AGENDA REPORT
Agenda Item 12
Reviewed:
City Manager
Finance Director
MEETING DATE: NOVEMBER 20, 2006
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AMENDMENT NO.1 TO CONSULTANT SERVICES AGREEMENT WITH JACOBS
CIVIL, INC. FOR CONSTRUCTION OVERSIGHT AND INSPECTION SERVICES
FOR PHASES II, III, AND IV OF THE DISTRICT (VESTARlKIMCO TUSTIN) OFF-
SITE BACKBONE INFRASTRUCTURE AT TUSTIN LEGACY
SUMMARY
Amendment No. 1 to Consultant Services Agreement between the City and Jacobs Civil Inc. will
provide construction oversight and inspection services for construction of Phases II, III, and IV of The
District (Vestar/Kimco Tustin) Off-Site Backbone Infrastructure at Tustin Legacy.
RECOMMENDATION
It is recommended that the City Council approve Amendment No. 1 to Consultant Services Agreement
with Jacobs Civil, Inc. to provide construction oversight and inspection services for construction of
Phases II, III, and IV of The District Off-Site Backbone Infrastructure at Tustin Legacy, and authorize
the Mayor and City Clerk to execute the Amendment on behalf of the City.
It is also recommended that the City Council appropriate $93,000 from the Tustin Legacy
Redevelopment Agency Fund to CIP No. 7169 (The District at Tustin Legacy) for the construction
oversight services on these projects.
FISCAL IMPACT
Pursuant to the Infrastructure Construction and Payment Agreement between the City of Tustin and the
Developer, Vestar/Kimco Tustin, inspection services for the construction of the backbone infrastructure
will be funded through fees collected from the Developer. Inspection services for these phases are
estimated to be $721,000 and were included in the backbone infrastructure cost estimates prepared for
the District Project. Construction oversight services are estimated to be $93,000. The cost for
construction oversight services is about 1 % of the low bid for construction of Phases II, III, and IV of
The District Off-Site Backbone Infrastructure. Cost for construction oversight services will be funded
from the Tustin Legacy Redevelopment Agency funds through an appropriation to CIP No. 7169 (The
District at Tustin Legacy).
BACKGROUND
Phase II of the proposed project involves construction of streets, storm drain systems, traffic signals,
parkways, and sidewalks that are backbone infrastructure improvements on Barranca Parkway
between Tustin Ranch Road and Jamboree Road. Phase III of the proposed project involves
construction of dry utilities on Tustin Ranch Road between Barranca Parkway and Warner Avenue,
Warner Avenue between Tustin Ranch Road and Park Avenue, and Park Avenue between Warner
Avenue and Tustin Ranch Road. Phase IV of the proposed project involves landscape improvements
on Tustin Ranch Road between Barranca Parkway and Warner Avenue, Warner Avenue between
Tustin Ranch Road and Park Avenue, Park Avenue between Warner Avenue and Tustin Ranch Road,
and a portion of North Loop Road between Warner Avenue and the Jamboree RoadlWarner Avenue
ramp.
Consultant Services Agreement for Construction Oversight and Inspection Services for Phases II, III,
and IV of The District (Vestar/Kimco) Off-Site Backbone Infrastructure at Tustin Legacy
November 20, 2006
Page 2
DISCUSSION
Construction of these projects will require the services of a Construction Oversight Manager and
multiple inspectors for support. In addition, the construction oversight team will include staff to perform
cost analysis functions, scheduling, quality control, and safety activities.
The Developer has retained Bayley Slater, a Construction Management Company, to manage their
interests in the project. Since the project involves reimbursement of funds for the construction of public
facilities, the City needs to provide a level of oversight and control of the construction activity and
related costs. The contract Construction Oversight Manager and contract Inspector will be responsible
for overseeing the construction to ensure that the project is constructed per City standards and in
conformance with the "Infrastructure Construction and Payment Agreement" between Vestar/Kimco
Tustin L.P. and the City, approved by the City Council on March 21, 2005. The contract Construction
Oversight Manager will coordinate the construction activities of all aspects of the project under the
oversight of the Public Works Department's Engineering Division.
