C8-9C4C-746F4B204097
• Agenda Item 9
AGENDA REPORT Reviewed: L
X5W
City Manager DS
Finance Director �a
MEETING DATE: MARCH 1, 2022
TO: MATTHEW S. WEST, CITY MANAGER
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE
ADVERTISEMENT FOR BIDS FOR THE ANNUAL ROADWAY REHABILITATION
AND SIDEWALK REPAIR PROJECT - ZONE 3, CIP NO. 70021
SUMMARY
The plans and specifications for the Annual Roadway Rehabilitation and Sidewalk Repair Project for
Zone 3 (CIP No. 70021) have been prepared and the project is now ready for bid.
RECOMMENDATION
It is recommended that the City Council:
1. Adopt Resolution No. 22-08 approving the plans and specifications for the Annual
Roadway Rehabilitation and Sidewalk Repair Project - Zone 3, (CIP No. 70021), and
authorize the City Clerk to advertise to receive bids; and
2. Appropriate $630,000 from the Measure M2 Fund (Fund139) for sidewalk repairs and
$1,700,000 from the General Fund - Capital Improvement Program (Fund 200) for
roadway repairs to meet the City's Measure M2 Maintenance of Effort (MOE)
obligation.
FISCAL IMPACT
This project is part of the City's on-going Maintenance of Effort (MOE) obligation to maintain eligibility
for Measure M2 funding. The City's MOE benchmark for FY 2022-2023 is $1,697,045.
It has been the City's practice to appropriate all necessary funding prior to awarding contracts for
construction. The engineer's estimate for the project is $2,230,000 and staff anticipates and
additional $100,000 will be needed for geotechnical and survey work as well as tree removal and
replacement. Funding for sidewalk repair, geotechnical, survey and tree related work is provided
through the City's Measure M2 Fair Share allocation (Fund 139) and pavement rehabilitation through
the General Fund - Capital Improvement Program (Fund 200). Staff expects most of the sidewalk
repair will occur prior to June 30, 2022 and will be reflected in FY 2021-2022 expenses. Roadway
rehabilitation will occur after July 1, 2022 and will be reflected in FY 2022-2023 expenses.
Staff requested a mid -year appropriation for this capital improvement project for related consultant
services and the annual Street Striping and Pavement Marking program. The funding request
outlined in this agenda report is specifically for the construction of roadway and sidewalk
improvements.
CORRELATION TO THE STRATEGIC PLAN
Rehabilitation of roadways and repair of sidewalks contributes to the fulfillment of the City's Strategic
Plan Goal B: Public Safety and Protection of Assets. Specifically, the project implements Strategy
DocuSign Envelope ID: 1E4DOB21-EOA5-43C8-9C4C-746F4B204097
Annual Roadway Rehabilitation and Sidewalk Repair Project
March 1, 2022
Page 2
#5, which among other items, is to ensure continuous maintenance and improvement of
transportation facilities.
DISCUSSION AND BACKGROUND
The Annual Roadway Rehabilitation and Sidewalk Repair Project, Zone 3 CIP No. 70021 includes
asphalt concrete pavement repair, asphalt concrete overlay, slurry sealing, and traffic striping on
various streets throughout the City within Zone 3 of the City's Pavement Management Program. The
City is divided into seven pavement management zones with one zone targeted each year for
pavement maintenance. Through a rolling seven-year cycle, this program is intended to maintain
the integrity of City streets. The current phase, Zone 3 (see attached map), is generally bounded by
Irvine Boulevard to the north, Browning Avenue to the east, Interstate Freeway 5 to the south and
Newport Avenue to the west.
Measure M2 Ordinance No. 3 requires each City to maintain a minimum level of General Fund
expenditure for the maintenance of local streets and roads to meet Maintenance of Effort (MOE)
obligations. The City's FY 2022-23 MOE benchmark is $1,697,045. The scope of work has been
established to ensure final expenditures are above this benchmark and that the City's eligibility to receive
Measure M2 funding is not compromised.
