HomeMy WebLinkAbout09 ADOPT RESOLUTION NO 22-31 APPROVING PROJECT LIST TO BE SUBMITTED TO THE CALIF TRANSPORTATION COMMISSDocuSign Envelope ID: 79268798-7820-44CD-A6D2-5682707D1ADA
AGENDA REPORT Reeewedm 9
DS
nB
City Manager
Finance Director Sa
MEETING DATE: JUNE 7, 2022
TO: MATTHEW S. WEST, CITY MANAGER
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS / CITY ENGINEER
SUBJECT: ADOPT RESOLUTION NO. 22-31 APPROVING PROJECT LIST TO BE
SUBMITTED TO THE CALIFORNIA TRANSPORTATION COMMISSION FOR
SB1 FUNDING FOR FISCAL YEAR 2022/23
SUMMARY
In order to be eligible to receive new funding under Senate Bill 1 (SB1), the City is required to submit
a Project List to the California Transportation Commission (CTC) no later than July 1, 2022.
RECOMMENDATION
Staff recommends the City Council:
1. Adopt Resolution No. 22-31 identifying projects to be submitted to the California
Transportation Commission for SB 1 funding; and
2. Direct staff to submit the Project List to the California Transportation Commission on
behalf of the City.
FISCAL IMPACT
Submittal of the Project List to the CTC allows the City to receive funding for maintenance,
rehabilitation, and safety related roadway projects. The current estimated revenue for Fiscal Year
2022-23 is approximately $1,823,778.
CORRELATION TO THE STRATEGIC PLAN
The recommended actions contribute to the fulfillment of the City's Strategic Plan Goal B, Public
Safety and Protection of Assets, ensuring that Tustin is an attractive, safe and well maintained
community in which people feel pride.
DISCUSSION
On April 28, 2017 the Governor signed SB1, which is known as the Road Repair and Accountability
Act of 2017 to address basic road maintenance, rehabilitation and critical safety needs on both the
state highway and local streets and road system.
Beginning November 1, 2017, the State Controller began depositing various portions of this new
funding into the newly created Road Maintenance and Rehabilitation Account (RMRA). A
percentage of this new RMRA funding is being apportioned by formula to eligible cities and counties
for basic road maintenance, rehabilitation, and critical safety projects on the local streets and roads
system. The City is required to adopt a Project List by resolution and submit to the CTC annually by
July 1 st for the upcoming fiscal year.
DocuSign Envelope ID: 7926879B-7B20-44CD-A6D2-5682707D1ADA
Adopt Resolution 22-31: Senate Bill 1 — Project List
June 7, 2022
Page 2
The attached Resolution No. 22-31 includes a list of previously approved and adopted projects that
may utilize FY 2022-23 RMRA revenues in their delivery that will be submitted to the CTC for review.
A list of eligible cities and counties will be adopted by the CTC in June and subsequently submitted
to the State Controller. It is expected that the Controller will continuously apportion RMRA funds on
a monthly basis.
Stack, P.E.
Public Works/City Engineer
Attachment 1: Resolution No. 22-31
S:\City Council Items\2022 City Council Items\06-07-2022\SB1 Project List\SBI Project List - Agenda Report.docx
DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
RESOLUTION NO 22-31
RESOLUTION ADOPTING A LIST OF PROJECTS FOR
FISCAL YEAR 2022-23 FUNDED BY SB 1: THE ROAD
REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017
(Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the
Governor in April 2017 in order to address the significant multi -modal transportation funding
shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will
ensure the residents of the City are aware of the projects proposed for funding in our
community and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt by resolution a list of all projects proposed to receive
fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created
by SB 1, which must include a description and the location of each proposed project, a
proposed schedule for the project's completion, and the estimated useful life of the
improvement; and
WHEREAS, the City will receive an estimated $1,823,778 in RMRA funding in Fiscal
Year 2022-23 from SB 1; and
WHEREAS, this is the sixth year in which the City is receiving SB 1 funding and will
enable the City to continue essential road maintenance and rehabilitation projects, safety
improvements, repairing and replacing aging bridges, and increasing access and mobility
options for the traveling public that would not have otherwise been possible without SB 1;
and
WHEREAS, the City uses a Pavement Management Plan (PMP) and Capital
Improvement Program to develop the SB 1 project list to ensure revenues are being used
on the most high-priority and cost-effective projects that also meet priorities for
transportation investment; and
WHEREAS, the funding from SB1 will enable the City to rehabilitate 1.4 miles of
roadway this fiscal year; and
WHEREAS, the 2020 California Statewide Local Streets and Roads Needs
Assessment found that the City's streets and roads are in good condition and this revenue
will help us maintain the current condition over the next decade; and
WHEREAS, the City's PMP has been developed to assist City personnel by providing
current data on the City's street network and to develop cost-effective maintenance
DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
strategies to maintain a desirable level of pavement performance on a network scale, while
optimizing the expenditure of limited fiscal resources; and
WHEREAS, the City's weighted pavement condition index (PCI) for the entire
network is 84.8; and
WHEREAS, system sustainability can only be achieved through proactive scheduling
and the implementation of cost-efficient pavement applications; and
WHEREAS, restoring roads before they fail reduces construction costs and
successive years of collecting pavement condition data has shown that it is far more
economical to preserve roads than to delay repairs; and
WHEREAS, the SB 1 project list and overall investment in our local streets and roads
infrastructure with a focus on basic maintenance and safety, investing in complete streets
infrastructure, and using cutting-edge technology, materials and practices, will have
significant positive co -benefits statewide.
