AGENDA REPORt
MEETING DATE: NOVEMBER 7, 2023
TO: NICOLE BERNARD, ACTING CITY MANAGER
Agenda Item
Reviewed: E
City Manager
Finance Director
FROM: MICHAEL GRISSO, ACTING DIRECTOR OF PUBLIC WORKS
SUBJECT: AWARD CONTRACT FOR THE TUSTIN LEGACY NEIGHBORHOOD "D" SOUTH
PHASE 2 INFRASTRUCTURE (CIP NO. 70256) CONSTRUCTION PROJECT -
PACKAGE #1 AND THE CIVIL PORTION OF THE WORK FOR THE SOUTH
HANGAR RENOVATION (CIP NO. 10076)
SUMMARY
Staff is requesting the City Council award a construction contract to the lowest
responsive/responsible bidder for the Tustin Legacy Neighborhood "D" South Phase 2 Infrastructure
(CI P No. 70256) Construction Project - Package #1 and the civil portion of the work for South Hangar
Renovation (CIP No. 10076) to Boudreau Pipeline Corporation ("Boudreau").
This project involves construction elements associated with five projects in the City's Capital
Improvement Program that are required to advance construction of Neighborhood D South, Tustin
Legacy Park from Armstrong Avenue to Warner Avenue and future pedestrian bridges over
Armstrong and Warner Avenue.
RECOMMENDATION
It is recommended that the City Council:
Award a construction contract in the amount of $8,771,596, for the Tustin Legacy
Neighborhood "D" South Phase 2 Infrastructure (CIP No. 70256) Construction Project -
Package #1 and the civil portion of the work for South Hangar Renovation (CIP No. 10076)
to Boudreau Pipeline Corporation as the lowest responsive and responsible bidder, and
authorize the Mayor and the City Clerk to execute the contract documents on behalf of the
City;
2. Appropriate $3,500,000 from Land Sale Proceeds Fund (Fund 189) for the Neighborhood D
South Phase 2 Improvements Project (CIP 70256);
3. Appropriate $550,000 from the Backbone Program Fund (Fund 187) for the Armstrong
Avenue Pedestrian Bridge Improvements Project (CIP 70257); and
4. Appropriate $520,000 from the Backbone Program Fund (Fund 187) for the Warner Avenue
Pedestrian Bridge Improvements Project (CIP 70260).
FISCAL IMPACT
This project involves construction elements that benefit five projects in the City's Capital
Improvement Program (Neighborhood D South Phase 2 Improvements, South Hangar Renovation,
Armstrong Avenue Pedestrian Bridge, Warner Avenue Pedestrian Bridge, and Tustin Legacy Park
from Armstrong Avenue to Warner Avenue). The table below summarizes the approved project
budget for each element of the five projects, and the construction bid item costs that have been
DocuSign Envelope ID: 6EA22186-1 F25-4BFA-9167-587106976A9F
Award Contract
November 7, 2023
Page 2
evaluated and assigned to each project inclusive of a 10% project contingency, SCE fees, IRWD
fees, and engineering and geotechnical support. Total project cost is estimated at $10,000,000.
Project
D South Phase 2
Construction
Budget
$4,000,000
Construction
Bid
$6,561,970
ContingencyAppropriation
. Related
Project Costs
$918,960
Total Cost
$7,480,930
Request
(Rounded)
$3,500,000
South Hangar
$5,421,683
$240,825
$33,726
$274,551
$0
Armstron Bride
$674,849
$1,071,487
$150,055
$1,221,541
$550,000
Warner Bride
$250,000
$671,324
$94,015
$765,339
$520,000
Tustin Legacy Park
$1,000,000
$225,991
$31,648
$257,639
$0
TOTAL
$11,346,532
$8,771,596
$1,228,404
$10,000,000
$4,570,000
As indicated above, sufficient budget funds exist for the portion of civil work that is part of the South
Hangar Renovation and Tustin Legacy Park from Armstrong Avenue to Warner Avenue projects.
The other three projects do not have sufficient funding in FY 2023-24 and will require additional
appropriations. The Backbone Program Fund (Fund 187) and Land Sale Proceeds Fund (Fund 189)
have sufficient fund balances to support these appropriation requests.