Jacobs Civil, Inc. is currently providing construction oversight and inspection services for construction
of Phase I of The District. Based upon evaluation and their performance on the Phase I, staff
recommended continuing Jacobs Civil, Inc. services for Phases II, III, and IV of The District projects.
The proposal and cost estimate submitted by Jacobs Civil, Inc. includes separate itemizations for
construction oversight and inspection services. All personnel assigned to this project by Jacobs Civil,
Inc. will be compensated on an hourly basis for providing these services. The number of person-hours
proposed by Jacobs Civil, Inc. is reasonable for the complexity and magnitude of this project.
It is recommended that the City Council approve the Amendment No. 1 to Consulting Services
Agreement with Jacobs Civil, Inc. for construction oversight and inspection services on Phases II, III,
and IV of The District Off-Site Backbone Infrastructure at Tustin Legacy.
Tim D. Serlet
Director of Public Works/City Engineer
Doug Anderson
Transportation and Development Services
Manager
Attachment: Amendm'ent No. 1 to Consultant Services Agreement
S:\City Councilltems\2006 Councilltems\Approval of Amendment No.1 with Jacobs - The District.doc
AMENDMENT NO.1
TO
CONSULTANT SERVICES AGREEMENT
THIS AMENDMENT NO. 1 TO CONSULTANT SERVICES AGREEMENT
("Amendment No.1") is made and entered into this day of , 2006,
by and between the CITY OF TUSTIN, a municipal corporation, hereinafter referred to
as "City", and JACOBS CIVIL, INC. a Missouri corporation, hereinafter referred to as
"Consultant."
RECITALS
WHEREAS, City and Consultant entered into the Consultant Services Agreement
as of February 21, 2006, (the "Agreement") for construction oversight and inspection
services for construction of Phase I of The District (Vestar/Kimco Tustin) Off-Site
Backbone Infrastructure at Tustin; and
WHEREAS, City and Consultant desire to amend Section 1 and Section 4 of the
Agreement to include additional construction oversight and inspection services for
construction of Phases II, III, and IV of The District (Vestar/Kimco Tustin) Off-Site
Backbone Infrastructure at Tustin.
NOW, THEREFORE, in consideration of the mutual promises, covenants, and
conditions contained herein, and upon the terms and conditions hereinafter set forth, the
parties agree as follows:
AGREEMENT
1. Section 1. Scope of Consultant's Services, of the Agreement is hereby
amended in its entirety to read as follows:
Consultant shall perform all work necessary to complete in a
manner satisfactory to City, the services set forth in Exhibit "A", Phase I of
The District (Vestar/Kimco Tustin) Off-Site Backbone Infrastructure at
Tustin Legacy in accordance with the terms and conditions of this
Agreement.
1
Consultant shall perform all work necessary to complete in a
manner satisfactory to City, the services set forth in Exhibit liB", Phases II,
III, and IV of The District (Vestar/Kimco Tustin) Off-Site Backbone
Infrastruture at Tustin Legacy in accordance with the terms and conditions
of this Agreement.
2. Section 4. Compensation, of the Agreement is hereby amended in its entirety
to read as follows:
A. The compensation to be paid under this Agreement shall be
as set forth in Exhibit "A", Phase I of The District
(Vestar/Kimco Tustin) Off-Site Backbone Infrastructure at
Tustin Legacy, which shall not exceed a total cost of
$1.746.377.00.
B. The compensation to be paid under this Agreement shall be
as set forth in Exhibit liB", Phases II, III, and IV of The District
(Vestar/Kimco Tustin) Off-Site Backbone Infrastructure at
Tustin Legacy, which shall not exceed a total cost of
$814.000.00.
C. Consultant shall submit detailed invoices, based upon the
actual work performed, accompanied by backup
documentation as requested by the City.
D. Progress payments for work completed shall be paid by the
City as the work progresses, within thirty (30) days of receipt
of Consultant's invoice.
