HomeMy WebLinkAbout06 ADOPT RESO TO ACCEPT IMPROVEMENTS FOR TUSTIN LEGACY NEIGHBORHOOD D SOUTHDocuSign Envelope ID: 63A42991 -01 B5-4C3D-A20E-28CA97933E8E
Agenda Item 6
dlw% UA AC3 E N REPUM Reviewed: D Sw
City Manager DS
1W Finance Director
MEETING DATE: JULY 18, 2023
TO: MATTHEW S. WEST, CITY MANAGER
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: ADOPT RESOLUTION NO. 23-37 TO ACCEPT IMPROVEMENTS FOR THE
TUSTIN LEGACY NEIGHBORHOOD "D" SOUTH PHASE 1 INFRASTRUCTURE
BACKBONE (CIP NO. 70246) AND NON -BACKBONE (CIP NO. 70250)
CONSTRUCTION PROJECT, AND AUTHORIZE THE CITY ENGINEER TO FILE
A NOTICE OF COMPLETION
SUMMARY
Construction of the Tustin -Legacy Neighborhood "D" South Phase 1 Infrastructure Backbone (CIP
No. 70246) and Non -Backbone (CIP No. 70250) Construction Project has been completed by
R.J. Noble Company to the satisfaction of the City Engineer and is now ready for City Council
acceptance.
RECOMMENDATION
It is recommended that the City Council take the following actions:
Adopt Resolution No. 23-37 accepting the construction of the Tustin -Legacy
Neighborhood "D" South Phase 1 Infrastructure Backbone (CIP No. 70246) and Non -
Backbone (CIP No. 70250) Construction Project, and
2. Authorize the City Engineer to execute and file the Notice of Completion with the Orange
County Recorder's Office.
FISCAL IMPACT
The final construction cost for The Tustin -Legacy Neighborhood "D" South Phase 1 Infrastructure
Backbone (CIP No. 70246) and Non -Backbone (CIP No. 70250) Construction Project is
$12,830,180.55, including authorized contract change orders. The contract change orders are
comprised of miscellaneous field modifications and final quantity adjustments. Sufficient funds
were budgeted and appropriated in the Capital Improvement Program in the total amount of
$13,500,000.00.
CORRELATION TO THE STRATEGIC PLAN
The construction of the N-D South Phase 1 Infrastructure Improvements Project contributes to
the fulfillment of the City's Strategic Plan Goal A: Economic and Neighborhood Development;
specifically, implementation of Strategy #1 which, among other items, is to develop critical phases
of Tustin Legacy.
DocuSign Envelope ID: 63A42991 -01 B5-4C3D-A20E-28CA97933E8E
Notice of Completion for N-D South Phase 1 Improvements Project, CIP No. 70246 & 70250
July 18, 2023
Page 2
DISCUSSION
Can March 10, 2020 bids were opened for this construction project. Due to continued ongoing
negotiations with Brookfield Homes Southern California LLC ("Brookfield") regarding residential
development on several parcels within Neighborhood "Y South, authorization of the award of the
construction contract to R.J. Noble Company by the City Council was delayed until November 17,
2020, with the Notice to Proceed issued on March 1, 2021.
The infrastructure construction of Neighborhood "D" South Phase 1 is within the area generally
bounded by Tustin Ranch Road, Warner Avenue, Barranca Parkway and Armstrong Avenue, and
consisted of clearing and grubbing, grading, construction of storm drain, water, reclaimed water,
sanitary sewer, dry utility work, roadway improvements and traffic signals installation including a
new signalized entry into The District parking lot from Tustin Ranch Road and a new median on
Tustin Ranch Road. Several infrastructure construction milestone dates were set forth in the
Disposition and Development Agreement with Brookfield including wet utilities completion in Flight
Way, Southern California Edison inspection completion, and Flight Way to be open to traffic. All
work was accomplished before the required agreed -upon deadlines.
'Stack, P.E.
Public Works/City Engineer
Attachment(s):
1. Resolution No. 23-37
2. Location Map
DocuSign Envelope ID: 63A42991 -01 B5-4C3D-A20E-28CA97933E8E
ATTACHMENT 1
Resolution 23-37
DocuSign Envelope ID: 63A42991-01B5-4C3D-A20E-28CA97933E8E
RESOLUTION NO. 23-37
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING THE WORKS OF IMPROVEMENT AND
AUTHORIZING THE RECORDATION OF THE NOTICE OF
COMPLETION FOR THE TUSTIN LEGACY NEIGHBORHOOD "D"
SOUTH PHASE 1 INFRASTRUCTURE BACKBONE (CIP NO. 70246)
AND NON -BACKBONE (CIP NO. 70250) CONSTRUCTION PROJECT
WHEREAS, R.J. Noble Company, having a contract with the City of Tustin to
construct the hereinafter described public works and improvement; and
WHEREAS, the City Engineer has duly certified to the construction and
completion of said public improvement hereinafter mentioned in a manner satisfactory
to the City Council of the City of Tustin; and
WHEREAS, the City Council finds that said contractor has completed said public
improvement hereinafter more particularly described in accordance with the provisions
of the contract documents and the Notice of Completion, and acceptance of said public
works and improvement should be filed and payment of the balance due said contract
authorized in accordance with the contract documents;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Tustin
that said public works and improvement is found to be complete, and the same is
hereby accepted. Said public works and improvement is more particularly described as
follows:
Tustin -Legacy Neighborhood "D" South Phase 1 Infrastructure Backbone
(CIP No. 70246) and Non -Backbone (CIP No. 70250) Construction Project
BE IT FURTHER RESOLVED that the City Engineer of the City of Tustin is
hereby authorized to execute and file a Notice of Completion for the acceptance of said
public works and improvement described herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of
Tustin held on the 18t" day of July, 2023.
AUSTIN LUMBARD, Mayor
ATTEST:
ERICA N. YASUDA
City Clerk
DocuSign Envelope ID: 63A42991-01B5-4C3D-A20E-28CA97933E8E
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS
CITY OF TUSTIN )
I, ERICA N. YASUDA, City Clerk and ex-officio Clerk of the City Council of the City of
Tustin, California, do hereby certify that the whole number of the members of the City
Council is five; that the above and foregoing Resolution No. 23-37 was duly and
regularly passed and adopted at a regular meeting of the City Council held on the 18tn
day of July, 2023 by the following vote:
COUNCILMEMBER AYES:
COUNCILMEMBER NOES:
COUNCILMEMBER ABSTAINED:
COUNCILMEMBER ABSENT:
ERICA N. YASUDA,
City Clerk
DocuSign Envelope ID: 63A42991 -01 B5-4C3D-A20E-28CA97933E8E
ATTACHMENT 2
Location Map
DocuSign Envelope ID: 63A42991-01B5-4C3D-A20E-28CA97933E8E
LOCATION MAP
Tustin Legacy Neighborhood D
Phase 1 Infrastructure
Backbone and Non-Backbc
Construction Project
TUSTIN
LEGACY
PROJECT LOCATION
Tustin Legacy Neighborhood
D South Phase 1 Infrastructure
Backbone (CIP No. 70246)
and Non -Backbone
(CIP No. 70250) Construction
Project
FILE: Neighborhood D South 70246 & 70250.dwg
TUSTIN
RANCH
PROJECT
LOCATION
6,q\
r�
NO SCALE