HomeMy WebLinkAbout08 APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE ADVERTISEMENT FOR BIDS FOR THE BENETA WELL NO. 2 – PHASE II EQUIPPING PROJECT, CIP NO. 60151DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
AGENDA REPORTAgenda Reeweldm 8
v
DS
City Manager
Finance Director Sa
MEETING DATE: JUNE 7, 2022
TO: MATTHEW S. WEST, CITY MANAGER
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE
ADVERTISEMENT FOR BIDS FOR THE BENETA WELL NO. 2 — PHASE II
EQUIPPING PROJECT, CIP NO. 60151
SUMMARY
The plans and specifications for the Beneta Well No. 2—Phase 11 Equipping Project, CIP No. 60151,
have been prepared and the project is now ready for bid.
RECOMMENDATION
It is recommended that the City Council:
1. Adopt Resolution No. 22-30 approving the plans and specifications for the Beneta Well
No. 2 — Phase II Equipping Project, CIP No. 60151; and
2. Authorize the City Clerk to advertise to receive bids.
FISCAL IMPACT
The FY 2021-22 Capital Improvement Program budget includes $5,061,802 for construction of both
the drilling and equipping phases of the project and is broken down as follows.
Phase I — Drilling Phase including Professional Hydrogeological Support Services $2,100,000
Phase II — Equipping Phase $3,500,000
Total $5,600,000
To fully fund Phase II of the project and ensure sufficient project contingency, the remaining
budgetary appropriation from Phase I is being carried over into FY 2022-23. As part of the FY 2022-
23 budget, staff is requesting an additional $1,000,000 be appropriated for this project in the Capital
Improvement Program budget.
The project is partially funded through a SARCCUP / OCWD grant in the amount of $1,575,140.
Information regarding the grant is provided later in this report. Full grant reimbursement will be
submitted immediately following the completion of Phase I.
CORRELATION TO THE STRATEGIC PLAN
The project contributes to the fulfillment of the City's Strategic Plan Goal B: Public Safety and
Protection of Assets. Specifically, the project implements Strategy 1, which among other items, is to
ensure continuous maintenance and improvement of public facilities. In addition, Goal D: Foster
strong relationships within the community, specifically, Strategy 2, enhance collaborative efforts with
agencies within and outside Tustin on issues of mutual interest and concern.
DocuSign Envelope ID: 79268798-7820-44CD-A6D2-5682707D1ADA
Beneta Well No. 2 — Phase II Equipping Project
June 7, 2022
Page 2
DISCUSSION AND BACKGROUND
The Orange County Water District (OCWD), in partnership with Santa Ana Watershed Project
Authority (SAWPA), was awarded $7,875,000 in Proposition 84 grant funds from the Department of
Water Resources (DWR) for the Santa Ana River Conservation and Conjunctive Use Program
(SARCCUP). These grant funds have been dedicated to construct five additional groundwater wells
within the OCWD service boundaries. Tustin was selected to receive $1,575,140 in matching funds
to assist in the construction of a new groundwater well. On February 2, 2021, the City Council
approved a contract entitled "Contract Between Orange County Water District and the City of Tustin
Regarding Construction of Wells for Santa Ana River Conservation and Conjunctive Use Program
(SARCCUP) Water Bank".
Construction of the Phase I Drilling Project is under way and is anticipated to be completed in July
2022. The scope of work of the Phase II Equipping Project includes construction of a concrete block
building to house the well; installation of a vertical turbine pump, motor and associated piping;
electrical equipment; construction of a pump to waste settling basin with discharge pipe to the
OCFCD flood channel; piping and fittings; chlorination facility; drainage of the site; landscaping and
irrigation; paving; motorized gate and accessories; connections to existing utilities; permits; and
disinfection and startup.
The tentative schedule for construction of this project is as follows:
• Authorization to Advertise for Bids....................................................................
06/07/2022
• First Legal Advertisement..................................................................................
06/09/2022
• Second Legal Advertisement.............................................................................
06/16/2022
• Bid Opening.......................................................................................................07/12/2022
• Award of Contract..............................................................................................
08/02/2022
• Start Construction.....................................................................................
September 2022
• Complete Construction..................................................................................
October 2023
A thorough environmental review and consultation with the City Attorney's Office determined the
project is Categorically Exempt under California Environmental Quality Act (CEQA) requirements. A
Notice of Exemption, prepared in accordance with Section 15303, has been recorded with the County
of Orange.
trAI s . Stack, P.E.
ec of Public Works/City Engineer
Attachment(s):
1. Resolution No. 22-30
2. Location Map
DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
ATTACHMENT 1
Resolution No. 22-30
DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
RESOLUTION NO. 22-30
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA
APPROVING PLANS AND SPECIFICATIONS FOR THE BENETA WELL NO. 2 —
PHASE II EQUIPPING PROJECT, CIP NO. 60151, AND AUTHORIZING
ADVERTISEMENT FOR BIDS
WHEREAS, it is the intention of the City Council of the City of Tustin, California to contract
for the construction of the Beneta Well No. 2 — Phase II Equipping Project, CIP No. 60151; and
WHEREAS, the City Engineer has presented plans and specifications for the construction
of said work; and
WHEREAS, the CIP No. 60151 project is categorically exempt from the requirements of
the California Environmental Quality Act (CEQA); Class 1, Section 15303: New Construction or
Conversion of Small Structures;
NOW, THEREFORE, BE IT RESOLVED that the plans and specifications presented by
the City Engineer are hereby approved as the plans and specifications for:
Beneta Well No. 2 — Phase II Equipping Project
CIP No. 60151
BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to
advertise as required by law for the receipt of sealed bids or proposals for the performance of the
work specified in the aforesaid plans and specifications;
PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin
held on the 7th day of June, 2022.
AUSTIN LUMBARD
Mayor
ATTEST:
CARRIE WOODWARD
Acting City Clerk
DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS
CITY OF TUSTIN )
I, Carrie Woodward, Acting City Clerk and ex -officio Clerk of the City Council of the City of Tustin,
California, do hereby certify that the whole number of the members of the City Council is five; that
the above and foregoing Resolution No. 22-30 was duly and regularly passed and adopted at a
regular meeting of the City Council held on the 71" day of June, 2022 by the following vote:
COUNCILMEMBER AYES:
COUNCILMEMBER NOES:
COUNCILMEMBER ABSTAINED:
COUNCILMEMBER ABSENT:
CARRIE WOODWARD
Acting City Clerk
DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
ATTACHMENT 2
Location Map
DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
CITY OF TUSTIN
PROJECT NAME: BENETA WELL NO. 2 - PHASE 11 EQUIPPING PROJECT (CIP NO. 60151)