E. Consultant shall provide City with a monthly itemization of all
work performed, and the fees accrued thereon, in complete
and sufficient detail to fully apprise City thereof.
F. City shall notify Consultant within ten (10) business days
after receipt of an invoice if it disputes all or some element of
the invoice. City and Consultant shall promptly attempt to
effect a resolution of any dispute. Not withstanding the
foregoing, City shall pay the undisputed portion of any
invoice.
3. Except as expressly amended herein, all other provisions of the Agreement
remain in full force and effect.
2
IN WITNESS WHEREOF, this Amendment NO.1 was executed by the parties on the
day and year written above.
"CITY"
CITY OF TUSTIN
Doug Davert, Mayor
ATTEST:
Pamela Stoker, City Clerk
APPROVED AS TO FORM:
Douglas C. Holland, City Attorney
"CONSULTANT"
JACOBS CIVIL, INC.
Sherry Sweitzer, Vice President
S:\CSA & RFP\2006\Amend # 1 CSA Jacobs,doc
3
5757 Plaza Drive, Suite 100
Cypress, California 90630 U.S.A.
1.714-503-3400 Fax 1.714-503-3999
EXHIBIT "B"
To:
City of Tustin
300 Centennial Way
Tustin, CA 92780-8991
Date: October 19,2006
Attention:
Mr. Douglas Anderson
Project:
Subject:
City of Tustin, The District
Bid Package Two, Three and Four Professional Services for Inspection and
Oversight Proposal
Dear Doug,
Thank you for asking Jacobs to propose on professional services for Bid Packages Two, Three
and Four.
This is in response to your request for Jacobs to provide separate pricing for inspection and
oversight professional services for Bid Packages 2 Barranca Road Improvements (Serna), Bid
Package 3 Dry Utilities (Team Fischel) and Bid Package 4 Landscaping (TBD). In our earlier
August 22, 2008 transmittal we listed inspection and oversight costs which were based on using a
portion of our BP I initial budget. After discussions with Benny Tenkean we have based our
proposed pricing on stand alone packages using the same basic inspection and oversight hourly
costs with similar services provided for approximately 4% of the construction value of each
package.
The proposed estimates pending your approval for BP 2, 3 and 4 are as follows.
Bid Package 02 Barranca Parkway (Serna)
Oversight '
Inspection
Subtotal
$65,137.80
$425,862.20
$491,000.00
Bid Package 03 Dry Utilities (Team Fischel)
Oversight
Inspection
Subtotal
$18,610.80
$162,389.20
$181,000.00
Bid Package 04 Landscaping (tbd)
Oversight
Inspection
Subtotal
$9,631.60
$132,368.40
$142,000.00
Total for Bid Packages 2,3 and 4
$814,000.00
Jacobs Engineering Group Inc.
Page 1 of 2
JACOBS
The attached schedule lists the staffing and expected durations at this time for the three packages
listed above. This work wilJ be billed on a time and material basis the same as we do for our base
BP 01 contract.
The BP 02 contract calls for 300 work days and NTP was issued on August 3, 2006. Completion
is scheduled for May 30, 2007. Our attached staffing plan shows our work beginning in August
2006 and completing in September 2007.
The BP 03 contract calls for 210 work days and NTP was issued on September 25,2006.
Completion is scheduled for April 23, 2007. The attached staffing plan shows our work
beginning in October 2006 and completing in December 2007.
The BP 04 contract calls for 180 work days and NTP is expected to be issued November 6, 2006
with work completing May 5, 2007. The attached staffing plan shows our work beginning in
October 2006 and completing in December 2007.
We appreciate this opportunity to be of service to you and the City of Tustin. Please call me at
619-261-0687 if you have any questions or need anything further.
Bill Zondorak
Project Manager
Enc1: BP 2, 3, 4 Cost Spreadsheet
cc: :file, Matt Van Gorp, Benny Tenkean, Hank Alonso, Robert Turner
Page 2 of2