CORRELATION TO THE STRATEGIC PLAN
The Tustin Legacy Neighborhood "D" South Phase 2 Infrastructure (CIP No. 70256) Construction
Project — Package #1 and the civil portion of the work for South Hangar Renovation (CIP No. 10076)
project contributes to the fulfillment of the City's Strategy Plan Goal A: Economic and Neighborhood
Development. Specifically, the project implementation of Strategy 1, which among other items, is to
develop critical phases of Tustin Legacy.
The civil portion of the work for the South Hangar Renovation project also contributes to fulfilling
Goal B: Public Safety and Protection of Assets, specifically the project implementation of Strategy
5, which is to create and implement a plan to protect the City's public assets.
DISCUSSION
The infrastructure construction of the Tustin Legacy Neighborhood "D" South Phase 2 — Package #1
in the area generally bounded by Airship Avenue, Warner Avenue, Compass Avenue and Armstrong
Avenue, consists of clearing and grubbing, grading, future pedestrian bridge surcharge mounding,
construction of storm drain, water, reclaimed water, sanitary sewer and roadway improvements.
Formal bids were submitted electronically, publicly opened on October 3, 2023 and reviewed by
Public Works. Out of ten contractors that obtained bid packages, only two submitted bids. Follow-
up discussion with a few contractors that did not submit bids generally revealed that non -participation
was due to current heavy workloads of contractors coupled with the amount of available work
throughout the construction industry. The two bids received are summarized below:
• Boudreau Pipeline Corporation..................................................................$ 8,771,596.00
• Nationwide Contracting Services, Inc. DBA Nationwide General Construction Services
.........................................................................................$ 11,989,223.35
Staff worked with the design engineer on the engineer's estimate using the contract prices from the
Neighborhood D South Phase 1 Infrastructure Construction Project including an inflation escalation.
Still, unit prices were higher across the board: 30% higher on grading, 80% higher on street
preparation improvements, and 120% higher on wet utility work. Although bid prices are higher than
DocuSign Envelope ID: 6EA22186-1 F25-4BFA-9167-587106976A9F
Award Contract
November 7, 2023
Page 3
anticipated, considering the competitive and busy construction environment, increased inflation, and
the priority in delivering ready to develop parcels, as well as the next phase of the Tustin Legacy
Park, staff recommends awarding this project to Boudreau as re -bidding is unlikely to provide more
favorable bid results and will cause significant delays in advancing the work. Staff has reviewed the
references, the State Contractor's License, and registration with the Department of Industrial
Relations for Boudreau and has determined that they are appropriate for the subject project.
Staff is recommending that the City Council award the construction contract for the Tustin Legacy
Neighborhood "Y South Phase 2 Infrastructure (CIP No. 70256) Construction Project — Package #1
and the civil portion of the work for South Hangar Renovation (CIP No. 10076) to Boudreau as the
lowest responsive/responsible bidder, and authorize the Mayor and the City Clerk to execute the
contract documents on behalf of the City.
DocuSigned by:
E
l Gvissb
C2CSD60ESFD34CC...
Michael Grisso
Acting Director of Public Works
Attachment: Location Map
IDocuSigned by:
6,I�,v br(ttr �asfzv
A71E3BA15004414...
Christopher Koster
Director of Economic Development
DocuSign Envelope ID: 6EA22186-1F25-4BFA-9167-587106976A9F
LOCATION MAP
Tustin Legacy Neighborhood D South
Phase 2 Infrastructure
f Construction Project
�p
E
4
.t
c � TusnN
RANCH
TUSTIN
LEGACY
Rl v
NO SCALE
P
PROJECT E T LOCATION
°F P�
Tustin Legacy Neighborhood PROJECT
D South Phase 2 Infrastructure LOCATION
Construction Project �� R AVfNUf
(CIP No. 70256)
10
Z
0
FPO
G
9y
o� TUSTIN RANCH ROAD
0
P
PARK
UE
a P��?J e9Pn ci� AVEN_
FILE: Neighborhood D South 70256.dwg