HomeMy WebLinkAboutITEM 15 - SOUTH HANGAR RENOVATIONSouth Hangar
Renovation
CIP 10076
November 15, 2022
Project Scope –Structural
2
Remove 2 center stairs, support 2 stairs on either end Repair spilt gussets in trusses Repair end splits in trusses
•Other:
•Eliminate access to catwalks
•Repair long splits in trusses
•Repair damaged bridging
•Tighten all angle clamps and bolts
Project Scope –Base Electrical
3
•New transformer with 480V service
•Power equipment & distribution throughout hangar
•Power to west hangar doors
•Interior lighting and exterior security lighting
•AT&T communications
•Sidewalk/street work
Interior photometric
Exterior photometric
SCE approved design
At Completion
•Permanent power for hangar (including doors)
•Permanent interior/exterior lighting
•Every truss bolt/anchor/clamp inspected, repaired, replaced or tightened
•Safety repairs
Result: Increased safety and ability for additional temporary events & filming!
4
Tentative Schedule
•Prepare bid documents & specs: November 2022
•Council approval of bid package: November 15, 2022*
•Bid release: January 2023
•Construction start : April 2023
•Construction: 12 months
5
*Request supplemental appropriation
Thank You!