CIP No. 70021 also includes the Annual Sidewalk Repair Project which focuses on removal and
replacement of damaged sidewalk at numerous locations in Zone 3 based on an annual field survey
conducted by the Engineering Division. The field survey identifies and evaluates locations where
tree roots are causing sidewalk and curb and gutter damage. Under the project, some of these trees
will be removed and replaced with trees of an acceptable species more suitable to the parkway area
as recommended by the City's Certified Arborist. This project also provides improvements
throughout the City to comply with the Americans with Disabilities Act (ADA). These locations are
typically requested by citizens or are identified by City staff to provide repair to existing pedestrian
access.
The tentative schedule for construction of this project is as follows:
• Authorization to Advertise for Bids ...............
• First Legal Advertisement .............................
• Second Legal Advertisement .......................
• Bid Opening .................................................
• Award of Contract ........................................
• Start Construction ........................................
• Complete Construction .................................
.......................................... 03/1/2022
.......................................... 03/3/2022
.......... I ............................. 03/10/2022
........................................ 03/29/2022
........................................ 04/19/2022
.......................................... May 2022
............. ...... I........... September 2022
Since this project involves the replacement and repair of existing facilities with minor modifications,
it is Categorically Exempt under California Environmental Quality Act (CEQA) requirements. A
Notice of Exemption has been prepared for the project, and will be recorded with the County of
Orange.
1# S. tack, P. E.
(oi gr Public Works/City Engineer
Attachment(s):
1. Resolution No. 22-08
2. Location Map
DocuSign Envelope ID: 1E4DOB21-EOA5-43C8-9C4C-746F4B204097
ATTACHMENT 1
Resolution No. 22-08
DocuSign Envelope ID: 1E4DOB21-EOA5-43C8-9C4C-746F4B204097
RESOLUTION NO. 22-08
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA
APPROVING PLANS AND SPECIFICATIONS FOR THE ANNUAL ROADWAY
REHABILITATION AND SIDEWALK REPAIR PROJECT - ZONE 3, CIP NO. 70021 AND
AUTHORIZING ADVERTISEMENT FOR BIDS
WHEREAS, it is the intention of the City Council of the City of Tustin, California to
contract for the construction of the Annual Roadway Rehabilitation and Sidewalk Repair Project
- Zone 3 CIP No. 70021; and
WHEREAS, the City Engineer has presented plans and specifications for the
construction of said work; and
WHEREAS, the CIP No. 70021 project is categorically exempt from the requirements of
the California Environmental Quality Act (CEQA); Class 1, Section 15301: Existing Facilities;
and
NOW, THEREFORE, BE IT RESOLVED that the plans and specifications presented by
the City Engineer are hereby approved as the plans and specifications for:
FY 2021-2022 Annual Roadway Rehabilitation and Sidewalk Repair Project — Zone 3
CIP No. 70021
BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to
advertise as required by law for the receipt of sealed bids or proposals for the performance of
the work specified in the aforesaid plans and specifications;
PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin
held on the 1 st day of March, 2022.
AUSTIN LUMBARD
Mayor
ATTEST:
ERICA N. YASUDA
City Clerk
DocuSign Envelope ID: 1E4DOB21-EOA5-43C8-9C4C-746F4B204097
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS
CITY OF TUSTIN )
I, Erica N. Yasuda, City Clerk and ex -officio Clerk of the City Council of the City of Tustin,
California, do hereby certify that the whole number of the members of the City Council is five;
that the above and foregoing Resolution No. 22-08 was duly and regularly passed and adopted
at a regular meeting of the City Council held on the 1 I day of March, 2022 by the following vote:
COUNCILMEMBER AYES:
COUNCILMEMBER NOES:
COUNCILMEMBER ABSTAINED:
COUNCILMEMBER ABSENT:
ERICA N. YASUDA
City Clerk