NOW, THEREFORE, BE IT RESOLVED that:
1. The foregoing recitals are true and correct; and
2. The previously approved and adopted projects on the attached Exhibit A may utilize
Fiscal Year 2022-23 Road Maintenance and Rehabilitation Account revenues in
their delivery. With the re -listing of these projects in the adopted fiscal year
resolution, the City is reaffirming to the public and the State its intent to fund these
projects with Road Maintenance and Rehabilitation Account revenues.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin
held on the 7t" day of June 2022.
AUSTIN LUMBARD,
Mayor
ATTEST:
CARRIE WOODWARD
Acting City Clerk
Resolution 22-31
Page 2 of 3
DocuSign Envelope ID: 79268796-7620-44CD-A6D2-5682707D1ADA
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS
CITY OF TUSTIN 1
I, Carrie Woodward, Acting City Clerk and ex -officio Clerk of the City Council of the City of
Tustin, California, do hereby certify that the whole number of the members of the City
Council of the City of Tustin is five; that the above and foregoing Resolution No. 22-31 was
duly passed and adopted at a regular meeting of the Tustin City Council, held on the 7t" day
of June 2022, by the following vote:
COUNCILMEMBER AYES:
COUNCILMEMBER NOES:
COUNCILMEMBER ABSTAINED:
COUNCILMEMBER ABSENT:
CARRIE WOODWARD
Acting City Clerk
Resolution 22-31
Page 3 of 3
DocuSign Envelope ID: 79268798-7820-44CD-A6D2-5682707D1ADA
Exhibit A
City of Tustin
Senate Bill (SB) 1 Local Streets and Roads Program List of Previously Approved / Re -listed Projects for FY 2022-23
Project Title
Project Type
Description
Location
Components
Priority
Est Start
Est
Est
State
State
Est Total
Status
Completion
Useful
Assembly
Senate
Project
Life
District
District
Cost
Newport Avenue
Road
Repave/resurface 0.63 miles of road, including localized
Sycamore
Construction
In Progress
06/2022
12/2022
20-30
68
37
$800,000
Rehabilitation
Maintenance &
removal and repair of asphalt concrete pavement failure areas,
Avenue to
21/22
Rehabilitation
repair of sidewalk and curb & gutter, reconstruction of curb
Interstate 5
ramps to be ADA compliant, cold plane existing asphalt,
Freeway
construction of asphalt concrete overlay, traffic signal detector
loops, and traffic striping.
Newport Avenue
Road
Repave/resurface 0.80 miles of road, including localized
Interstate 5
Construction
In Progress
06/2022
12/2022
20-30
68
37
$1,100,000
Rehabilitation
Maintenance &
removal and repair of asphalt concrete pavement failure areas,
Freeway to
21/22
Rehabilitation
repair of sidewalk and curb & gutter, reconstruction of curb
Holt Avenue
ramps to be ADA compliant, cold plane existing asphalt,
construction of asphalt concrete overlay, traffic signal detector
loops, and traffic striping.
Red Hill Avenue
Road
Repave/resurface 0.60 miles of road, including localized
San Juan St.
Pre-
Forecasted
07/2022
12/2022
20-30
68
37
$1,100,000
01/2023
12/2023
Rehabilitation
Maintenance &
removal and repair of asphalt concrete pavement failure areas,
to Melvin Way
Construction
22/23
Rehabilitation
repair of sidewalk and curb & gutter, reconstruction of curb
and
ramps to be ADA compliant, cold plane existing asphalt,
Construction
construction of asphalt concrete overlay, traffic signal detector
loops, installation of a pedestrian hybrid beacon (PHB) system
at the Olwyn Drive crosswalk, and traffic striping.
Red Hill Avenue
Road
Repave/resurface 0.47 miles of road, including localized
Walnut Ave. to
Pre-
Forecasted
01/2023
06/2023
20-30
68
37
$550,000
Rehabilitation
Maintenance &
removal and repair of asphalt concrete pavement failure areas,
Interstate 5
Construction
22/23
07/2023
06/2024
Rehabilitation
repair of sidewalk and curb & gutter, reconstruction of curb
Freeway
and
ramps to be ADA compliant, cold plane existing asphalt,
Construction
construction of asphalt concrete overlay, traffic signal detector
loops, and traffic striping.
Jamboree Road
Road
Repave/resurface 1.6 miles of road, including localized
Barranca
Pre-
Forecasted
07/2025
12/2025
20-30
68
37
$1,300,000
Rehabilitation
Maintenance &
removal and repair of asphalt concrete pavement failure areas,
Parkway to
Construction
25/26
01/2026
12/2026
Rehabilitation
repair of sidewalk and curb & gutter, reconstruction of curb
SCRRA
and
ramps to be ADA compliant, cold plane existing asphalt,
Railroad
Construction
construction of asphalt concrete overlay, traffic signal detector
loops, and traffic striping.